Highway Pavement
What is a pavement
1. A multi-layer system that distributes the vehicular loads over a larger area.
Or
2. HW pavement is a structures consisting of superimposed layers of selected
and processed materials whose primary function is to distribute the applied
load to subgrade. Or
3. Structures which separates the tires of vehicles from under lying
foundation.
1|shahadaT
3. It should provide a reasonably hard wearing surface, so that the abrasive
action of wheels does not damage the surface.
4. It should be dust free so that traffic safety is not impaired.
5. Its riding quality should be good.
6. Should have low friction with tire- low energy consumption
7. Texture and adequate roughness to prevent skidding of vehicle.
8. No excessive sound from moving vehicle.
9. Impervious surface
10. Long life and low maintenance cost.
History
Macadam Roads
2|shahadaT
1. John Macadam used a sloped subgrade surface to improve drainage on
which he placed angular aggregate (hand-broken, maximum size 75 mm)
in two layers for a total depth of about 200 mm.
2. On top of this, the wearing course was placed (about 50 mm thick with a
maximum aggregate size of 25 mm) to provide a “smooth” ride for wagon
wheels. Thus, the total depth of a typical Macadam pavement was about
250 mm.
3. An interesting quote by Macadam was that “no stone larger than will enter
a man’s mouth should go into a road”
4. The largest permissible load for this type of design was estimated to be
158 N/mm (900 lb. per in. width)
5. Macadam realized that the layers of broken stone would eventually
become “bound” together by fines generated by traffic.
Telford Roads
3|shahadaT
4. On top of this were placed two layers of stones of 65 mm maximum size
(about 150 to 250 mm total thickness) followed by a wearing course of
gravel about 40 mm thick.
5. It was estimated that this system would support a load corresponding to
88 N/mm (500 lb. per in. of width)
Types of Pavement
Flexible Pavement
4|shahadaT
5. In flexible pavements material layers are usually arranged in order of
descending load bearing capacity with the highest load bearing capacity
material (and most expensive) on the top and the lowest load bearing
capacity material (and least expensive) on the bottom.
1. Surface course. This is the top layer and the layer that comes in contact
with traffic. It may be composed of one or several different HMA sublayers.
2. Base course. This is the layer directly below the surface course and
generally consists of aggregate (either stabilized or unstabilized) or HMA.
3. Subbase course. This is the layer (or layers) under the base layer. A
subbase is not always needed.
5|shahadaT
Surface course
1. The surface course is the layer in contact with traffic loads and normally
contains the highest quality materials.
2. It provides characteristics such as friction, smoothness, noise control, rut
and shoving resistance and drainage.
3. In addition, it serves to prevent the entrance of excessive quantities of
surface water into the underlying base, subbase and subgrade.
4. This top structural layer of material is sometimes subdivided into two layers:
a. Wearing Course:
i. This is the layer in direct contact with traffic loads. It is meant to take
the brunt of traffic wear and can be removed and replaced as it
becomes worn.
ii. A properly designed (and funded) preservation program should be
able to identify pavement surface distress while it is still confined to
the wearing course.
iii. This way, the wearing course can be rehabilitated before distress
propagates into the underlying intermediate/binder course.
b. Intermediate/Binder Course: This layer provides the bulk of the HMA
structure. Its chief purpose is to distribute load.
Base course
Base courses are most typically constructed from durable aggregates that will
not be damaged by moisture or frost action. Aggregates can be either stabilized
or unstabilized. In certain situations, where high base stiffness is desired, base
6|shahadaT
courses can be constructed using a variety of HMA mixes. In relation to surface
course HMA mixes, base course mixes usually contain larger Maximum
aggregate sizes, are more open graded and are subject to more lenient
specifications.
Sub-Base course
1. The subbase course is between the base course and the subgrade. It
functions primarily as structural support but it can also:
a. Minimize the intrusion of fines from the subgrade into the pavement
structure.
b. Improve drainage.
c. Minimize frost action damage.
d. Provide a working platform for construction.
2. The subbase generally consists of lower quality materials than the base
course but better than the subgrade soils.
3. A subbase course is not always needed or used. For example, a
pavement constructed over a high quality, stiff subgrade may not need the
additional features offered by a subbase course so it may be omitted from
design
4. However, a pavement constructed over a low quality soil such as a
swelling clay may require the additional load distribution characteristic that
a subbase course can offer.
5. In this scenario the subbase course may consist of high quality fill used to
replace poor quality subgrade.
7|shahadaT
Full - Depth Asphalt Pavements are constructed by placing bituminous
layers directly on the soil sub- grade. This is more suitable when there is
high traffic and local materials are not available.
Contained Rock Asphalt Mats are constructed by placing dense/open
graded aggregate layers in between two asphalt layers. Modified dense
graded asphalt concrete is placed above the sub-grade will significantly
reduce the vertical compressive strain on soil sub-grade and protect from
surface water. (CT-16)
1. Surface course
a. Seal coat
b. Surface course
c. Tack coat
d. Binder course
e. Prime coat
2. Base course
3. Sub-base course
4. Compacted sub-grade
5. Natural sub-grade
8|shahadaT
Seal Coat: Seal coat is a thin surface treatment used to water-proof the
surface and to provide skid resistance.
