ID Task Name DurationStart Finish Planned % March 2018

complete 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15
1 RM Building Alembic 79 daysTue 13-02-18Wed 02-05-18 20%
2 Phase -1 79 daysTue 13-02-18Wed 02-05-18 20%
3 Foundation 40 daysTue 13-02-18Sat 24-03-1840%
4 Pad Footing 1 day Tue 13-02-18Tue 13-02-18100%
5 Column (14 nos) 1 day Sat 24-02-18Sat 24-02-18100%
6 Ground Beam 10 daysThu 15-03-18Sat 24-03-180%
7 Rebaring/Welding2 days Thu 15-03-18Fri 16-03-18 0%

8 reinforcement Laying
2 days Fri 16-03-18 Sat 17-03-180%
9 Shuttering 2 days Sat 17-03-18Sun 18-03-180%
10 Concreting 1 day Mon 19-03-18 Mon 19-03-18 0%
11 back filling & compaction
2 days Wed 21-03-18 Thu 22-03-180%
12 Floor PCC 1 day Sat 24-03-18Sat 24-03-180%
13 Staircase 5 days Wed 14-03-18 Sun 18-03-180%
14 Shuttering 3 days Wed 14-03-18 Fri 16-03-18 0%
15 Concreting 2 days Sat 17-03-18Sun 18-03-180%
16 Ground floor Works 30 daysMon 26-02-18 Tue 27-03-1810%
17 Column 1 day Mon 26-02-18 Mon 26-02-18 100%
18 Lift 3 & 4 4 days Sat 10-03-18Tue 13-03-180%
19 Rebaring 1 day Sat 10-03-18Sat 10-03-180%
20 Reinforcement Laying
1 day Sun 11-03-18Sun 11-03-180%
21 Shuttering 1 day Mon 12-03-18 Mon 12-03-18 0%
22 Concreting 1 day Tue 13-03-18Tue 13-03-180%
23 Lift 1 & 2 5 days Tue 13-03-18Sat 17-03-180%
24 Rebaring 2 days Tue 13-03-18Wed 14-03-18 0%
25 Reinforcement Laying
2 days Wed 14-03-18 Thu 15-03-180%
26 Shuttering 2 days Thu 15-03-18Fri 16-03-18 0%
27 Concreting 2 days Fri 16-03-18 Sat 17-03-180%
28 Staircase 9 days Mon 19-03-18 Tue 27-03-180%
29 Shuttering 7 days Mon 19-03-18 Sun 25-03-180%
30 Reinforcement Laying
6 days Wed 21-03-18 Mon 26-03-18 0%
31 Concreting 5 days Fri 23-03-18 Tue 27-03-180%
32 Block Masonary 3 days Sat 10-03-18Mon 12-03-18 0%
33 Internal Plaster 6 days Mon 12-03-18 Sat 17-03-180%
34 1st Floor Works 29 daysThu 08-03-18Thu 05-04-180%
35 Column 2 days Thu 08-03-18Fri 09-03-18 0%
36 Shuttering (6nos) 2 days Thu 08-03-18Fri 09-03-18 0%

37 Concreting (6nos)2 days Thu 08-03-18Fri 09-03-18 0%

38 Lift 3 & 4 7 days Wed 14-03-18 Tue 20-03-180%


39 Rebaring 3 days Wed 14-03-18 Fri 16-03-18 0%
40 Reinforcement Laying
4 days Thu 15-03-18Sun 18-03-180%
41 Shuttering 4 days Fri 16-03-18 Mon 19-03-18 0%
42 Concreting 4 days Sat 17-03-18Tue 20-03-180%
43 Lift 1 & 2 7 days Sun 18-03-18Sat 24-03-180%

Task External Tasks Manual Task Finish-only Progress


Split External Milestone Duration-only Deadline
Project: Project3 PCC working 1
Date: Sat 10-03-18 Milestone Inactive Task Manual Summary Rollup Baseline
Summary Inactive Milestone Manual Summary Baseline Milestone
Project Summary Inactive Summary Start-only Baseline Summary

Page 1
ID Task Name DurationStart Finish Planned % March 2018
complete 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15
44 Rebaring 3 days Sun 18-03-18Tue 20-03-180%
45 Reinforcement Laying
4 days Mon 19-03-18 Thu 22-03-180%
46 Shuttering 4 days Tue 20-03-18Fri 23-03-18 0%
47 Concreting 4 days Wed 21-03-18 Sat 24-03-180%
48 Staircase 9 days Wed 28-03-18 Thu 05-04-180%
49 Shuttering 7 days Wed 28-03-18 Tue 03-04-180%
50 Reinforcement Laying
6 days Fri 30-03-18 Wed 04-04-18 0%
51 Concreting 5 days Sun 01-04-18Thu 05-04-180%
52 Block Masonary 5 days Tue 13-03-18Sat 17-03-180%
53 Internal Plaster 6 days Fri 16-03-18 Wed 21-03-18 0%
54 2nd Floor Works 37 daysFri 09-03-18 Sat 14-04-180%
55 Column 2 days Fri 09-03-18 Sat 10-03-180%
56 Shuttering (6nos) 2 days Fri 09-03-18 Sat 10-03-180%

