Anda di halaman 1dari 30

Achieving Drilling-Performance Improvement

in Horizontal Tight-Gasfield Development

T he full-field development plan


for the Khazzan project in Oman
is based on drilling approximately
is cemented in place before fracturing
operations. Figs. 1 and 2 are schematics
of the well designs.
cluding downhole weight on bit (WOB),
downhole torque measurement, and
pressure-while-­drilling measurement;
300 wells targeting gas-producing The targeted reservoir is either Barik and selection of downhole tools.
horizons at measured depths of or Amin sandstone, both of which have a A core aspect of the strategy is to in-
approximately 6000 m with 1000‑m high unconfined compressive strength crease the power available at the bit. The
horizontal sections. The first attempt (exceeding 35,000 psi). The Barik sand- application of high-torque motors and
to drill these wells had to overcome stone is at the upper margins of the glob- the latest generation of drilling turbines,
many drilling challenges, including al rock-strength envelope. Indeed, when coupled with an improved understanding
wellbore instability and drilling core samples were analyzed by the bit of downhole drilling dynamics, promotes
dysfunctions. This paper shows manufacturer, the strength far exceed- the efficient transfer of energy from the
how the application of existing ed any of their global stock of reference topdrive to the bit face.
technologies and processes is rock samples. Several drilling dysfunctions were
leading to performance gains and Horizontal drilling in these hard-rock experienced in the first horizontal well,
improvements in wellbore quality. conditions presents several challenges: and it was recognized that, by address-
◗◗Hard rock and slow rate of ing each of these issues, hole quality and
penetration (ROP) drilling dynamics could be improved. A
Introduction ◗◗High levels of shock and greater efficiency in transferring power
BP has embarked on an appraisal drilling vibration to the bit, therefore, could be achieved.
campaign that targets a tight gas reser- ◗◗Polycrystalline-diamond-
voir in northern Oman. The subject field compact (PDC) -bit cutter Mud Weight. Once it was confirmed
is an area of approximately 2800  km2 durability that the first well was suffering from
and contains the Cambrian Barik, Miqrat, ◗◗Drillpipe fatigue ­borehole-stability problems, the mud
and Amin reservoirs. ◗◗Wellbore stability weight was increased from a specif-
The field-development plan is based ◗◗Torque and drag management ic gravity of 1.31 to 1.39. This helped
on a deep-horizontal-well design. When ◗◗High downhole static minimize wellbore breakouts that were
the appraisal phase began, there was very temperatures up to 143°C a result of redistribution of the bore-
limited experience within the country in hole stresses caused by hole deviation
drilling deep horizontal gas wells. Other Challenges to Project Delivery in those formations. The elevated mud
operators in Oman were mostly drilling The 12¼- and 8½-in. hole sections weight was maintained to the well total
vertical gas wells. There were no analog consume more than 80% of the total depth and was applied to the second well
data available on horizontal wells in the drilling time; therefore, improving the with positive results.
Barik reservoir. ROP and bit-run longevity would have
The wells will be drilled vertically to clear benefits for project economics. A Equivalent Circulating Density (ECD).
approximately 4000-m measured depth hard-rock drilling strategy was devel- Managing the ECD helps maintain the
before building up and landing to hori- oped. This strategy targeted drilling mud weight within a safe window. There-
zontal in the Barik or Amin reservoir. An practices and procedures; optimization fore, it is one of the measurements that
8½×8⅜-in. 1000-m horizontal interval of ­bottomhole-assembly (BHA) design; should be monitored continuously with
is drilled, and a 7×4½-in. tapered liner usage of logging-while-drilling tools, in- a downhole pressure-while-drilling tool.

Time Dependency. The wellbore in the


This article, written by Special Publications Editor Adam Wilson, contains highlights
build section was deteriorating over
of paper SPE 166699, “Achieving Drilling-Performance Improvement in Horizontal
time. This issue has been observed only
Tight-Gasfield Development,” by Mohamed Najwani, SPE, Yaseen Najwani, SPE, on horizontal wells; no wellbore dete-
and Hani Al Lawati, BP Exploration (Epsilon); Colin Cockburn, SPE, BP Exploration rioration was observed on vertical wells.
Operating Company; and Mohammad Reza Heidari, SPE, and Martin Sanderson, Both Barakat and Mabrouk forma-
SPE, Schlumberger, prepared for the 2013 SPE/IADC Middle East Drilling Technology tions have high clay contents, which
Conference and Exhibition, Dubai, 7–9 October. The paper has not been peer reviewed. may react with water and swell. To ex-

For a limited time, the complete paper is free to SPE members at www.spe.org/jpt.

154 JPT • OCTOBER 2014


Subsurface safety valve

18⅝-in. casing

13⅜-in. casing

9⅝-in. casing

7×4½-in. liner hanger

5½-in. 23 lbm/ft×4½-in. 17 lbm/ft S13CR tubing

7×4½-in. tapered liner


Kickoff point, 4114 m Four fracture stages
measured depth
below rotary table

Maximum dogleg
severity, 4.4°/30 m

Landing point, 4784 m Total depth, 5784 m


measured depth measured depth
Fig. 1—Barik horizontal-well design.