Tack Coat: Tack coat is a very light application of asphalt, usually asphalt
emulsion diluted with water. It provides proper bonding between two layer
of binder course and must be thin, uniformly cover the entire surface, and
set very fast. (VVI) (16, CT-16)
Prime Coat: Prime coat is an application of low viscous cutback bitumen
to an absorbent surface like granular bases on which binder layer is
placed. It provides bonding between two layers. Unlike tack coat, prime
coat penetrates into the layer below, plugs the voids, and forms a water
tight surface. (VVI) (16, CT-16)
9|shahadaT
3. It must be water proof to protect the entire base and sub-grade
from the weakening effect of water
• Binder course: This layer provides the bulk of the asphalt concrete
structure. It’s chief purpose is to distribute load to the base course The binder
course generally consists of aggregates having less asphalt and doesn’t
require quality as high as the surface course, so replacing a part of the
surface course by the binder course results in more economical design.
• Base course: The base course is the layer of material immediately beneath
the surface of binder course and it provides additional load distribution and
contributes to the sub-surface drainage It may be composed of crushed
stone, crushed slag, and other untreated or stabilized materials
Difference between Tack Coat and Prime Coat (VVI) (16, CT-16)
10 | s h a h a d a T
Tack coat does not require the In order to be effective, a prime coat
penetration into the underlying layer penetrates into the underlying layer,
plugs the voids, and forms a watertight
surface.
Tack coat prevents slippage and may Prime coat asphalt acts as an initial
sometimes function as a more long- sealer in the asphalt laying process to
term sealer to protect the substrate block the other layers from moisture,
from moisture and bacteria. dust and debris before additional
coating installations.
• Give figure
1. Empirical method with or without soil strength test (A-1 to A-8, B1 to B3)
11 | s h a h a d a T
What is Mechanistic Empirical Method (ME) (VVI) (CT-17)
Climatic Effects Limited – can change inputs Integral – weather data from
based on season 600+ US weather stations
included
12 | s h a h a d a T
Performance Present Serviceability Index Various distresses, IRI
Parameter (International roughness
index)
Rigid Pavement
Surface course. This is the top layer, which consists of the PCC slab.
Base course. This is the layer directly below the PCC layer and generally
consists of aggregate or stabilized subgrade.
13 | s h a h a d a T
Subbase course. This is the layer (or layers) under the base layer. A
subbase is not always needed and therefore may often be omitted.
Surface course
1. The surface course is the layer in contact with traffic loads and is made of
PCC.
2. It provides characteristics such as friction smoothness, noise control and
drainage.
3. It serves as a waterproofing layer to the underlying base, subbase and
subgrade.
4. The surface course can vary in thickness but is usually between 150 mm
(6 inches) (for light loading) and 300 mm (12 inches) (for heavy loads and
high traffic).
Base course
14 | s h a h a d a T
c. Dense-graded HMA.
d. Permeable HMA.
e. Lean concrete
Sub Base
1. The subbase course is the portion of the pavement structure between the
base course and the subgrade. It functions primarily as structural support
but it can also:
a. Minimize the intrusion of fines from the subgrade into the pavement
structure.
b. Improve drainage.
c. Minimize frost action damage.
d. Provide a working platform for construction.
2. The subbase generally consists of lower quality materials than the base
course but better than the subgrade soils. Appropriate materials are
aggregate and high quality structural fill. A subbase course is not always
needed or used.
15 | s h a h a d a T
used more frequently for airport pavements than for highway pavements
because the saving in thickness for airport pavements is much greater than that
for highway pavements. Slab Length varied from 300 to 700 ft.
16 | s h a h a d a T
Comparison between Flexible and Rigid Pavements (VVI) (CT-16,17)
17 | s h a h a d a T
quality of material is used at or near
the surface
Main Modes of failure (Imp)
Rutting Fatigue
Fatigue Joint failure
Shear Temperature Cracks
Advantages
Low initial involvement Can deal with very heavy
Offer stage construction traffic
Easy to maintain / correct foundation Very long life span
error Require little maintenance
Give smooth riding quality (in hilly Give good light reflectance
area/rolling terrain it is the better quality
option Provide pleasing appearance
Offer high skid resistance They perform quite
Non-slippery even in wet condition satisfactory even when
Produce low level of noise constructed on poor sub-
Cutting/digging road side trench for grade
up-gradation of utility services is Less susceptible to weather –
easier specially at submerged
Can be open for traffic immediately condition
after construction Heating of aggregates and
Recycling is easier cement is not required
Disadvantages
High maintenance cost High initial cost (but low life-
Susceptible to weather – bleeding at cycle cost)
high temperature cracking at low Difficult to repair and correct
temperature and stripping under foundation error
submerged condition Produce high noise due to
Poor light reflectance quality wear and tear of vehicles
Short life span Up-gradation of different
Suitable for roads in residential and underground utility services is
built-up areas very difficult
Required uniform support Stage construction is not
Reflect the deformation of lower possible
layers Cannot be reconstructed
Performance is very sensitive to At the end of pavement life,
surface as well as sub-surface crushing of the layer is
drainage condition required before laying of new
Produce high built-up of bituminous surface course
superheated air layer above
18 | s h a h a d a T
pavement surface or high ambient Before opening for traffic at
temperature least 28 days curing is
required
After some time of use
surface becomes smooth and
slippery.
