Anda di halaman 1dari 11

Construction Activity

Pipeline & Trunkline


Existing Proposed

Productivity Total Day Productivity Target


Total Day
No Area Activity Unit QTY Remark per Day per Day Completion Effective day Recommendation
Total Progress Remaining###
###
###
###
###
###Remaining 6
Piping JB Today 3/9/2018
Pipe Spool 1/22/2018 End date 2/15/2018
Welding Dia-Inch 454.5 416.5 38 38 24 1.6 48 0.791666667 No of date -22.00 Penambahan welder khusus untuk JB
Sandblasting + Primery M2 17.4 15.0 2.4 1/24/2018 Friday Holiday -0.857142857 NPD 40% status material Komplit
Painting (Top Coat) M2 17.4 15 2.421 1/24/2018 -21.14
Pipe Support Installation Ea 45 10 35 1/27/2018
Pipe Spool Installation Ea 39 0 39 3/6/2018 Effective Day -12.68571429

Piping JB (CPP) Today 3/9/2018


Pipe Spool End date 2/15/2018
Welding Dia-Inch 818 780 38 38 24 1.6 72 0.527777778 3/9/2018 No of date -22.00 Penambahan welder khusus untuk JB
Sandblasting M2 0 4.3 1/31/2018 Friday Holiday -0.857142857 NPD 40% status material Komplit
Painting M2 0 1/31/2018 -21.14
Pipe Support Installation Ea 0 2/15/2018
Pipe Spool Installation Ea 0 2/15/2018 Effective Day -12.68571429

Pipeline JB Today 3/9/2018


Ja
Stringing Mtr 9800 9800 0 m End date 2/7/2018
b
Welding Joint 817 808 9 o 9 2 4.5 10 0.9 2/6/2018 No of date -30.00 NPD 40% Penambahan welder khusus untuk Pipeline JB
B
NDT Joint 817 808 9 a 9 Friday Holiday -2
l
FJC Joint 817 808 9 e 9 -28.00
Trenching Mtr 9600 9555 45 45 1/23/2018
Lowering Mtr 9800 9755 45 45 1/24/2018 Effective day -16.8
Cable Pulling 1/25/2018
Backfill Mtr 9600 9555 45 45 180 0.3 500 0.09 1/27/2018
CIVIL JB (Receiver & Metering) Today 3/9/2018
Excavation M3 0 1/28/2018 End date 1/22/2018 Penambahan Tim di area JB dan Penambahan Molen
Lean Concrete M3 0.86 0.86 0 1/29/2018 No of date -46.00 NPD 40% terkendala akses jalan
Install Rebar Ton 0 2/1/2018 Friday Holiday -4.285714286
Install Formwork M2 0 2/4/2018 -41.71
Pouring Concrete M3 8.9 0 8.9 2.9 3.115 2/5/2018 1/16/2018
Concrete Curing Time Lot 1 0 1 2/22/2018 2/1/2018 Effective day -25.02857143

CIVIL JB (Anchorblock) Today 3/9/2018


Excavation M3 0 End date 1/22/2018
Lean Concrete M3 0.31 0.31 0 No of date -46.00 NPD 40%
Install Rebar Ton 0 Friday Holiday -1.764705882
Install Formwork M2 0 -44.24
Pouring Concrete M3 5.29 5.29 0 2.9 0 1/16/2018
Concrete Curing Time Lot 1 0 1 2/1/2018 Effective day -26.54117647

CIVIL JB Pipe Support OUTSTANDING :


Footing Pcs 44 43 1
Pedestal Pcs 59 49 10

CIVIL CPP Today 3/9/2018


Excavation M3 23.34 23.34 0 End date 1/22/2018 Selesai di COR untuk JB, JR1, dan AR
Lean Concrete M3 23.34 23.34 0 No of date -46.00 NPD 40%
Install Rebar Ton 0 Friday Holiday -4.285714286
Install Formwork M2 0 -41.71
Pouring Concrete M3 323 322.568 0.43 2.857142857 0.1512 1/16/2018
Concrete Curing Time Lot 1 1 2/1/2018 Effective day -25.02857143