57 Concreting (6nos)2 days Fri 09-03-18 Sat 10-03-180%

58 Lift 3 & 4 7 days Wed 21-03-18 Tue 27-03-180%


59 Rebaring 3 days Wed 21-03-18 Fri 23-03-18 0%
60 Reinforcement Laying
4 days Thu 22-03-18Sun 25-03-180%
61 Shuttering 4 days Fri 23-03-18 Mon 26-03-18 0%
62 Concreting 4 days Sat 24-03-18Tue 27-03-180%
63 Lift 1 & 2 7 days Sun 25-03-18Sat 31-03-180%
64 Rebaring 3 days Sun 25-03-18Tue 27-03-180%
65 Reinforcement Laying
4 days Mon 26-03-18 Thu 29-03-180%
66 Shuttering 4 days Tue 27-03-18Fri 30-03-18 0%
67 Concreting 4 days Wed 28-03-18 Sat 31-03-180%
68 Staircase 9 days Fri 06-04-18 Sat 14-04-180%
69 Shuttering 7 days Fri 06-04-18 Thu 12-04-180%
70 Reinforcement Laying
6 days Sun 08-04-18Fri 13-04-18 0%
71 Concreting 5 days Tue 10-04-18Sat 14-04-180%
72 Block Masonary 5 days Sun 18-03-18Thu 22-03-180%
73 Internal Plaster 6 days Thu 22-03-18Tue 27-03-180%
74 3rd Floor Works 49 daysTue 06-03-18Mon 23-04-18 0%
75 Column 9 days Tue 06-03-18Wed 14-03-18 0%
76 Beam 8 days Tue 06-03-18Tue 13-03-180%
77 Shuttering 6 days Tue 06-03-18Sun 11-03-180%
78 Reinforcement Laying
6 days Wed 07-03-18 Mon 12-03-18 0%
79 Concreting 1 day Tue 13-03-18Tue 13-03-180%
80 Slab 8 days Tue 06-03-18Tue 13-03-180%
81 Shuttering 6 days Tue 06-03-18Sun 11-03-180%
82 Reinforcement Laying
6 days Wed 07-03-18 Mon 12-03-18 0%
83 Concreting 1 day Tue 13-03-18Tue 13-03-180%
84 Lift 3 & 4 7 days Wed 28-03-18 Tue 03-04-180%
85 Rebaring 3 days Wed 28-03-18 Fri 30-03-18 0%
86 Reinforcement Laying
4 days Thu 29-03-18Sun 01-04-180%

Task External Tasks Manual Task Finish-only Progress


Split External Milestone Duration-only Deadline
Project: Project3 PCC working 1
Date: Sat 10-03-18 Milestone Inactive Task Manual Summary Rollup Baseline
Summary Inactive Milestone Manual Summary Baseline Milestone
Project Summary Inactive Summary Start-only Baseline Summary

Page 2
ID Task Name DurationStart Finish Planned % March 2018
complete 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15
87 Shuttering 4 days Fri 30-03-18 Mon 02-04-18 0%
88 Concreting 4 days Sat 31-03-18Tue 03-04-180%
89 Lift 1 & 2 7 days Sun 01-04-18Sat 07-04-180%
90 Rebaring 3 days Sun 01-04-18Tue 03-04-180%
91 Reinforcement Laying
4 days Mon 02-04-18 Thu 05-04-180%
92 Shuttering 4 days Tue 03-04-18Fri 06-04-18 0%
93 Concreting 4 days Wed 04-04-18 Sat 07-04-180%
94 Staircase 9 days Sun 15-04-18Mon 23-04-18 0%
95 Shuttering 7 days Sun 15-04-18Sat 21-04-180%
96 Reinforcement Laying
6 days Tue 17-04-18Sun 22-04-180%
97 Concreting 5 days Thu 19-04-18Mon 23-04-18 0%
98 Block Masonary 5 days Fri 23-03-18 Tue 27-03-180%
99 Internal Plaster 6 days Tue 27-03-18Sun 01-04-180%
100 4th Floor Works 47 daysSat 17-03-18Wed 02-05-18 0%
101 Column 7 days Sat 17-03-18Fri 23-03-18 0%
102 Reinforcement Laying
6 days Sat 17-03-18Thu 22-03-180%
103 Shuttering 3 days Tue 20-03-18Thu 22-03-180%
104 Concreting 2 days Thu 22-03-18Fri 23-03-18 0%
105 Beam 13 daysSun 25-03-18Fri 06-04-18 0%
106 Shuttering 9 days Sun 25-03-18Mon 02-04-18 0%
107 Reinforcement Laying
8 days Wed 28-03-18 Wed 04-04-18 0%
108 Concreting 2 days Thu 05-04-18Fri 06-04-18 0%
109 Lift 3 & 4 7 days Wed 04-04-18 Tue 10-04-180%
110 Rebaring 3 days Wed 04-04-18 Fri 06-04-18 0%
111 Reinforcement Laying
4 days Thu 05-04-18Sun 08-04-180%
112 Shuttering 4 days Fri 06-04-18 Mon 09-04-18 0%
113 Concreting 4 days Sat 07-04-18Tue 10-04-180%
114 Lift 1 & 2 7 days Sun 08-04-18Sat 14-04-180%
115 Rebaring 3 days Sun 08-04-18Tue 10-04-180%
116 Reinforcement Laying
4 days Mon 09-04-18 Thu 12-04-180%
117 Shuttering 4 days Tue 10-04-18Fri 13-04-18 0%
118 Concreting 4 days Wed 11-04-18 Sat 14-04-180%
119 Staircase 9 days Tue 24-04-18Wed 02-05-18 0%
120 Shuttering 7 days Tue 24-04-18Mon 30-04-18 0%
121 Reinforcement Laying
6 days Thu 26-04-18Tue 01-05-180%
122 Concreting 5 days Sat 28-04-18Wed 02-05-18 0%
123 Block Masonary 5 days Wed 28-03-18 Sun 01-04-180%
124 Internal Plaster 6 days Sun 01-04-18Fri 06-04-18 0%
125 M.R & O.H.T 24 daysMon 26-03-18 Wed 18-04-18 0%
126 Bottom Slab 6 days Mon 26-03-18 Sat 31-03-180%
127 Shuttering 5 days Mon 26-03-18 Fri 30-03-18 0%
128 Reinforcement Laying
3 days Wed 28-03-18 Fri 30-03-18 0%
129 Concreting 1 day Sat 31-03-18Sat 31-03-180%