Suitable for roads in open
areas where noise problem is
not a big issue & no need to
lay utility pipes.
Submerged Condition
Water is enemy for bituminous Ware course is water friendly
wearing course (stripping prob. (Concrete grains strength)
Quality Control Compliances
Aggregate quality, gradation & layer W/C control
compaction Curing control
Stringent requirement of
temperature control
Equipment Involvement
High no. of equipment is needed Involvement of equipment is
Need involvement of heavy minimum
compaction equipment For concreting work, no roller
Need heating facility is needed
Need professional contractor For low standard road, no
need of involving professional
contractor.
Temperature (Imp)
No stress is developed due to Stress is produced due to
temperature in flexible pavement. temperature in rigid
pavement.
Economy (15,16,Imp)
Construction cost less but Construction cost high but
maintenance cost high maintenance cost less
19 | s h a h a d a T
More Comparison
1. Glare and night visibility (16,Imp)
Concrete is naturally brighter and more reflective than asphalt. This requires
less energy to illuminate comparable areas, which is good for the
environment. To overcome the lack of light reflectance, an asphalt pavement
requires either:
For concrete pavement it is difficult to rip open the slab and restore it to the
original condition if any changes in the utility lines are to be made. For this
purpose, gaps are lift in the pavement in flexible pavement random cut in
pavement structure is possible. So for an unplanned and densely populated city
flexible pavement is preferable because utility cutting is very common feature
in these road areas.
4. Penetration of water
20 | s h a h a d a T
5. Traffic dislocation
21 | s h a h a d a T
b. This means fewer raw materials are used both in the short term
and over the life of the pavement.
c. This also means fewer pollutants are going into our water air and
soil.
d. It also results in less energy begin used in construction equipment.
e. Longer lasting concrete helps reduce traffic congestion because
there are simply fewer construction work zones slowing traffic flow.
22 | s h a h a d a T
LEC 05-06
Pavement Design Requirement (Math)
The tyre pressure is an important factor, as it determines the contact area and
the contact pressure between the wheel and the pavement surface. Even
though the shape of the contact area is elliptical, for sake of simplicity in
analysis, a circular area is often considered.
23 | s h a h a d a T
Problem
24 | s h a h a d a T
Axle configuration (Imp)
The load carrying capacity of the commercial vehicle is further enhanced by the
introduction of multiple axles
25 | s h a h a d a T
Equivalent Axle Load Factor
An equivalent axle load factor (EALF) defines the damage per pass to a
pavement by the axle in question relative to the damage per pass of a standard
axle load, usually the 18-kip (80-kN) single-axle load. The design is based on
the total number of passes of the standard axle load during the design period,
defined as the equivalent single-axle load (ESAL) and computed by
in which m is the number of axle load groups, Fi is the EALF for the ith -axle load
group, and ni is the number of passes of the ith-axle load group during the design
period. The EALF depends on the type of pavements, thickness or structural
capacity, and the terminal conditions at which the pavement is considered
failed. Most of the EALFs in use today are based on experience. One of the
most widely used methods i s based on the empirical equations developed from
the AASHO Road Test (AASHTO, 1972). The EALF can also be determined
theoretically based on the critical stresses and strains in the pavement and the
failure criteria. EALF can be determined from table 6.4 (Huang-259) or
Problem
26 | s h a h a d a T
LEC 07
Road Test (Math)
ASSHO Road Test
(Huang-19)
Objective (16)
The test consisted of four large loops, numbered 3 through 6, and two smaller
loops, 1 and 2. Each loop was a segment of a four-lane divided highway whose
parallel roadways, or tangents, were connected by a turnaround at each end.
Tangent lengths were 6800 ft. (2070 m) in loops 3 through 6, 4400 ft. (1340 m)
in loop 2, and 2000 ft. (610 m) in loop 1. In all loops, the north tangents were
surfaced with HMA and south tangents with PCC. Centerlines divided the
pavements into inner and outer lanes, called lane 1 and lane 2. Each tangent
was constructed as a succession of pavement sections called structural
sections. Pavement designs varied from section to section. The minimum length
of a section was 100 ft (30 .5 m) in loops 2 through 6 and 15 ft. (4.6 m) in loop
1. Construction began in August 1956, and test traffic was inaugurated on
October 15, 1958. Test traffic was operated until November 30, 1960, at which
time 1,114,000 axle loads had been applied. The total cost of the project was
$27,000,000.
Time
Test Facilities
27 | s h a h a d a T
Loops 2 through 6 = subject to traffic described in Figure 2
Figure 1: Loop 5 and 6 AASHO Road Test Layout (redrawn from Highway Research Board,
1961)
One important contribution of the AASHO Road Test was the development of
the pavement serviceability concept together with the equations relating
serviceability, load, and thickness design of both flexible and rigid pavements.
