Un-encumbered Length availability

Construction of Four Lane (Partial Access Controlled) Laddowal Bypass


from Km. 0.00 to Km. 17.041 Linking NH-95 with NH-1 via Laddowal Seed
Farm at Ludhiana in the State of Punjab on Hybrid Annuity Mode.

S.No Description Unit Length Remarks

1 Total Length of the Project Km 17.041

2 Encumbrances due to
Length affected due to Canal From Ch 0+000 to 4+500 BHS Approval
A (Approvals awaited from Irrigation Km 2.250 awaited from Irrigation Department,Govt. of
department) Punjab

From Ch14+800 to Ch17+041, Award has


B Length affected due to Land Acuisition Km 2.241 been declared and compensation pending

Ch 4+500 to Ch 5+100 (BHS) compensation


Length affected due to compensation of
C Km 0.600 of structure has not been paid
structures in LA
From Ch 8+500 – 8+700 and Ch 9+100 –
Length affected due to Poplar trees in 10+500 (i.e. a linear length of 900m) are
D Km 0.900 occupied by “popular trees” in Pvt Land
Private Land

A few locations affected by Tube wells &


E Miscellaneous due to Tube Wells & Utility Km 0.200 Utility shifting( Non deposition of Supervision
charges)

Balance available for Work Km 10.850

Percentage Unencumbered length


% 63.7
available for work