2)compare the price quotation for selecting the vendor.
Selection criteria: a) best price and quality b)credit terms c) hidden charges if any.
These are done by Murgan sir by co-ordination with
Head of accounts and Head of Engineering.
1) Purchase order preparation (done by Gomathi
madam)
1. Material tracking 2. Collecting Delivery challan duly sign by engineering person. 3. Documentation.
(These are done by Satish sir)
1. Original bills collection and taking photo copy
2. Original bills filling for GST 3. Photo copy bills submitted to Satish sir.
(These are done by VL madam)
1. Attaching Mat. Req., Purchase order, Delivery challan and Invoice are done by Satish sir 2. Vendor Documents (R, PO, DC, I) are submitted to Raghu for Tally posting.
(Co-ordination B/W accounts and Purchase)
1) After tally posting, Vendor Documents are to be reconciliation by
Raghu or VL mam and put pass for payment seal
Vendor Documents are
submitted to Head of accounts Mismatched vendor for getting signature and then documents are send to Satish filed to outstanding files sir to rectify the documents (Inter Co-ordination with accounts Departments)
Send to engineering Department for EAP process
vendor documents are to be filed in
outstanding files
Finally, payments were made based on trade credit days or demand of