Major findings for flexible and rigid pavements are summarized separately as
follows:
Flexible Pavements
1. The superiority of the four types are: bituminous treated, cement treated,
crushed stone, and gravel. Gravel base failed very early in the test, and
28 | s h a h a d a T
their performance was definitely inferior to that of the sections with
crushed-stone base.
2. The pavement needed to maintain a certain serviceability at a given
number of axle-load applications would be considerably thinner in the
inner than in the outer wheel path.
3. Rutting of the pavement was due principally to decrease in thickness of
the component layers. About 91% of the rutting occurred in the pavement
itself: 32% in the surface, 14% in the base, and 45% in the subbase.
Thus, only 9% of a surface rut could be accounted for by rutting of the
embankment.
4. More surface cracking occurred during periods when the pavement was
in a relatively cold state than during periods of warm weather.
5. The deflection occurring within the pavement structure (surface, base,
and subbase), as well as that at the top of the embankment soil, was
greater in the spring than during the succeeding summer months.
Rigid Pavements
Objective (16)
29 | s h a h a d a T
The objective of this project was to determine the relative effects of four different
axle loadings on a particular concrete pavement (HRB, 1952). The tests were
conducted on a 1 .1-mile (1 .76-km) section of concrete pavement constructed
in 1941 on US 301 approximately 9 miles (14.4 km) south of La Plata, Maryland.
1. Both the average cracking and the average settlement of slab at the joint
increased in this order: 18,000-lb (80-kN) single axle, 32,000-lb (142-kN)
tandem axle, 22,400-lb (100-kN) single axle, and 44,800-lb (200-kN)
tandem axle.
2. Pumping occurred on plastic clay soils but not on granular subgrades with
low percentages of silt and clay.
3. The failure of the slabs on the fine-grained soil can be explained by the fact
that the deflections of these slabs under all of the test loads were sufficient
to cause pumping when the other requisites for pumping were present. As
pumping developed, the deflections increased with corresponding more
rapid increase of stress to a magnitude sufficient to cause rupture of the
slab.
4. With the exception of the corner case of loading for pumping soils, the
stress and deflection resulting at vehicle speed of 40 mph (64 km/h)
averaged approximately 20% less than those at creep speed. For pumping
slabs under corner loading, the stresses averaged approximately the same
for both vehicle speeds.
5. The stresses and deflections caused by loads acting at the corners and
edges of slabs were influenced to a marked degree by temperature curling.
30 | s h a h a d a T
LEC 08-10
Stress and Strain (Math)
Flexible Pavement
31 | s h a h a d a T
Q: Compare between Boussinesq’s and Bermisters methods for analysis
of flexible pavement stress.
32 | s h a h a d a T
Problem
33 | s h a h a d a T
Drawbacks of Boussinesq’s approach
1. The assumptions that soil is perfectly elastic and homogenous is not true.
Soil may be elastic up to a certain limit.
2. The pavement consists of a number of layers, each with its own modulus
of elasticity. Hence the assumption of one constant property for the entire
mass is not justified.
3. The assumption that the load is uniformly distributed may not be correct.
34 | s h a h a d a T
Problem
35 | s h a h a d a T
36 | s h a h a d a T
(VVI Fig)
Problem (15,16)
37 | s h a h a d a T
38 | s h a h a d a T
39 | s h a h a d a T
Rigid Pavement
Three positions of loading are generally considered for estimating the stresses
in a slab in a conventional method of design. They are illustrated in Fig. 22.1.
Interior loading produces tensile stresses at the bottom of the slab. Edge
loading produces tensile stresses at the bottom of the slab parallel to the edge
and another smaller tensile stress at the top of the slab at right angles to the
edge. Corner loading produces tensile stresses at the top of the slab parallel to
the bisector of the corer angle.
40 | s h a h a d a T
Temperature changes (Imp)
1. Changes in the temperature gradient through the slab will cause differential
expansion or contraction between the top and bottom of the slab. The slab
then tends to warp, but is prevented from warping due to the slab weight
and friction at load transferring devices. Stresses are induced due to such
restraint.
2. The expansion or contraction of the slab due to temperature changes is
restrained due to the friction between the subgrade and the slab. This
causes stresses in the slab.
1. The concrete slab is homogeneous and isotropic and has uniform elastic
properties.
2. The reaction of the subgrade is vertical only and is proportional to the
deflection of the slab. In other words, the support provided by the subgrade
is similar to that given by a dense fluid and the subgrade has no shear
strength (Fig. 22.2).
3. The reaction of the subgrade at a point is equal to K x Deflection at that
point, the constant K being the Modulus of Subgrade Reaction.
4. The slab is uniform in thickness.
5. The load in the interior and the corner is circular in shape, positioned as
indicated in Fig. 22.1. The edge loading is semi-circular as in Fig. 22.1.