CIVIL CPP TOTAL OUTSTANDING :


Footing Pcs 42 42 0
Productivity Total Day Productivity Target
Total Day
No Area Activity Unit QTY Remark per Day per Day Completion Effective day Recommendation
Pedestal Pcs 82 82 0

Piping JR-1 (CPP) Today 3/9/2018


Pipe Spool 2/11/2018 End date 2/15/2018
Welding Joint 274.75 264.75 10 10 24 0.4166667 72 0.138888889 No of date -22.00 NPD 40% status material Komplit
Sandblasting M2 190.9 116.9 74 74 2/13/2018 Friday Holiday -0.857142857
Painting M2 190.9 116.9 74 74 2/13/2018 -21.14
Pipe Support Installation Ea TBA 0 0 2/8/2018
Pipe Spool Installation Ea TBA 0 0 2/15/2018 Effective Day -12.68571429
Piping JR-1 Today 3/9/2018
Pipe Spool 2/11/2018 End date 2/15/2018
Welding Dia-Inch 1928.5 1888.5 40 40 24 1.6666667 72 0.555555556 No of date -22.00 NPD 40% status material Komplit
Sandblasting M2 0 2/13/2018 Friday Holiday -0.857142857
Painting M2 0 2/13/2018 -21.14
Pipe Support Installation Ea 111 31 80 2/8/2018
Pipe Spool Installation Ea 124 48 76 2/15/2018 Effective Day -12.68571429
Trunkline JR1 Today 3/9/2018
Stringing Mtr 2800 2800 0 End of date 2/20/2018
Welding Joint 233 233 0 5 0 20 0 No of date -17.00 NPD 40%
NDT Joint 233 233 0 Friday Holiday -0.142857143
FJC Joint 233 233 0 -16.86
Trenching Mtr 2800 2800 0
Lowering Mtr 2800 2800 0 Effective day -6.742857143
Backfill Mtr 2800 2800 0 0 1/15/2018

CIVIL JR-1 (Pig Launcer) Today 3/9/2018 Sudah selesai


Excavation M3 5.26 5.26 0 End date 1/15/2018
Lean Concrete M3 0.52 0.52 0 No of date -53 NDP 40%
Install Rebar Ton 0.57 0.57 0 Friday Holiday -5.285714286
Install Formwork M2 9.24 9.24 0 -47.71428571
Pouring Concrete M3 5.29 5.29 0 36.78 2.857142857 0
Concrete Curing Time Lot 1 1 0 1/15/2018 Effective Day -28.62857143

CIVIL JR-1 TOTAL OUTSTANDING :


Footing Pcs 64 64 0
Area 1 29 29 0
Area 2 32 32 0
Area 3 3 3 0
Pedestal Pcs 64 64 0
Area 1 29 29 0
Area 2 32 32 0
Area 3 3 3 0

Trunkline AS Today 3/9/2018


Stringing Mtr 7000 7000 0 End date 3/1/2018 Penambahan welder
Welding Joint 583 576 7 5 1.4 7 1 No of date -8.00 NPD 40%
NDT Joint 583 530 53 Friday Holiday 1
FJC Joint 583 536 47 -9.00
Trenching Mtr 7000 5514 1486
Lowering Mtr 7000 5936 1064 Effective Day -5.4
Cable Pulling
Backfill Mtr 7000 5445 1555
Piping AS Today 3/9/2018
Pipe Spool End date 3/1/2018 Penambahan welder
Welding (Claded & SS) Dia-Inch 5872.5 205 5667.5 5831.5 4 1468.125 192 29.51822917 No of date -8.00 40% progress pertanggal 23 jan
Welding (CS ) Dia-Inch 250 250
Sandblasting M2 8800 1100 7700 Friday Holiday 0.8571428571
Painting M2 8800 1100 7700 -8.86 * DB (FAB)
Productivity Total Day Productivity Target
Total Day
No Area Activity Unit QTY Remark per Day per Day Completion Effective day Recommendation
Pipe Spool Installation Ea
Pipe Valves Installation Ea Effective Day -5.314285714

