Get
PDF
TOP
SHARE
< 1K V = 1 MΩ minimum
>1KV = 1 MΩ /1KV
As per IE Rules-1956
At a pressure of 1000 V applied between each live conductor and earth for a period
of one minute the insulation resistance of HV installations shall be at least 1 Mega
ohm or as specified by the Bureau of Indian Standards.
As per CBIP specifications the acceptable values are 2 Mega ohms per KV
We need to test winding to winding and winding to ground ( E ).For three phase
transformers, We need to test winding ( L1,L2,L3 ) with substitute Earthing for Delta
transformer or winding ( L1,L2,L3 ) with earthing ( E ) and neutral ( N ) for wye
transformers.
0 32 0.25
5 41 0.36
10 50 0.50
15 59 0.720
20 68 1.00
30 86 1.98
40 104 3.95
50 122 7.85
Example: For 1600KVA, 20KV/400V,Three Phase Transformer
Transformer Coil Megger Size Min.IR Value Liquid Min.IR Value Dry Type
Voltage Filled T/C T/C
IR Value of Transformers
Test Connections of Transformer for IR Test (Not Less than 200 MΩ)
For any installation, the insulation resistance measured shall not be less than:
HV – Earth 200 M Ω
LV – Earth 100 M Ω
HV – LV 200 M Ω
For electric motor, we used a insulation tester to measure the resistance of motor
winding with earthing (E).
For insulation testing, we need to disconnect from panel or equipment and keep
them isolated from power supply. Thewiring and cables need to test for each other
( phase to phase ) with a ground ( E ) cable. The Insulated Power Cable Engineers
Association (IPCEA) provides the formula to determine minimum insulation
resistance values.
R = K x Log 10 (D/d)
The first conductor for which cross insulation is being measured shall be
connected to Line terminal of the megger. The remaining conductors looped
together (with the help of crocodile clips) i. e. Conductor 2 and onwards, are
connected to Earth terminal of megger. Conductors at the other end are left
free.
Now rotate the handle of megger or press push button of megger. The reading
of meter will show the cross Insulation between conductor 1 and rest of the
conductors. Insulation reading shall be recorded.
Now connect next conductor to Line terminal of the megger & connect the
remaining conductors to earth terminal of the megger and take
measurements.
IR Value Measurements:
(Sec-Phase) 5KV,10 KV 50 MΩ
Control Circuit 0.5KV 50 MΩ
A low resistance between phase and neutral conductors, or from live conductors to
earth, will result in a leakage current. This cause deterioration of the insulation, as
well as involving a waste of energy which would increase the running costs of the
installation.
1 Phase Wiring
>The IR test between Phase-Natural to earth must be carried out on the complete
installation with the main switch off, with phase and neutral connected together,
with lamps and other equipment disconnected, but with fuses in, circuit breakers
closed and all circuit switches closed.
Where two-way switching is wired, only one of the two stripper wires will be tested.
To test the other, both two-way switches should be operated and the system
retested. If desired, the installation can be tested as a whole, when a value of at
least 0.5 M Ohms should be achieved.
1 Phase Wiring
3 Phase Wiring
In the case of a very large installation where there are many earth paths in parallel,
the reading would be expected to be lower. If this happens, the installation should
be subdivided and retested, when each part must meet the minimum requirement.
3 Phase Wiring
The IR tests must be carried out between
Phase-Phase-Neutral-Earth with a minimum
acceptable value for each test of 0.5 M Ohms.
Recommended EE stuff //
About Author //
Jignesh Parmar
jiguparmar - Jignesh Parmar has completed M.Tech (Power
System Control) ,B.E(Electrical). He is member of Institution
of Engineers (MIE),India. Membership No:M-1473586.He has
more than 13 years experience in Transmission -
Distribution-Electrical Energy theft detection-Electrical
Maintenance-Electrical Projects (Planning-Designing-
Technical Review-coordination -Execution). He is Presently
associate with one of the leading business group as a Deputy Manager at
Ahmedabad,India. He has published numbers of Technical Articles in "Electrical
Mirror", "Electrical India", "Lighting India", "Industrial Electrix"(Australian Power
Publications) Magazines. He is Freelancer Programmer of Advance Excel and
design useful Excel base Electrical Programs as per IS, NEC, IEC,IEEE codes. He is
Technical Blogger and Familiar with English, Hindi, Gujarati, French languages. He
wants to Share his experience & Knowledge and help technical enthusiasts to find
suitable solutions and updating themselves on various Engineering Topics.
© 2015 EEP - Electrical Engineering Portal. All Rights Reserved | Privacy Policy | Terms of Service | 55 queries in 0.214
seconds.
Powered by CsanyiGroup