amine the chemical reactiveness of Torque and Drag Management. The Hole Quality and Borehole Spiraling.
these formations, the operator under- deep-kickoff well design, coupled with In the problematic build section of the
took a series of detailed laboratory tests high WOB requirements, leads to a risk first horizontal well, the caliper log re-
on samples. This revealed that shales of pipe buckling around the kickoff vealed that an increasingly severe spiral-
in this location are relatively inactive; point. This limits weight transfer and ing pattern was present in the wellbore.
therefore, chemical deterioration was can increase the risk of drillstring fail- This had been initiated while drilling
deemed to be only a minor contributor to ure. Heavyweight drillpipe is spaced with a rotary BHA in the vertical zone,
borehole degradation. across this interval to reduce the risk of and it continued with the turbine drill-
The instability is believed to be re- buckling and improve transfer of weight ing assembly. Ultimately, a stiff rotary
lated to tectonic stresses combined and torque to the bit. BHA with multiple roller reamers was
with weak laminated clays, which will Torque levels were approaching required to clear the worst of the undu-
tend to collapse when disturbed by string limitations by the end of the first lations and enable drilling to continue.
drilling activities. horizontal well. This situation resulted The spiraling signatures in the verti-
partly from earlier problems stemming cal part of the first well were mainly asso-
Hard Reaming. The wellbore quality de- from a mechanical sidetrack. High side ciated with excessive stabilizer spacing,
teriorated after extensive hard reaming. forces were evident as the drillstring short bit-gauge length, and poor wellbore
The wireline-caliper log confirmed that passed across the sidetrack interval. condition. The stabilizer interval pro-
the borehole enlargement was more se- Friction factors were analyzed as drill- vided a self-perpetuating spiral pattern;
vere where hard reaming had been im- ing progressed through the abrasive- each stabilizer followed the repeated un-
plemented. Both Barakat and Mabrouk sandstone interval, and the torque pro- dulations in the wellbore and caused the
formations have laminated weak bed- jections were updated continually. bit to continue the spiral pattern. The
ding planes, which break out because of Where possible, steering intervals were overgauged hole reduced the effective-
harsh drillstring vibration. minimized to reduce wellbore tortuos- ness of the stabilizers and allowed off-
Once the deteriorated wellbore con- ity, although there were tight direction- center rotation to be established.
dition was understood, a rotary-steerable al constraints to be maintained. Torque Dynamic and static BHA analysis
system was introduced. This provided a was also reduced by enhancing hole- was made to predict BHA behavior. A va-
smoother buildup, with improved weight cleaning practices. It was observed that riety of BHA designs were modeled with
transfer to the bit and less detrimental on-bottom and off-bottom torque will a long-gauge PDC bit. The results showed
shock and vibration energy being im- drop after performing a cleanout cycle in that the optimum BHA for maintaining
parted to the wellbore. the horizontal hole. low side forces at the bit was a point-the-

156 JPT • OCTOBER 2014


Subsurface safety valve

18⅝-in. casing

13⅜-in. casing

9⅝-in. casing

7×4½-in. 5½-in. 23 lbm/ft×4½-in. 17 lbm/ft S13CR tubing


liner hanger

Kickoff point, 4510 m


7×4½-in. measured depth
tapered liner below rotary table Six fracture stages

Maximum dogleg
severity, 4.4°/30 m

Landing point, 5179 m Total depth, 6179 m


measured depth measured depth

Fig. 2—Amin horizontal-well design.

bit rotary-steerable system coupled with turbine BHA with a bend limited the sur- The oversized borehole in the first
a low-speed, high-torque motor. Another face revolutions-per-minute value for op- well had a major effect on increasing
purpose of running a high-torque, low- timum hole cleaning. Under these condi- the shock and vibration in the drill-
speed motor was to deliver the power to tions, several instances of packoffs were string by increasing the lateral free-
the bit from a downhole drive system in- experienced, which, in turn, contributed dom of the BHA. Further adjustments
stead of from the topdrive, hence reduc- to further wellbore degradation. were clearly required to improve dy-
ing the surface torque and wasted energy In the next well, a rotary-steerable namics. Dynamic simulation resulted in
caused by drillstring and BHA dysfunc- system was run in the build section, which the recommendation to use a combined
tions. The low-speed aspect of the motor helped increase the cuttings-carrying ca- rotary-steerable system and a high-
was to aid bit durability when drilling the pacity, although it was still necessary torque, low-speed motor as the most
abrasive formation. to drill with turbines and diamond- stable BHA to drill the vertical and the
impregnated bits through the horizontal build sections.
Hole Cleaning. Drilling the horizontal reservoir. High-angle hole-cleaning prac-
sections through hard rock at a slow tices were implemented, contributing to Bit Wear. The horizontal reservoir sec-
ROP should not, in itself, lead to a hole- improved hole quality. tion is hard and abrasive with occasion-
cleaning problem. The turbines that are al interbedded clays, to the extent that
used in the horizontal section generate Shock and Vibration. Shock and vibra- these formations are not yet considered
fines as opposed to PDC-bit cuttings, and tion and stick/slip are common issues in PDC-bit drillable. This interval is, there-
these fines should be easier to remove hard-rock drilling operations. There is fore, drilled with diamond-impregnated
from the wellbore. The ROPs are so low very little dampening of shocks because bits and turbines. The analysis from the
that the system should see minimal sol- of the hard-formation/BHA interface, second well showed more than 30% of
ids loading. leading to greater severity and increased the average bit-run time had been spent
However, under certain circumstanc- frequency of shocks. High WOB is typ- on tripping, so bit durability is a key to
es, hole cleaning can become an issue even ically required, especially in PDC-bit performance improvement.
under these slow hard-rock conditions. In drilling, which contributes to increased A high-speed turbine improved the
Well 1, wellbore instability resulted in in- levels of stick/slip. ROP by more than 25%, but the aver-
creased solids loading in the wellbore, The most severe shock and vibra- age bit-run length was less than 160 m.
coupled with overgauged hole and the as- tion were experienced in the first well Diamond-impregnated bits require op-
sociated reduction in annular velocities. through the build section. This resulted timized WOB not only to maximize the
The flow rate was also restricted because in reduced ROP and bit life and in BHA ROP but also to extend the bit life. It has
of high turbine pressure losses. Having a and drillstring failures. been found that running higher WOB in-