41 | s h a h a d a T
These equations (22.2-22.8 will be given in exam, know the notations only)
42 | s h a h a d a T
Problem
43 | s h a h a d a T
Critical combination of stresses (15,16)
The three conditions of loading are first analyzed for wheel load stresses. The
maximum wheel load stress occurs in the corner and the minimum occurs in the
interior. The edge load condition gives an intermediate value. The temperature
stress is critical at the edge and the interior, and is minimum at the corner. Thus,
the combination of wheel load and temperature can be critical at the edge. The
total stress by this combination should be checked with the stress at the corner
due to wheel loads.
44 | s h a h a d a T
LEC 11
Joints
Why joints are Needed? (15)
Joints are provided to control such stresses, so that premature cracks due to
moisture/temp change will not occur.
Types of Joint
1. Contraction Joint
2. Expansion Joint
3. Isolation Joint
4. Construction Joint
Contraction Joint
1. They are generally between 1/4–1/3 the depth of the slab and typically
spaced every 3.1–15 m (12 – 50 ft.)
2. As a rough guide, the joint spacing in feet for plain concrete pavements
should not greatly exceed twice the slab thickness in inches.
3. For example, the maximum joint spacing for an 8-in. (203-mm) slab is 16
ft. Also, as a general guideline, the ratio of slab width to length should not
exceed 1 .25
Fig
1. Expansion joints are transverse joints for the relief of compressive stress
that develop when concrete expands by providing space for movement.
2. Because expansion joints are difficult to maintain and susceptible to
pumping, they are no longer in use today.
3. Also their progressive closure tends to cause contraction joints to
progressively open.
4. Contraction joint openings cause a loss of load transfer particularly joints
without dowel bars.
5. Their use is compensated by using contraction joint and using isolation
joint in bridges.
47 | s h a h a d a T
2. They are typically filled with a joint filler material to prevent water and dirt
infiltration.
They increase load transfer efficiency by Although they may provide some
allowing the leave slab to assume some minimal amount of load transfer, they are
of the load before the load is actually not designed to act as load transfer
over it devices and should not be used as such
Typically used between transverse slab. Typically used at longitudinal joints (see
This reduces joint deflection and stress Figure 2.37) or between an edge joint
in the approach and leave slabs. and a curb or shoulder
Dowel bars are typically 1.25 to 1.5 Typically, tie bars are about 0.5 inches in
inches in diameter 18 inches long and diameter and between 24 and 40 inches
spaced 12 inches apart. Thumb rule long.
diameter of dowel be equal to 1/8 of slab
thickness.
48 | s h a h a d a T
LEC 13
Pavement Distress
Flexible Pavement Distress
49 | s h a h a d a T
Repair: A fatigue cracked pavement should be investigated to determine the
root cause of failure. Any investigation should involve digging a pit or coring
the pavement to determine the pavement's structural makeup as well as
determining whether or not subsurface moisture is a contributing factor. Once
the characteristic alligator pattern is apparent, repair by crack sealing is
generally ineffective. Fatigue crack repair generally falls into one of two
categories:
1. Small, localized fatigue cracking indicative of a loss of subgrade support.
Remove the cracked pavement area then dig out and replace the area of
poor subgrade and improve the drainage of that area if necessary. Patch
over the repaired subgrade.
2. Large fatigue cracked areas indicative of general structural failure. Place
an HMA overlay over the entire pavement surface. This overlay must be
strong enough structurally to carry the anticipated loading because the
underlying fatigue cracked pavement most likely contributes little or no
strength.
Bleeding (15,16)
Possible Causes: Bleeding occurs when asphalt binder fills the aggregate
voids during hot weather and then expands onto the pavement surface. Since
bleeding is not reversible during cold weather, asphalt binder will accumulate
on the pavement surface over time. This can be caused by one or a combination
of the following:
1. Excessive asphalt binder in the HMA (either due to mix design or
manufacturing)
50 | s h a h a d a T
2. Excessive application of asphalt binder during BST application (as in the
above figures)
3. Low HMA air void content (e.g., not enough room for the asphalt to
expand into during hot weather)
Repair: The following repair measures may eliminate or reduce the asphalt
binder film on the pavement's surface but may not correct the underlying
problem that caused the bleeding:
1. Minor bleeding can often be corrected by applying coarse sand to blot up
the excess asphalt binder.
2. Major bleeding can be corrected by cutting off excess asphalt with a
motor grader or removing it with a heater planer. If the resulting surface
is excessively rough, resurfacing may be necessary (APAI, no date
given).
Patching
Description: An area of pavement that has been replaced with new material to
repair the existing pavement. A patch is considered a defect no matter how well
it performs.
Problem: Roughness.
Possible Causes:
1. Previous localized pavement deterioration that has been removed and
patched.
2. Utility cuts.
Repair: Patches are themselves a repair action. The only way they can be
removed from a pavement's surface is by either a structural or non-structural
overlay.
51 | s h a h a d a T
Potholes (13,16)
Raveling (13,16)
Rutting (13,16)
53 | s h a h a d a T
Problem: Ruts filled with water can cause vehicle hydroplaning, can be
hazardous because ruts tend to pull a vehicle towards the rut path as it is steered
across the rut.
