RENCANA ANGGARAN BIAYA (RAB)

BAHAN DAN BIAYA

HARGA SATUAN JUMLAH HARGA KETERANG


NO URAIAN KUANTITAS SATUAN
(Rp.) (Rp.) AN
1 2 3 4 5 6 7

I. BAJA RINGAN
I.I Kuda-Kuda (Bahan Canal)
1. Kuda-kuda type 1 (11 Unit)
- Canal C-80 354.37 M' 16,666.67 5,906,166.67
2. Kuda-kuda type 2 (01 Unit)
- Canal C-80 20.93 M' 16,666.67 348,833.33

3. Kuda-kuda type 3 (04 Unit)


- Canal C-80 42.40 M' 16,666.67 706,666.67
JUMLAH I.I 417.70 M' 6,961,666.67
69.62 Btg

I.II Reng (bahan Reng Baja Ringan)


1. Reng Type 1 (28 btg)
- Reng R-37 456.00 M' 8,333.33 3,800,000.00
2. Reng Type 2 (16 btg)
- Reng R-37 45.80 M' 8,333.33 381,666.67
3. Reng Type 3 (09 btg)
- Reng R-37 60.85 M' 8,333.33 507,083.33
JUMLAH I.II 562.65 M' 4,688,750.00
93.78 btg

II. BAHAN PENUTUP ATAP (MULTIROOF)


II.I Bahan Atap
1. Luas atap 1 (71,98 M2) 195.44 pcs 48,000.00 9,381,224.49
2. Luas atap 2 (7,53 M2) 20.50 pcs 48,000.00 983,771.43
3. Luas atap 3 (19,26 M2) 26.20 pcs 48,000.00 1,257,600.00
JUMLAH II.I 242.14 pcs 11,622,595.92
II.II Bubungan
4. Penutup Bubungan (p=1,1m) 17.32 pcs 35,000.00 606,136.36
JUMLAH II.II 17.32 pcs 606,136.36

TOTAL HARGA BAHAN 23,879,148.95