158 JPT • OCTOBER 2014


0
prompt mitigation with corrosion in-
500 hibitors as necessary.
Barik Well 1 Barik Well 2
1000
Directional Control. In the first well,
Depth (meters below rotary table)

1500
steering the well path within the tight tol-
2000 erances of the directional plan was chal-
2500 lenging and, in some cases, resulted in
tripping out of hole for a correction run.
3000
In the vertical part of the first well,
3500 stabilizer spacing was too long, which al-
4000 lowed the BHA to deviate from vertical.
4500
Reducing the stabilizer spacing and run-
ning a vertical rotary-steerable system
5000 helped eliminate drifting the well from
5500 vertical and minimized spiraling.
6000
0 25 50 75 100 125 150 175 200 225 250 275 300 325 350 375 Results and Additional
Time Performance Improvement
Fig. 3—Time vs. depth curve showing significant improvement on the second well. The first horizontal well had experienced
multiple nonproductive-time events,
creased the ROP to some extent but re- has been revised for all drillstring com- and, ultimately, the reservoir section had
duced the bit life substantially. ponents. This involved following the to be sidetracked before finally achieving
highest service level for directional- the required 1000-m horizontal interval
Downhole-Tool Reliability. There were drilling tools and applying the most rig- in Hole 2.
several downhole-tool or drillstring orous inspection procedure for drillpipe Application of lessons learned in the
failures in both wells, which required and heavyweight drillpipe. A corrosion- first well enabled construction time for
extra prevention or mitigation to ex- monitoring program was put in place the second well to be reduced by 53%
tend the tools’ reliability. To mitigate to monitor corrosion levels from the and cost to be lowered by more than 30%
these failures, the inspection program water-based drilling fluid and provide (Fig. 3). JPT

Under the Patronage of the Ministry of Oil, State of Kuwait


His Excellency Dr. Ali Saleh Al-Omair, Minister of Oil and Minister of State for National Assembly Afairs, State of Kuwait

HEAVY OIL INNOVATIONS BEYOND LIMITATIONS

Register today at www.spe.org/go/hoce


Exhibition space is still available—book now!

Titanium Sponsor Platinum Sponsors Gold Sponsor Gala Dinner Sponsor Lanyards and
Day One Luncheon
Sponsor

Silver Sponsors Exclusive Delegate Stationery Sponsor


Bag Sponsor

JPT • OCTOBER 2014 159


SPE 62893

Cementation of Horizontal Wellbores


S. A. McPherson, SPE, BJ Services Co. Ltd

Copyright 2000, Society of Petroleum Engineers Inc.


demonstrate how horizontal casings and liners can be
This paper was prepared for presentation at the 2000 SPE Annual Technical Conference and cemented with equal success to vertical ones. Cementing
Exhibition held in Dallas, Texas, 1–4 October 2000.
practices and procedures used successfully to cement
This paper was selected for presentation by an SPE Program Committee following review of horizontal zones in the North Sea will be reviewed and
information contained in an abstract submitted by the author(s). Contents of the paper, as
presented, have not been reviewed by the Society of Petroleum Engineers and are subject to discussed. In addition, data from a number of BP Amoco’s
correction by the author(s). The material, as presented, does not necessarily reflect any
position of the Society of Petroleum Engineers, its officers, or members. Papers presented at Wytch Farm wells will be presented.
SPE meetings are subject to publication review by Editorial Committees of the Society of
Petroleum Engineers. Electronic reproduction, distribution, or storage of any part of this paper
Since BP Amoco’s extended reach drilling work started at
for commercial purposes without the written consent of the Society of Petroleum Engineers is Wytch Farm in 1993, they have continually increased the
prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300
words; illustrations may not be copied. The abstract must contain conspicuous boundaries of horizontal drilling, most recently completing
acknowledgment of where and by whom the paper was presented. Write Librarian, SPE, P.O. well number 1M-18-SP. The longest well drilled from M-Site
Box 833836, Richardson, TX 75083-3836, U.S.A., fax 01-972-952-9435.
was 1M-16-SP. An outline of the well bore follows:
• vertical pre-set 26inch conductor at 25m
Abstract
• 18-5/8inch casing set at 260m within the Top Chalk
This paper outlines the cement slurry design methodology
• 13-3/8inch casing set within the Oxford Clay at 1009m
used to cement one of the world’s longest horizontal well
measured depth and 764m vertical depth.
bores. The work detailed has been carried out on ‘M-Site’ of
BP Amoco’s Wytch Farm Development on the south coast of • 9-5/8inch casing being set in the Top Sherwood reservoir
Dorset, England, over the past 4-5 years. Of the 17 wells, so at 7451m measured depth and 1590m vertical depth.
far completed on M-Site, none have required remedial • 8-1/2-inch section to a total depth of 11,278m – making
cementing work and all reservoir sections exhibit satisfactory this the world’s longest horizontal section to date.
zonal isolation, as confirmed by bond log results. The • 7inch liner set at vertical depth of 1610m and a total
formations to be drilled exhibit very low fracture gradients, depth of 10,210m.
with the possibility of losses during the cement job constantly At the time of writing, 4 wells in excess of 9,000m MD have
present. been drilled and cemented at BP Wytch Farm.
The discussion compares and contrasts cementing techniques As with any project of this size and duration, changes have
between vertical and horizontal casings. It looks at procedures been introduced to the procedures and recommendations, to
and concerns common to both, then describes how downhole allow improvements in job performance, cost efficiency,
temperature calculation and some lab testing techniques, were safety and environmental issues. To account for this evolution
modified to account for the nature of the horizontal well bore. process, the discussion will focus on the cementation of the
Output from the computer temperature simulator confirmed liner sections of the last 4 or 5 wells.
assumptions made earlier in the project. Details of the slurry The 12 ¼” and 8 ½” open hole sections were drilled with
design criteria and testing procedures are discussed. The slurry low toxicity oil based mud having the properties detailed in
properties included zero free water and low fluid loss, along Table 1.
with considerable thickening times, to allow for correct
placement. Spacers and Pre-flushes
The discussion includes hole cleaning measures, and the It is accepted throughout the industry, that increased
influences of mechanical contribution, such as centralisers and displacement and circulation rates offer direct improvements
pipe movement. Spacers and flushes with controlled flow in mud removal, allowing better bonding to pipe and
regimes have been used to provide optimum mud and solids formation and improved zonal isolation. All the liner cement
removal. In addition, an outline of the computer simulation jobs in the Wytch Farm development have used large volumes
programme used for well bore analysis is shown to be of spacers and pre-flushes. At the start of the extended reach
invaluable to the design engineer, by allowing modification of work liner well bores were prepared for cementing using a
many inputs very quickly. base oil pre-flush followed by a weighted water based spacer,
at about half way between the mud and cement densities. This
Introduction system had repeatedly provided the cement slurry with a
As exploitable petroleum deposits are found in increasingly substantial base for good bonding to the pipe and formation, as
harsh environments so, the technical limits of each discipline borne out by the cement bond logs run on wells M08 and
are stretched to meet this demand. This paper aims to M10, and that no remedial work has ever been required. At
2 S.A. MCPHERSON SPE 62893