Possible Causes: During cold periods (e.g., winter) PCC slabs contract leaving
wider joint openings. If these openings become filled with incompressible
54 | s h a h a d a T
material (such as rocks or soil), subsequent PCC slab expansion during hot
periods (e.g., spring, summer) may cause high compressive stresses. If these
stresses are great enough, the slabs may buckle and shatter to relieve the
stresses. Blowup can be accelerated by:
1. Joint spalling (reduces slab contact area and provides incompressible
material to fill the joint/crack)
2. D cracking (weakens the slab near the joint/crack area)
3. Freeze-thaw damage (weakens the slab near the joint/crack area)
Spalling (15)
55 | s h a h a d a T
Repair: Spalling less than 75 mm (3 inches) from the crack face can generally
be repaired with a partial-depth patch. Spalling greater than about 75 mm (3
inches) from the crack face may indicated possible spalling at the joint bottom
and should be repaired with a full-depth patch.
Pumping (15,16)
Problem: Decreased structural support of the slab, which can lead to linear
cracking, corner breaks and faulting.
Repair: First, the pumping area should be repaired with a full depth patch to
remove any deteriorated slab areas. Second, consideration should be given to
using dowel bars to increase load transfer across any significant transverse
joints created by the repair. Third, consideration should be given to stabilizing
any slabs adjacent to the pumping area as significant amounts of their
underlying base, subbase or subgrade may have been removed by the pumping.
Finally, the source of water or cause of poor drainage should be addressed.
56 | s h a h a d a T
LEC 15-17
Design of Flexible Pavement (Math)
Asphalt Institute Method
Two types of strains have frequently been considered the most critical for the
design of asphalt pavements. One is the horizontal tensile strain 𝜖𝑡 at the bottom
of the asphalt layer, which causes fatigue cracking ; the other is the vertical
compressive strain 𝜖𝑐 on the surface of the subgrade, which causes permanent
deformation or rutting . These two strains are used as failure criteria in the
Asphalt Institute method.
Pic
1. Fatigue Criterion. For a standard mix with an asphalt volume (Vb) of 11%
and an air void volume (Va) of 5%, the equation is
57 | s h a h a d a T
2. Permanent Deformation Criterion The allowable number of load
repetitions to control permanent deformation can be expressed as
Equation 11.22 was used to develop the design charts. As long as good
compaction of the pavement components is obtained and the asphalt mix is well
designed, the use of Eq. 11.22 should not result in rutting greater than 0.5 in.
(12.7 mm) for the design traffic.
Material Characterization
1. Poisson ratios can be reasonably assumed as 0.45 for subgrade soils and
0.35 for all other materials.
2. Resilient Modulus The resilient modulus (𝑀𝑅 ) used in this design
procedure is the normal resilient modulus, which is not representative of
times when the subgrade is freezing or thawing. At least six to eight test
values are usually used to determine the design subgrade resilient modulus.
The design subgrade resilient modulus is defined as the modulus value that
is smaller than 60, 75, or 87 .5% of all the test values. Lower design 𝑀𝑅 is
assigned when higher traffic level exists to ensure a conservative design
Other relations when direct test results are not available: For most fine-
grained soil or for materials with MR less than 210 MPa (30ksi)
58 | s h a h a d a T
Problem
59 | s h a h a d a T
Emulsified Asphalt Mixtures It is permissible to use emulsified asphalt
mixtures for base courses. Depending on aggregate types, three types of mixes
are specified:
60 | s h a h a d a T
Environmental Condition on Subgrade Materials
Problem
61 | s h a h a d a T
62 | s h a h a d a T
63 | s h a h a d a T
Problem
64 | s h a h a d a T
AI Procedure Design Flowchart (15)
65 | s h a h a d a T
AASHTO Design Procedure
Design Equation
1. Performance Period
a. Period of time that the initial pavement structure will last before it
requires rehabilitation.
b. Pavement deteriorates from the initial serviceability to the terminal
serviceability.
c. Designer or Government Agency selects the duration (typically 20
years).
2. Analysis Period
a. Time period that any design strategy must cover.
b. Can be equal to or greater than performance period.
c. Include the initial pavement service life plus one rehabilitation (Table
11.13). Usually maximum 50 years.
66 | s h a h a d a T
Reliability (“Safety Factor”) (16)
67 | s h a h a d a T
Serviceability (∆PSI) (15)
1. PSI or Present Serviceability Index – describing physical characteristics of
pavements which can be measured objectively and then related to subjective
evaluations of comfort (roughness, cracking, patching, rut depth)
2. ∆PSI=PSIi – PSIt
PSIi: initial serviceability (immediately after construction) ~4.2
PSIt: terminal serviceability (lowest acceptable level before remedial
action must be taken) dependent on roadway classification, typically
2.5 for highway
3. ∆PSI = ƒ (traffic, environment)
Loss of Serviceability
1. The total loss of serviceability can be computed with the following equation:
Where,
The effective roadbed soil resilient modulus is an equivalent modulus that would
result in the same damage if seasonal modulus values were actually used.