CIVIL AS TOTAL OUTSTANDING :


Footing Pcs 166 90 76
Pedestal Pcs 191 46 145

CIVIL JR-1 (Anchorblock) J


u A
Today 3/9/2018 Concrete Curing Time masih berjalan sampai 24 Jan 18
Excavation M3 7.8 7.8 0 l
u
l
u End of date 3/1/2018
R r
Lean Concrete M3 0.352 0.352 0 a R No of date -8.00 NPD 40%
y a
Install Rebar Ton 0.783 0.783 0 u m Friday Holiday 1.1428571429
1 b
Install Formwork M2 10 10 0 o -9.14
n
Pouring Concrete M3 6 6 0 g 52.16 2.857142857 0 2/22/2018
Concrete Curing Time Lot 1 0 1 3/1/2018 Effective day -5.485714286
J
u
l
u
ELECTRICAL Power Cable CPP to Alur Siwah Cluster A R
a
y
Trenching m e
2
Laying Cable m 7296 1500 5796
Splicing Joint
Backfiiling m 7296 350 6946
Termination point

ELECTRICAL Power Cable CPP to Alur Rambong


Trenching m
Laying Cable m 14936 290 14646
Splicing Joint
Backfilling m 14936 700 14236
Termination point
ELCETRICAL FO CPP to Jambo Balee
Trenching m 19624 19624 0 Completed
Laying Cable m 19624 19624 0 Completed
Splicing Joint 2 2
Backfilling m 9712 8100 1612
Termination point 2 2
ELECTRICAL FO Cable CPP to Alur Siwah Cluster A
Trenching m
Laying Cable m 14592 3000 11592
Splicing Joint
Backfilling m 7296 350 6946
Termination point
ELECTRICAL FO CPP to Alur Rambong
Trenching m
Laying Cable m 28872 1400 27472
Splicing Joint
backfilling m 14936 530 14406
Termination point
CIVIL AR TOTAL OUTSTANDING :
Footing Pcs 77 0 77
Pedestal Pcs 84 0 84
ELECTRICAL Power Cable CPP to Jambo Balee
Trenching m 9712 9712 0 Today 3/9/2018 Completed
Laying Cable m 9712 9712 0 End of date 1/26/2018 Completed
Splicing Joint 20 20 No of date -42 NPD 40% Menerapkan Jam kerja lembur
Backfilling m 9712 8100 1612 300 5.3733333 1500 1.074666667 1/26/2018 Friday Holiday -3.714285714 penambahan Utility ( 6 Excavator, 2 Water Pump, 4 Dump Truck Kecil, 1 unit tower light)
Termination point 2 2 -38.28571429 merubah metode Kerja
Ohm meter / multi tester belum ada yg tersertifikasi
REMAINING CONSTRUCTION WORK
Pipeline & Trunkline
Disipline Description Unit Remaining Status
Piping
Test Pack
JR1 Test Pack 1 0
Test Pack 2 4 Completed
Test Pack 3 4 Completed
Test Pack 4 4 Completed
Test Pack 5 1
Test Pack 6 20
JB Test Pack 1
Test Pack 2
CPP JR1 Test Pack 1 0
CPP JB Test Pack 1 9
Test Pack 2 11
Test Pack 3 9
JB Pipe Spool Installation ea 39
Pipe Support ea 35
JR1 Pipe Spool Installation ea 76
Pipe Support ea 83
CPP Pipe Spool Installation ea 67
Pipe Support ea 26
AS Pipe Spool Installation ea
Pipe Support ea
AR Pipe Spool Installation ea
Pipe Support ea
PIPELINE
Trunkline JR1
Welding Joint 0
NDT Joint 0
FJC Joint 0
Trenching Mtr 0
Lowering Mtr 0
Backfill Mtr 0
Pipeline JB