this time the average displacement rate for liner jobs was in annular surfaces, offering improved bonding to both pipe and
the region of 6-8bpm. During planning for well M11 (the first formation. In addition, the density and rheological properties
well with a liner set at greater than 10,000m MD), it was noted of the spacer help prevent channelling of the cement through
that the displacement rate would have to be reduced to the previous fluids.
approximately 4bpm to ensure the fracture pressure of the A summary of the spacer properties is shown in
formation was not exceeded during cementing. Table 2.
Work done previously by Lockyear, Ryan and
Gunningham1 indicated, that as flow rate decreases, so the Slurry Design
degree of channeling increases, except where water is being Cement Type and Slurry Density. The extended reach work
displaced. In addition, due to the increased ease of gaining a at Wytch Farm has all been done at vertical depths of less than
turbulent flow regime, less viscous fluids are more effective at 1800m, for which the drilling programme states a reservoir
displacing more viscous ones. Based on this work and the temperature of 150-165degF. The slurries are mixed with neat
previous successful well cementations, it was decided to Class ‘G’ cement and sea water to 1.92S.G. (16ppg).
introduce a water only phase to the current spacer system. This (Although land based, Wytch Farm does not have a ready
led to the use of a number of fluids with varying densities and supply of fresh water.) The 16ppg slurry density ensures the
flow regimes. In addition, density differences can help reduce generation of a sheath of cement with competent compressive
channelling of the cement during placement 1. strength development to properly support the casing.
Since well number M11, the following fluids have been
used ahead of the cement on liner cementations. Typically 100 Test Temperature. In order for the laboratory testing to
barrels of base oil is pumped first, due to its compatibility with closely simulate circulation along the extended horizontal
the low toxicity, solids laden oil based mud used for drilling. section, the API temperature tables detailed in Spec. 10a2 are
With its viscosity of 1-2cp the base oil is in turbulent flow, only used to determine the bottom hole static temperature
even at very low pump rates. This allows improved mud (BHST). The calculation of the bottom hole circulating
removal throughout the annulus, especially below the pipe, temperature is based on the assumption, that at some
where mud tends to get trapped. The base oil thins and horizontal distance from a vertical well bore, cold fluids
removes mobile mud ahead of it and contributes greatly to the pumped from surface will have been exposed to the well
breakdown of filter cakes and pockets of immobile mud. The temperature for sufficient time to warm up to BHST
base oil flush is followed by 75 barrels of sea water. Again the conditions. As a result of this, it is assumed all fluids will
turbulent flow regime of this fluid promotes the removal of reach the bottom hole static temperature by the time they are
immobile mud on the low side of the annulus. displaced to the total measured depth of the well. To simulate
Seventy-five barrels of water based spacer containing a this all laboratory work is carried out at ambient (surface
surfactant, is weighted to part way between the density of the conditions) and bottom hole static temperatures. This
mud and the cement slurry, using barite. Weighting this fluid assumption has been verified using a computer based well
ensures the equivalent density of fluids in the annulus does not temperature simulator.
fall below the pore pressure of the formation. The surfactant Graph 1 details the well temperature simulator output for
aids the break down and removal of immobile mud and will well number 1M-16-SP, over the duration of the 7” liner
prevent the formation of any incompatibility products at the cementation. At the start of the simulation, it is assumed the
spacer/mud interface. As with vertical wells, incompatibility well is in (worst case) static conditions. In this case the bottom
between oil based mud and water based spacer is usually hole static temperature taken from the Drilling Programme,
manifest as the generation of a thick mixture resembling 165degF, is used. The computer programme accounts for the
“putty”. Depending on severity, these incompatibility products pumping of all the fluids detailed in the spacer section, along
can be of great detriment to hole cleaning by changing the with the required amount of cement slurry. As the job
calculated flow regime to something less effective, or by progresses the cold fluids pumped from surface force the well
creating a blockage. In addition, the spacer yield point is kept temperature to decrease. At the end of the simulation the
low to promote turbulent flow and cuttings removal. temperature at the toe of the liner is approximately 164degF,
A second sea water flush of 75 barrels follows the showing that in this case the bottom hole circulating
weighted spacer to reduce the ECD and therefore the pressure temperature is not measurably different from the bottom hole
on the formation. The sea water contains the same surfactant static temperature. Laboratory testing was therefore carried
as the weighted spacer, which in conjunction with the out at 165degF, bottom hole static temperature.
turbulent flow regime of this fluid, continues the attack on
immobile mud pockets in the annulus. Thickening Time. Inherent with the extended length of both 9
The final fluid ahead of the cement slurry is a further 75 5/8” casing strings and the liners, is the requirement for
barrels of water based spacer. Mixed to the same design as the extended slurry thickening times to compensate for the large
previous weighted spacer pill, it has mutual solvent added at displacement volumes. In addition, real well situations can be
the same loading as the surfactant. The density of the fluid and different from the simulated ones and a long thickening time
the surfactant content work in the same way as before. The allows the displacement rate to be reduced, if required, during
mutual solvent dramatically improves the water wetting of the the job. Building-in safety margins to slurry thickening times
SPE 62893 CEMENTATION OF HORIZONTAL WELLBORES 3

