CONSTRUCTION OF MODUNAGHAT WATER TREATMENT PLANT & PATENGA BOOSTER PUMP STATION (CWSISP/W-1)

Casting Schedule for July 2016

Structure Name Structural Part Casting Date Concrete Remarks


Quantity (Cum)
Floculator Base (Road Side),+1.2 11-May-16 302
Level
Floculator Middle wall (River 15-May-16 95
Side),+1.2 Level
Floculator Slope wall (River Side), 15-May-16 200
+1.2 Level
Floculator Middle wall (Road 19-Jun-16 95
Side),+1.2 Level
Floculator Slope wall (Road Side), 19-Jun-16 200
+1.2 Level
Clarifier
Floculator North wall (Road 29-May-16 95
Side),+1.2 Level

Receiving Well Base,+2.7 Level 20-May-16 15

Receiving Well Base,+3.35 Level 20-May-16 120

Clarifier Base at +4.70 Level 12-Jun-16 360


(River side)
Clarifier Base at +4.70 Level 20-Jul-16 250
(Road side)

Base Casting,Zone-2 (Road side) 22-May-16 324


Rapid Sand Filter
Base Casting,Zone-1(Road side) 25-Jun-16 534

Wall Casting +3.7 to +4.7 27-May-16 62


Back Wash Wast Tank
Wall Casting +4.7 to +6.5 29-Jun-16 112

Wall Casting +1.4 to +3.5 (River 29-Apr-16 90


Side)

Pump House Wall Casting +1.4 to +3.5 (Road 30-Apr-16 110


Side)

Wall Casting +3.5 to +5.6 3-Jul-16 200

10 May 2016 to
Levelling Concrete 70
10 June 2016
Dewatering Building
20 May 2016 to
Base Casting 300
20 July 2016