Welding Joint 4
NDT Joint 4
FJC Joint 4
Trenching Mtr 20
Lowering Mtr 20
Backfill Mtr 20
Disipline Description Unit Remaining Status
CPP
JR1
Welding Dia-Inch 10
Sandblasting M2 74
Painting M2 74
Pipe Support Installation Ea 80
Pipe Spool Installation Ea 76
JB
Welding Dia-Inch 19
Sandblasting M2
Painting M2
Pipe Support Installation Ea 35
Pipe Spool Installation Ea 39
E&I
Power Cable CPP to Jambo Balee
Laying Cable m 0 Completed
Splicing point 2
FO CPP to Jambo Balee
Laying Cable m 0 Completed
Splicing point 20
CIVIL
CIVIL JR-1
Footing
Area 1 Pcs 0
Area 2 Pcs 0
Area 3 Pcs 0
Pedestal
Area 1 Pcs 0
Area 2 Pcs 0
Area 3 Pcs 0
CIVIL JB Metering Pipe Support
Footing Pcs 1
Pedestal Pcs 0
Anchor Block Pcs 0 Pouring Concrete Complete
Cathodic Protection JB
Cad Weld point 1
Install Test Box ea
Install Groundbed Anodes ea
Install Tranformer Rectifier ea
Termination point
Cathodic Protection JR
Disipline Description Unit Remaining Status
Cad Weld point 0
Install Test Box ea
Disipline Description Unit Remaining Status
Install Groundbed Anodes ea
Install Tranformer Rectifier ea
Termination point
Cathodic Protection AR
Cad Weld point 15
Install Test Box ea
Install Groundbed Anodes ea
Install Tranformer Rectifier ea
Termination point
CIVIL CPP Pipe Support
Footing Pcs 0 Completed
Pedestal Pcs 0 Completed
Anchor Block Pcs 0 Pouring Concrete Complete, Curing Time
Description Column1 Column2 Unit Total To Day Cummulative
Pipeline
Welding
JB Joint 850 0 850
JR1 Joint 233 0 233
AS Joint 583 0 577
AR Joint 1,241 12 985
JR 38 Joint 100 0 51
JR 40 Joint 141 0 27
Lowering
JB m 10,200 0 10,200
JR1 m 2,800 0 2,800
AS m 7,000 0 5,924
AR m 14,900 1260 6,921
JR 38 m 1,200 0 -
JR 40 m 1,700 0 -
Civil Work
Footing
AS Pcs 166 0 98
AR Pcs 77 0 -
JR 38 Pcs
JR 40 Pcs
Pedestal
AS Pcs 196 8 64
AR Pcs 84 0 -
JR 38 Pcs
JR 40 Pcs
Piping Work
Spool Fabrication
JB Ea
JR1 Ea 124 0 48
AS Ea
AR Ea
JR 38 Ea
JR 40 Ea
Field Install
JB Ea 39 0 -
JR1 Ea 124 0 48
AS Ea
AR Ea
JR 38 Ea
JR 40 Ea
Electrical Instrument
Pouling Cable
JB m 9,700 0 9,700
JR1 m
AS m 7,296 0 1,500
AR m 14,936 0 1,500
JR 38 m
JR 40 m
Cathodic
JB Ea 13 0 13
JR1 Ea 7 0 7
AS Ea 15 0 5
AR Ea 20 0 10
JR 38 Ea
JR 40 Ea
Temination
JB Point
JR1 Point
AS Point
AR Point
JR 38 Point
JR 40 Point
Mechanical Completion
Hydrotest Trunkline
JB Pack 3 2 2
JR1 Pack 6 2 5
AS Pack
AR Pack
JR 38 Pack
JR 40 Pack
Hydrotest Pipeline
JB Line Check
JR1 Line Check
AS Line Check
AR Line Check
JR 38 Line Check
JR 40 Line Check
Remaining

-
-
6
256
49
114

-
-
1,076
7,979
1,200
1,700

68
77

132
84

76

39
76
-

5,796
13,436

-
-
10
10

1
1

Anda mungkin juga menyukai