allows the cementer and rig site personnel to deviate from the slurry to the permeable reservoir section, liner slurries for use
simulated programme, if well conditions dictate. This at Wytch Farm, must have an API fluid loss of less than 80mls
flexibility can be used, for example, to heal a fracture created in 30min, tested with a differential pressure of 1000psi and at
during cementing in a previously unseen weak spot, by bottom hole static temperature. This level of fluid loss from
reducing pump rate and therefore ECD. the slurry generates a thin sacrificial filter cake, which
On average, liner slurry designs have a thickening time of prevents further loss of fluid from the slurry during
10 hours, with the cement job taking in the region of 5-7 displacement.
hours. The cement slurry used on the liner for well 1M-16-SPz The Wytch Farm development is oil producing and does
had a thickening time of 15 hours, with the job taking 81/2 not have a requirement for gas migration control within
hours to complete. cement slurries.

Free Water. Cement slurries with long thickening times, Rheology. API rheology measurements are taken, using a
tested at BHST inherently take a long time to set when in the standard Fann 35 rheometer, at ambient and bottom hole static
annulus. This has an effect on more than just the drill out time temperatures. These readings are used to determine a number
of the shoetrack or when the liner lap can be pressure tested. of characteristics about the fluid. Its ease of mixing at the
Having the slurry in a liquid state for extended periods cement unit is of paramount importance as stoppages during
downhole can lead to increased free water generation and mixing and pumping will interrupt the planned flow regimes
solids segregation. Free water generation by cement slurries in of fluids already in the pipe and annulus. The fluid model
horizontal sections can be more detrimental to the overall which best represents the slurry can also be calculated and
annular isolation than the same percentage loss from slurries used to predict, among other things, expected pressures during
in vertical wells. In vertical wells, any free water released by the job and hole cleaning abilities. This information can then
the cement will migrate to the top of the cement column, be used to determine optimum pump rates and spacer designs.
resulting in the potential formation of fluid channels and poor For speed, the figures can be incorporated into computer based
well bore isolation. Unless the free water generation is very job simulation programmes, which generate information on
high this effect does not greatly influence vertical work. In more than just the critical factors stated above.
horizontal wells the top of the cement column runs the full
length of the well bore and any free water generated will result Other Testing. Inherent with the long open hole sections are
in poor bonding and possible communication along the high large annular volumes and consequently large amounts of
side of the well bore. cement are required to fully isolate the annulus. To ensure that
To guard against this, laboratory testing involves two cement used at the end of the job performs to the same
stability tests. The first is based around the API free water test. standard as that used at the start, the API thickening time of
Initially, it is carried out with the test cylinder vertical using the final slurry is re-tested with a second sample of cement
the procedure described in Spec. 10a.2. When the slurry design taken from a different sample point to the first. Only when
has passed this test it is re-tested with the test cylinder set at these two samples are within experimental error limits, is
45degrees inclination. For work at Wytch Farm the results for testing complete.
both these tests must be zero free water at bottom hole static Table 3 details the cement slurry lab results for 3 recent
temperature. liners.
The second stability test, The Segregation Tube Test3
allows empirical measurement of the density of the set slurry Well bore considerations During Displacement
over the height of the tube. The variation in density from the The ECD values seen while cementing horizontal wells vary
top to the bottom of the tube gives a clear indication of the greatly from those experienced with vertical wells. Graph 2
amount of settlement experienced during the setting of a compares ECD values calculated during the displacement of a
specific slurry design. For a Wytch Farm liner slurry to pass horizontal well (demarked by squares) with those for a vertical
the test, this variation must be less than 1.5% of the design well of the same length (demarked by triangles) using the
density. same fluids and displacement rates. As can be seen the vertical
well exhibits lower ECD’s for the majority of the job but these
Fluid Loss Control. Loss of mix water from the slurry, during rise by the end of the displacement to almost 0.7ppg higher
displacement, will reduce the slurry’s thickening time and than those seen in the horizontal well. This is due to the
increase its viscosity4. As the slurry loses water it will lay hydrostatic weight of the fluids having greater influence in the
down a filter cake, against the permeable formation wall. vertical instance.
Uncontrolled, this will change the flow regime of the slurry However, in a horizontal well, the weight of the fluids in
from the calculated one to some unpredictable alternative and the liner or casing, are spread along the length of the hole.
may result in excessive ECD being experienced during Centralisers applied using spacing that will support the casing
displacement. The filter cake will continue to grow over the off the bottom of the hole would have to be increased in
whole length of the permeable zone, and in extreme cases may number to support the extra weight of the cement in the
result in a total blockage of the annulus, preventing further casing. At Wytch Farm the number of centralisers used over
displacement. To reduce the amount of fluid lost from the the length of the liner section has fallen as later wells are
4 S.A. MCPHERSON SPE 62893