68 | s h a h a d a T
69 | s h a h a d a T
Structural Number (SN) (15)
Where:
ai = Layer Coefficients
mi = Drainage Coefficients
Di = Minimum Layer Thicknesses
Design: use design SN number to calculate minimum layer thickness Di
Solution not unique – cost analysis, construction consideration
Figure 11.25
70 | s h a h a d a T
Layer Coefficients (ai)
71 | s h a h a d a T
Minimum Layer Thicknesses (Di)
72 | s h a h a d a T
73 | s h a h a d a T
Advantages of AASHTO Procedure
1. Straight forward.
2. Inclusion of reliability and standard deviation.
3. Can be applied to a variety of traffic, climate, material condition.
74 | s h a h a d a T
LEC 18-19
RHD Design (Math)
International method which form the basis of RHD Design guide (13)
This RHD Pavement Design Guide has been prepared based on two
internationally recognized design standards, namely the AASHTO Pavement
Design Manual and the TRL Overseas Road Note 31, with a view to making
the design of road pavements as straightforward as possible and to ensure that
the same standards are adopted for all RHD roads.
For both the geometric and pavement design of new roads, or the upgrading /
widening of existing roads, traffic counts must be undertaken to establish the
current Average Annual Daily Traffic (AADT) on the road. At least one whole
day (24 hour) traffic count in both directions of flow should be undertaken on a
typical weekday for sections of the road having more or less the same traffic
volumes.
For geometric design purposes the forecast traffic demand for the road
in the design year should be estimated expressed in passenger car units
(PCUs). This determines the required capacity or width of the road and details
of this design procedure are contained in the RI-ID Geometric Design Manual.
For the design of road pavements, a different approach is adopted in that
an estimate must be made of the cumulative number of heavy axle loads that
the road pavement will be subjected to over its design life. In this cars,
rickshaws and other light traffic may be ignored with only trucks and other
commercial vehicles being considered.
For single carriageway roads the average truck and commercial vehicle
flow in both directions is adopted for design purposes i.e. 0.5 x the sum of both
directions. For dual carriageways, where trucks may be more heavily loaded in
one direction than the other, the' pavement for each carriageway should be
subject to a separate design based on the forecast commercial traffic for that
carriageway (heaviest loaded lane).
For new roads and the full depth reconstruction of existing roads the following
design standards are to be adopted:
75 | s h a h a d a T
Pavement Design Traffic Growth Rate
Life
National Road 20 years 10% pa
Regional 20 years 7% pa
Road
Table 2: Pavement Design Life and Traffic Growth Rates
For pavement design purposes all heavy commercial vehicles are expressed
in terms of the equivalent number of standard axles that they represent. A
Standard Axle is taken to be 8,160 kg. Based on axle load studies previously
undertaken in Bangladesh, the following equivalence factors have been
determined:
Vehicle Category Equivalence Factor
Large Truck (dual axle) 4.8
Medium Truck (Single axle) 4.62
Small Truck 1.0
Large Bus 1.0
Mini Bus 0.5
Table 3: Vehicle Equivalence Factors
Using the recorded (or estimated) AADT for the above vehicle categories
together with their equivalence factors, estimates should be made of the current
daily ESAs for the road. This should then be multiplied by 365 to obtain the
annual ESAs for the road.
To obtain the cumulative ESA loading over the design life of the road, the
current annual ESA loading should be multiplied by one of the following factors:
The above factors have been derived from the following compound growth
formula:
76 | s h a h a d a T
The above factors have been derived from the following compound growth
formula:
(Note: For National Roads r = 10% and n = 20 years; For Regional Roads r=7%
and n = 20 years)
77 | s h a h a d a T
4. Determination of Improved Sub-Grade Thickness.
Q: In Bangladesh how the low CBR Problem is assessed? (13,16)
It can be seen from the foregoing design chart that it assumes a minimum sub-
grade strength pf 5% CBR. In Bangladesh, apart from higher ground within the
Chittagong Hill Tracts where in situ CBRs will be higher, most roads are
constructed on embankments that will have a CBR of less than 5%. Under
these circumstances an improved sub-grade layer should be provided as
follows:
In all cases, sub-grade material with a CBR of less than 2% should be removed
and replaced with fill material complying with Section 2.6 of the RHD
Specification.
1. 1m to 1.2m above 50-year HFL measured from the HFL to the road top
at embankment edge
2. 0.30 m above 50-year HFL measured from HFL to top of subgrade
(bottom of pavement)
3. 1.5 m above ponding level measured from stagnant water level to top of
subgrade (to avoid saturation of subgrade owing to capillary action).
4. Highest level calculated from the above three criteria shall be applicable.
In case of Zila roads 20-year I-IFL may be considered.
78 | s h a h a d a T
The embankment height for important new roads such as bypasses must be
designed strictly in accordance with these freeboard guidelines. For upgrading
existing roads, especially in built-up areas, the freeboard may have to be
reduced for other considerations.
79 | s h a h a d a T
Problem (15)
80 | s h a h a d a T
81 | s h a h a d a T
82 | s h a h a d a T
LEC 20-22
Rigid Pavement (Math)
AASHTO Rigid Pavement Design
Modulus of Subgrade Reaction
The property of roadbed soil to be used for rigid pavement design is the modulus
of subgrade reaction k, rather than the resilient modulus MR. It is therefore
necessary to convert MR to k. As with MR, the values of k also vary with the
season of the year, and the relative damage caused by the change of k needs
to be evaluated.
