Anda di halaman 1dari 4

PT Bias petrasia persada

TABLE OF REQUEST FOR INSPECTION

Date
No. Inspection Item RFI No. Project Client Kontraktor Prepared by Approved by Item Work No. BA
Open Close
PT.BIAS PETRASIA
1 Pengukuran situasi untuk volume tanah 8-Jul-17 7-Aug-17 RFI-PLTM-C-0001 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI GIRI UTAMA Surveyor
PERSADA
PT.BIAS PETRASIA
2 Pengukuran situasi untuk Elevasi tanah keras 26-Jul-17 28-Jul-17 RFI-PLTM-C-0002 PLTM CICATIH PROJECT PT.KRAKATAU EN DHIMAS KUSUMA ADHI GIRI UTAMA Surveyor
PERSADA
Pemasangan Corrugated Pipe dengan panjang 171.000 PT.BIAS PETRASIA
3 27-Jul-17 21-Aug-17 RFI-PLTM-C-0003 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI GIRI UTAMA Installation Material
Meter PERSADA
PT.BIAS PETRASIA
4 Stake Out area Power House (Coordinate & Elevation ) 6-Aug-17 RFI-PLTM-C-0004 PLTM CICATIH PROJECT
PERSADA
PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI batal
PT.BIAS PETRASIA
5 Pengukuran Situasi untuk Galian Tanah ( Opname 1 ) 3-Aug-17 RFI-PLTM-C-0005 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI GIRI UTAMA Surveyor
PERSADA
PT.BIAS PETRASIA
6 Pengukuran elevasi & Coordinate Corrugated Pipe Temporary 21-Aug-17 29-Jul-17 RFI-PLTM-C-0006 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI GIRI UTAMA Surveyor
PERSADA
PT.BIAS PETRASIA
7 Pengukuran Situasi untuk Galian Tanah 20-Sep-17 22-Sep-17 RFI-PLTM-C-0007 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI GIRI UTAMA Surveyor
PERSADA
Pengukuran Situasi untuk Galian Tanah Total Area Slope
PT.BIAS PETRASIA
8 Head Pond ( sebelum Galian Head Pond ) dan Area Power 5-Oct-17 28-Sep-17 RFI-PLTM-C-0008 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI GIRI UTAMA Surveyor
PERSADA
House ( Opname 2 )
Pengukuran situasi tanah sebelum pelaksanaan galian PT.BIAS PETRASIA
9 7-Oct-17 09-Okt-17 RFI-PLTM-C-0009 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI GIRI UTAMA Surveyor
Headpond ( Kolam Penenang ) PERSADA
Pengukuran Situasi untuk Galian Tanah Total Area Head Pond PT.BIAS PETRASIA
10 31-Oct-17 RFI-PLTM-C-0010 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI Surveyor BA-010/BPP-KE/PLTM/2017
( Opname 3 ) PERSADA
PT.BIAS PETRASIA
11 Pengukuran elevasi & Coordinate actual saluran pengalih 16-Nov-17 16-Nov-17 RFI-PLTM-C-0011 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI GIRI UTAMA Surveyor BA-011/BPP-KE/PLTM/2017
PERSADA
PT.BIAS PETRASIA
12 Material Inspection Rebar D 16 Ulir & Rebar D 25 Ulir 21-Oct-17 RFI-PLTM-C-0012 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI Material On Site BA-012/BPP-KE/PLTM/2017
PERSADA
PT.BIAS PETRASIA
13 Material Inspection Rebar D 13 Ulir 22-Oct-17 RFI-PLTM-C-0013 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI Material On Site BA-013/BPP-KE/PLTM/2017
PERSADA
PT.BIAS PETRASIA
14 Material Inspection Rebar D 16 Ulir & D 19 Ulir 2-Nov-17 RFI-PLTM-C-0014 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI Material On Site BA-014/BPP-KE/PLTM/2017
PERSADA
PT.BIAS PETRASIA
15 Material Inspection Rebar D 16 Ulir 4-Nov-17 RFI-PLTM-C-0015 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI Material On Site BA-015/BPP-KE/PLTM/2017
PERSADA
PT.BIAS PETRASIA
16 Material Inspection Rebar D 19 Ulir 6-Nov-17 RFI-PLTM-C-0016 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI Material On Site BA-016/BPP-KE/PLTM/2017
PERSADA
PT.BIAS PETRASIA
17 Material Inspection Rebar D 16 Ulir & Rebar D 22 Ulir 7-Nov-17 RFI-PLTM-C-0017 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI Material On Site BA-017/BPP-KE/PLTM/2017
PERSADA

Pekerjaan Disposal tanah Ex. Galian Headpond ke Disposal


PT.BIAS PETRASIA
18 Area Bogorindo menggunakan Dump truck ( periode 09 30-Nov-17 RFI-PLTM-C-0018 PLTM CICATIH PROJECT PT.KRAKATAU ENG. DHIMAS KUSUMA ADHI Disposal Tanah BA-018/BPP-KE/PLTM/2017
PERSADA
Nov 2017 sd 30 Nov 2017 )
PT Bias petrasia
persada REQUEST FOR INSPECTION (RFI)

PROJECT : PLTM CICATIH PROJECT TANGGAL : 21 Oktober 2017

CLIENT : PT.BIAS PETRASIA PERSADA RFI NO. : RFI-PLTM-C-0012

KONTRAKTOR : PT. KRAKATAU ENGINEERING

INSPECTION ITEM :

Material Inspection Rebar D 16 Ulir & Rebar D 25 Ulir

Date : 21 Oktober 2017

Time : 09.00 wib

REFERENCE :
(Dwg,Spec,Prod Catalog,etc)

MILL'S CERTIFICATE
DATA SHEET OF MATERIAL

Remark :

PREPARED BY, APPROVED BY,


PT.KRAKATAU ENGINEERING PT. BIAS PETRASIA PERSADA

( Adhi Srie He rmanto ) ( Dhimas Kusuma Adhi Y.A )

Dhimasblackforest@gmail.com
PT Bias petrasia
persada

BERITA ACARA PEKERJAAN


BA-014/BPP-KE/PLTM/2017

Hari ini, Kamis 02 November 2017, antara PT. Krakatau Engineering dengan PT. Bias Petrasia Persada
telah sepakat membuat Berita Acara untuk :

Material Inspection Rebar D 16 Ulir & D 19 Ulir

Berita Acara ini dibuat untuk disetujui oleh PT. Bias Petrasia Persada, dengan deskripsi sebagai berikut :

Penjelasan
No Item Pekerjaan Diameter Jumlah Unit Keterangan
Pekerjaan

Material 16 4005 batang


Inspection Rebar
1 Material On Site RFI-PLTM-C-0014
D 16 Ulir & D 19 19 298 batang
Ulir

Demikian berita acara pekerjaan ini dibuat sebagai bukti untuk dapat dipergunakan sebagaimana mestiny

Kontraktor : Owner :

PT. Krakatau Engineering PT. Bias Petrasia Persada


Prepared By, Approved By,

(……………………………………) (……………………………………)
s Petrasia Persada

psi sebagai berikut :

Keterangan

RFI-PLTM-C-0014

ebagaimana mestiny

da

Anda mungkin juga menyukai