drilled, see discussion in Centraliser section. This allows the enhances well bore cleanup and cement placement. The blade
extra weight of the casing string to force the casing into design promotes turbulence of fluids in the annulus and
eccentricity. This change in well bore profile and narrowing of improves the removal of filter cake solids. The reduced stand-
the low side of the annulus can lead to decreased solids off achieved by this centraliser programme is compensated for
removal efficiency, pockets of trapped dehydrated mud and in the spacers and pre-flushes described earlier.
will alter the planned flow regimes of the hole cleaning The centralisation of the 7inch liner for well number 1M-
spacers ahead of the cement. To overcome this effect the 16-SPz differs from previous liners by using low torque
spacer system described earlier has been designed so that it centralisers. These units have rollers mounted on the outside
will provide effective annulus cleaning, before casing stand- and inside of the centraliser. The rollers on the outside are
off reduction becomes significant, and will be easily removed angled long the length of the pipe to reduce the forces seen
by cement slurry when required. When the leading edge of the while running pipe. They were run at one per joint, over the
cement leaves the shoe and enters the annulus, it initially length of the whole liner, without stop collars so that at the
passes along the high side of the hole. As more cement enters end of running each would sit at the high end of the pipe. The
the annulus, so the weight of the liner decreases allowing internal rollers allow the pipe to move inside the centraliser.
access to the low side. At this time any spacer previously This reduces friction experienced during rotation, compared to
trapped below the casing, is swiftly removed by the cement solid centralisers, as the pipe is only moved against the smooth
slurry. Due to the minimal effect upon ECD while cementing rollers, rather than the centralisers scraping against the well
shallow horizontal casings and liners, relatively high density, bore. Use of these low torque centraliers allowed the liner to
cement slurries can be passed through low fracture gradient be rotated for nearly the entire cement job.
formations in controlled conditions.
Movement of pipe
Centralisation Movement of the pipe, during pre-job circulation and
Regardless of well geometry, a minimum API stand-off of cementing, either by reciprocation or rotation has long been
67% is recommended to obtain a sound cement job. This accepted by the industry as beneficial to primary cementing
amount of clearance from the well bore allows sufficient operations. Moving the pipe has been shown to improve
access around the casing for good mud removal and correct cuttings and filter cake removal, and help break down mud
cement placement. When cementing liners, many operators gel. These advantages continue to hold true when considering
and service companies recommend a higher stand-off, in the horizontal or highly deviated wells. However, due to the
region of 80%, to ensure high quality cement job. As the nature of the well bore, pipe tends to lie along the bottom
deviation angle increases, the number of centralisers required, introducing additional torque and drag forces, which must be
to achieve these stand-off figures also increases. In addition, overcome.
compressible (bow type) centralisers have to overcome the Reciprocation raises a number of risks including, high
weight of the pipe as it lies along the low side of the well. This slack-off drag, which may prevent the casing from returning to
extra strain on the restoring force results in each centraliser bottom, perhaps leading to a liner not being set where
contributing less to the “lift” of the casing or liner from the designed. In addition, surge pressures greatly in excess of
low side of the well bore. In extreme cases the stand-off those experienced while running casing may be countered and
achieved will be lower than the minimum API in long casing strings, movement at the drill floor may not be
recommendation, perhaps only 60%. In response to this solid transmitted to where it is needed due to pipe stretch5.. These
centralisers, that are not be limited by restoring forces, are issues are only exacerbated as longer and longer casings and
used in highly deviated and horizontal well bores. liners are run.
Liner jobs for the Wytch Farm project have used solid For these reasons most liners are now set and released
centralisers from the outset of the extended reach programme. before pumping cement, and whenever possible, rotated. In
They were applied at 2 per joint over the whole length of the addition, when the casing/bore hole relationship is severely
liner and generated up to 90% stand-off. As the horizontal eccentric rotation appears to be more beneficial than
sections extended the forces required to run all these reciprocation 6. Rotation of the pipe requires sufficient torque
centralisers became too great and latterly they were only used to overcome the down hole forces. These include the weight of
over intervals which required a particularly high degree of the pipe (which is lying on the low side of the open hole with
zonal isolation. When the liner on 1M-10-SP was cemented little or no buoyancy), the weight of the cement slurry before
centralisers were used every 6m, over the required intervals, it leaves the pipe and the inherent restrictions associated with
this was stretched to every 24.4m for the liners on M-11 and (any) centralisers etc. Liners at Wytch Farm have been rotated,
M-12 and has remained between these values for the during circulation and cementing, at rates up to 30rpm. Since
remainder of the project. This change was mainly due to the well number 1M-10-SP, 7inch liners have been run in 8-½inch
increased running forces experienced with the extremely long open hole, with an average liner length of over 2330m.
liners. In addition, it has been found that, an excessive number Mathematical models can predict these operating forces, and
of centralisers would increase the rotational friction forces of should be used, to ensure the casing connections, the liner
the centraliser/well bore interface beyond manageable limits. hanger and the surface equipment are designed with the
The centralisers used have a spiral blade design, which required performance.
SPE 62893 CEMENTATION OF HORIZONTAL WELLBORES 5

