EXECUTIVE SUMMARY

PROJECT PEMATANGAN LAHAN PADAT VIBRO


DI KAWASAN ALAM SUTRA KEDATON

NO URAIAN HARGA
HARGA SATUAN PADAT VIBRO = Rp 60.000 /M3
VOLUME PEKERJAAN PERTAHUN = 3.283.200 M3
JUMLAH RITASE (VOLUME PEKERJAAN / KUBIKASI)
[ 3.283.200 /19M3] 172.800 RIT
NILAI PROJECT = Rp 196.992.000.000

ESTIMASI BIAYA PELAKSANAAN PEKERJAAN


HARGA TANAH = Rp 160.000
ONGKOS GENDONG = Rp 240.000
KOORDINASI WILAYAH DAN JALAN / LINGKUNGAN = Rp 240.000
BIAYA ALAT EKSCAVATOR / BEKO = Rp 100.000
BIAYA ALAT DOZER DAN VIBRO = Rp 200.000

TOTAL BIAYA PELAKSANAAN /RIT Rp 940.000


TOTAL BIAYA PELAKSANAAN KESELURUHAN 162.432.000.000
TOTAL LABA KOTOR ( NILAI PROJECT - BIAYA PELAKSANAAN)
34.560.000.000

MEKANISME PEMBAYARAN
INVOICE TIAP 14.400 RIT

ESTIMASI KEBUTUHAN MODAL


HARGA TANAH (14.400 X 160.000) 2.304.000.000
ONGKOS GENDONG (14400 X 240.000) 3.456.000.000
KOORDINASI WILAYAH DAN JALAN (14.400 X 240.000) 3.456.000.000
EXCAVATOR/ BEKO (14.400 X 100.000) 1.440.000.000
DOZER DAN VIBRO ( 14.400 X 200.000) 2.880.000.000

TOTAL KEBUTUHAN MODAL PER INVOICE 13.536.000.000

ESTIMASI VOLUME PEKERJAAN


JUMLAH ARMADA 40 UNIT
JUMLAH RITASE / HARI (12 X 40 UNIT) 480
JUMLAH RITASE / BULAN 14.400
JUMLAH RITASE / TAHUN 172.800

NOTE :
JENIS ARMADA DT INDEKS 22 - 24 M3
JARAK TEMPUH 9 KM PP
JUMLAH RITASE / UNIT DT / HARI 12 RIT /HARI