Task External Tasks Manual Task Finish-only Progress


Split External Milestone Duration-only Deadline
Project: Project3 PCC working 1
Date: Sat 10-03-18 Milestone Inactive Task Manual Summary Rollup Baseline
Summary Inactive Milestone Manual Summary Baseline Milestone
Project Summary Inactive Summary Start-only Baseline Summary

Page 3
ID Task Name DurationStart Finish Planned % March 2018
complete 09 11 13 15 17 19 21 23 25 27 01 03 05 07 09 11 13 15
130 Column/Shear wall 6 days Wed 04-04-18 Mon 09-04-180%
131 Reinforcement Laying
6 daysWed 04-04-18 Mon 09-04-180%
132 Shuttering 3 days Thu 05-04-18Sat 07-04-180%
133 Concreting 2 days Sat 07-04-18Sun 08-04-180%
134 Top Slab 8 days Wed 11-04-18 Wed 18-04-180%
135 Shuttering 6 days Wed 11-04-18 Mon 16-04-180%
136 Reinforcement Laying
5 days Fri 13-04-18 Tue 17-04-180%
137 Concreting 1 day Wed 18-04-18 Wed 18-04-180%

Task External Tasks Manual Task Finish-only Progress


Split External Milestone Duration-only Deadline
Project: Project3 PCC working 1
Date: Sat 10-03-18 Milestone Inactive Task Manual Summary Rollup Baseline
Summary Inactive Milestone Manual Summary Baseline Milestone
Project Summary Inactive Summary Start-only Baseline Summary

Page 4
April 2018 May 2018
15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04

Task External Tasks Manual Task Finish-only Progress


Split External Milestone Duration-only Deadline
Project: Project3 PCC working 1
Date: Sat 10-03-18 Milestone Inactive Task Manual Summary Rollup Baseline
Summary Inactive Milestone Manual Summary Baseline Milestone
Project Summary Inactive Summary Start-only Baseline Summary

Page 5
April 2018 May 2018
15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04

Task External Tasks Manual Task Finish-only Progress


Split External Milestone Duration-only Deadline
Project: Project3 PCC working 1
Date: Sat 10-03-18 Milestone Inactive Task Manual Summary Rollup Baseline
Summary Inactive Milestone Manual Summary Baseline Milestone
Project Summary Inactive Summary Start-only Baseline Summary

Page 6
April 2018 May 2018
15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04

Task External Tasks Manual Task Finish-only Progress


Split External Milestone Duration-only Deadline
Project: Project3 PCC working 1
Date: Sat 10-03-18 Milestone Inactive Task Manual Summary Rollup Baseline
Summary Inactive Milestone Manual Summary Baseline Milestone
Project Summary Inactive Summary Start-only Baseline Summary

Page 7
April 2018 May 2018
15 17 19 21 23 25 27 29 31 02 04 06 08 10 12 14 16 18 20 22 24 26 28 30 02 04

Task External Tasks Manual Task Finish-only Progress


Split External Milestone Duration-only Deadline
Project: Project3 PCC working 1
Date: Sat 10-03-18 Milestone Inactive Task Manual Summary Rollup Baseline
Summary Inactive Milestone Manual Summary Baseline Milestone
Project Summary Inactive Summary Start-only Baseline Summary

Page 8