Computer Simulations pipe to be rotated for the majority of the cement placement
Calculation of all the varying factors encountered during a process.
cement job can be very time consuming. It is not practical to
determine all the changes to all the interrelated factors Acknowlegements
experienced during the job by hand. Use of a computer The author wishes to thank BJ Services Co. Ltd. and BP
simulation programme gives much more versatility to the Amoco and partners in the Wytch Farm oilfield for permission
design engineer. Fluid flow regimes and pump rates can be to publish this work. Thanks also to Steve Gill, Dan Daulton
changed within seconds and the effects of these changes and Graham Want (Snr. Service Supervisor) of BJ Services
studied many times over. Many parameters including fluid Co. Ltd.
type and rheology, pump rates, well trajectory and excess
cement handling, are used by the simulation’s algorithms to References
generate the job. 1. Lockyear, C.F., Ryan, D.F., Gunningham, M.M., “Cement
As mentioned above the anticipated well bore temperature Channeling: How to Predict and Prevent”, SPE 19865.
during the job is also modelled using a computer simulation Presented at the SPE Annual Technical Conference and
programme. Using similar information as above it calculates Exhibition held in San Antonio, 8-11 October 1989
2. American Petroleum Institute, Specification for Well Cements
the temperature along the well bore during the pumping, 10a, 21st Edition, 1 September 1991
shutdowns and displacement, of the cement job. 3. Greaves, C., Hibbert, A., “Test Improves Measurement Of
The output of the programmes can be shown graphically, Cement Slurry Stability”, Oil and Gas Journal, 12 February
or as text listings, alternatively both can be incorporated in to 1990
a more detailed report. 4. Cook, C., Cunningham, W., “Filtrate Control – A Key in
These computer simulations can also be used for real time Successful Cementing Practices”, SPE 5898. Presented at the
data collection and post-job analysis. In real time mode the Rocky Mountain Regional Meeting, May 11-12, 1976
engineer can study the well bore as the job is being pumped, 5. Buchan, R., Little, M.T.S., “Innovative Techniques Improve
allowing any necessary adjustments to be made. The post job Liner Cementation in North Sea Wells; An Operator’s
Experience”, SPE 15896. Presented at the SPE Conference held
analysis mode allows the engineer to review jobs already in London, 20-22 October 1986
pumped, so that authentic job information to be fed back into 6. Haut, R.C., Crook, R.J., “Primary Cementing: The Mud
the job design process. Displacement Process”, SPE 8253
7. BP Amoco Exploration, Wytch Farm Stage 111 Development,
Post-Job Data Drilling Programme Revision 1, 3 February 1999
Due to their inherent cost cement bond logs are not usually run
on every well within a development. At Wytch Farm cement Author’s Note
logs have been taken twice since well number 1M-10-SP, in In the text reference is made to API Spec 10a dated 1991.
both cases to verify cement coverage for dual Please note that this was the most recent issue of the
producer/injector wells. During the each test the casing was specification at the start of the project and that test procedures
filled with sea water and there was no pressure applied during have been continually compared against more recent issues, as
logging. Conclusions from both these tests found that the they have become available.
required zonal isolation had been achieved and completion
was to continue as planned. In addition, none of the liners
within the development have reported poor zonal isolation or
required remedial work.

Conculsion
Excellent well bore isolation at Wytch Farm has primarily
been successful through the application of the well grounded,
cementing practices. Due to the limitations on reciprocation of
the pipe and the low fracture gradient of the formation,
annular cleaning has been achieved by other techniques.
Implementation of the multiple spacers, each with a different
flow regime, has allowed improved hole cleaning, while
reducing the placement ECD. The thin low fluid loss slurry is
easy to mix and pump, yet provides excellent zonal isolation
and pipe support. The ability to simulate the job on computer
ensured that the fluid’s rheology and density, were beneficial
to the job objectives and that the effects of any changes were
accounted for. In addition, the novel use of centralisers, with
rollers during well 1M-16-SPz allowed this long section of
6 S.A. MCPHERSON SPE 62893

Table 1
12 ¼” Open Hole 8 ½” Open Hole
Weight (PPG) 10.0 – 10.4 9.60 – 10.0
PV (cp) 40 – 60 15 – 20
YP (lb/100ft2) 28 – 32 10 – 14
Stability (volts) >400 >400
Fluid Loss (mls) @ 200degF <5 <4
Oil / Water 60 / 40 70 / 30
Fluid Base Base Oil Base Oil