Without Subbase
If the slab is placed directly on the subgrade without a sub - base, AASHTO
suggested the use of the following theoretical relationship based on an analysis
of a plate-bearing test:
Without Subbase
If a subbase exists between the slab and the subgrade the composite modulus
of subgrade reaction can be determined from fig 12.8. The modulus is based
on subgrade of infinite depth and is denoted by k∞
83 | s h a h a d a T
Rigid Foundation at Shallow Depth
Equation 12.22 and Figure 12.18 are based on a subgrade of infinite depth. If
a rigid foundation lies below the subgrade and the subgrade depth to rigid
foundation DSG is smaller than 10 ft (3 m), then the modulus of subgrade
reaction must be modified by the chart shown in Figure 12 .19. The chart can
be applied to slabs either with or without a subbase.
84 | s h a h a d a T
85 | s h a h a d a T
Effective Modulus of Subgrade Reaction
-----------------------------Equation -12.30
86 | s h a h a d a T
Computation
87 | s h a h a d a T
Explanation of Columns in Table 12 .1 7
88 | s h a h a d a T
89 | s h a h a d a T
Loss of Subgrade Support
90 | s h a h a d a T
Thickness Design
Problem-1 (VVI, 2016)
91 | s h a h a d a T
92 | s h a h a d a T
Problem-2
93 | s h a h a d a T
PCA Rigid Pavement Design
1. Fatigue Analysis
Edge loads produce the worst stresses. Fatigue based on tensile stress
due to edge loads. Fatigue analysis is based on the edge stress midway
between the transverse joints, with the most critical loading position being
shown in Figure 12.9 Because the load is near the mid slab far away from the
joints, the presence of the joints has practically no effect on the edge stress.
When a concrete shoulder is tied onto the mainline pavement, the magnitude
of the critical stress is reduced considerably. The cumulative damage concept,
is used for fatigue analysis.
94 | s h a h a d a T
in which Dr is the damage ratio accumulated over the design period due to all
load groups.
2. Erosion Analysis
in which C2 = 0.06 for pavements without concrete shoulders and 0 .94 for
pavements with tied concrete shoulders. With a concrete shoulder, the corner
deflection is not significantly affected by the truck load placement, so a large
C2 should be used. The percent erosion damage should be less than 100%.
95 | s h a h a d a T
Damage Analysis (Memorize the eqn)
Damage is based on fatigue cracking only. For fatigue cracking damage ratio
accumulated over the design period due to all load group is
If Dr <1 then load is less than allowable. The allowable number of repetitions
can be expressed as
96 | s h a h a d a T
Problem (15)
97 | s h a h a d a T
98 | s h a h a d a T
99 | s h a h a d a T
Comparison between AASHTO and PCA method of Rigid Pavement
Design Procedure (15)
AASHTO PCA
Based on reliability, using mean Does not consider reliability, but
values for all variables incorporates load safety factors an d
more conservative material
properties
Based on the equivalent 18-kip (80- Considers both fatigue cracking and
kN) single-axle load applications and foundation erosion, using actual
does not distinguish the type of single- and tandem-axle loads .
distress
Following parameter values are A load safety factor of 1 .2 and the
assumed: : same Sc of 650 psi and k of 100 pci
reliability R = 95%, standard deviation are assumed.
So = 0.35, serviceability loss ∆PSI =
2.0 (pt = 2.5), drainage coefficient Cd
= 1 .0, load transfer coefficient J = 3.2
without concrete shoulders and 2.5
with concrete shoulders, concrete
modulus of rupture Sc = 650 psi and
modulus of subgrade reaction k = 100
pci.
The use of the AASHTO equation for The ESAL obtained by the PCA
thin pavements, such as concrete method is more reasonable, at least
shoulders, is less conservative for thinner pavements.
100 | s h a h a d a T
LEC 22
Soil Stabilization
1. Macadam Road (13)
2. Prime Coat
a. A prime coat is an application of liquid bituminous material to a
previously untreated base or wearing surface. The bituminous
material penetrates the surface and is generally completely
absorbed.
b. The prime coat serves to promote adhesion or "bond" between the
base and wearing surface. Secondly, it serves to consolidate the
surface on which the new treatment is to be placed. Thirdly, it may
function to a certain extent as a deterrent to the rise of capillary
moisture into the wearing surface.
101 | s h a h a d a T
c. The material used in the prime coat should be liquid asphalt or road
tar of low viscosity and high penetrating qualities.
3. Tack Coats
a. A "tack coat" is defined as a single application of bituminous material
to an existing bitumen, Portland cement concrete, brick or block
surface or base. Its purpose is to provide adhesion between the
existing surface and the new bituminous wearing surface.
b. Tack coats are very frequently applied to old surfaces of various
types as a first step in the construction of a new bituminous wearing
surface. As in the case of prime coat, it is absolutely essential that
the surface to which the material is applied be clean and dry. The
bituminous material is applied be clean and dry.
102 | s h a h a d a T
LEC 23
Construction Equipment
Types of Equipment
103 | s h a h a d a T