Table 2
Pumping Order 1 2 3 4 5
Weight (PPG) 7.8 8.55 11.5 8.55 11.5
PV (cp) 1 1 8.5794 1 8.5794
YP (lb/100ft2) - - 3.2612 - 3.2612
Surfactant Concentration - - 2 2 2
(gal/bbl)
Mutual Solvent Concentration - - - - 2
(gal/bbl)
Minimum Rate for Turbulent 0.3746 0.34375 3.1327 0.34375 3.1327
Flow (bbls/min)

Graph 1 – Bottom Hole Temperature v’s Time @ 1610m TVD


SPE 62893 CEMENTATION OF HORIZONTAL WELLBORES 7

Table 3
1M-14-SP 1M-15-SP 1M-16-SP
Test Temperature (degF) 160 150 165
Time to 50Bc (Hrs:Min) 9:52 13:17 14:42
Time to 70Bc (Hrs:Min) 10:02 13:27 14:55
Time to 100Bc (Hrs:Min) 10:11 13:39 15:10
API Freewater (%) 0 0 0
Fluid Loss (mls) 72 80 54
Rheology @ Test Temperature 78 79 68
600 rpm
300 rpm 42 44 36
200 rpm 30 32 24
100 rpm 17 18 14
6 rpm 3 4 3
3 rpm 2 3 2
Compressive Strength Development @ Test Temperature 32 hrs; 32hrs; 32hrs; 3272psi
2108psi 2000psi

Graph 2 – Comparison of ECD values calculated in Horizontal and Vertical wells

12

1 1 .5

11
ECD at Shoe Depth (ppg)

1 0 .5

10

9 .5

8 .5

8
0

60

12

72

33

93

53

13

73

00

24

48

72

87

99

11

23

35
12

18

24

30

36

40

44

50

56

62

68

72

77

83

89

95

10

10

11

11

12

13

13

14

14

14

14

14

14

15

15

15

V o lu m e o f F lu id P u m p e d ( b b ls )
.
1+
aOdMydmrc+lulaFe&,
-@

SPE 39647

Chemical Wellbore Plug for Zone Isolation in Horizontal Wells


Nestor F. Saavedra, SPE, Ecopetrol, Daulat D. Mamora, SPE, Texas A&M U., David B. Burnett, SPE, Westport Tech.
Center Int., and Frank M. Platt; SPE, Texas A&M U.

Copyright 1998, Society of Petroleum Engineers, lnc

Tfds paper wss pi’epared fof pmsentafioir at the 199S SPE/OOE Impfov.sd Oil RecoveIY Introduction
Symposium held in Tulsa, Otdahoma, 1S-22 P+ril 199S.
Although horizontal drilling is not a new idea,’ less than 50
This paper was selected for pmsentafiin by an SPE Prcgram Commitfes following review of
mfcimation cmntained in an abstract submtied by the author(s), Contents of the paper, as “modem” horizontal wells had been drilled worldwide by
presented, have no! been reviswed by the %cisty G+Petroleum Engineers and am subject to
cl%-r@fksr by the suftr@s). The matarisl, as presented, does not necessarily raffed any
1986.2 This number rose significantly in the next few years as
position of the Society of Petrolswn Engineers, its off”m, or memhs Paprs presented af “booms” occurred in the Pearsall and Giddings Austin chalk
SPE meetings ere subjed io pubfkdon mviow by E@!oriaI Committees of the %=ciety of
Petroleum Engineers. Elacfmnic rsprcducfii. dlstrlwtion, c+ storage of any part of this paper fields and in the Bakken formation in North Dakota and
for czwnmercial purposes wifhcd tfm wriffsn consent cd ths Society of Petroleum Engineers is
prohibited Pwrnisalon to mproducs in jxfnf is res!rfcfetf to an abstract of rwf mom than 3c0
Montana. Activity levels then flattened in the U. S., and
words illustratkms may not tM copied The ebsfr@d must ccotain conspicuws horizontal drilling stabilized at about 8V0 of the rig count.
Wkmw@dgment cd where and by wlwrn fhe papsr was presentsd Wriie Librarian. SPE, P.O
BOX ~, R-tiard-, TX 750S3-3836. U S A, W 01 -972-952-S435 Horizontal drilling has been made possible by technological
advances in the drilling, completion, formation evaluation,
stimulation, and production of horizontal wells: DriIling
Abstract breakthroughs include dual-powerhead mud motors,
A new technique for zone isolation in horizontal wells has retrievable whipstocks, and routine multiple lateral wells.3
been developed and tested in the laboratory. The technique With the current technology, horizontal drainhole distances
consists of three sequential stages: (i) setting a chemical that are much longer than the fracture lengths achieved by
wellbore plug upstream of the problem zone, (ii) spotting and hydraulic fracturing are possible at moderate costs.
squeezing a gel into the problem zone, and (iii) washing or The two main types of completion for horizontal wells are
drilling out excess gel and the wellbore plug to clean the openhole, and cased and cemented.4 Openhole completions
borehole prior to production. may be subdivided into three types, namely, true open hole
Two main problems were investigated using laboratory completions, slotted or preperforated liner/casing, and
horizontal wellbore models: (a) placement of the wellbore segmented uncemented liner/casing (Fig. 1). The true open
plug so that slumping would not occur, and (b) selection and hole completion is the simplest and cheapest to execute.
testing of chemicals that could be used to make wellbore plugs Slotted or preperforated liners are run to help prevent
with suftlciently high holding pressures. The horizontal borehole collapse. Slotted liners are generally used in
wellbore models consisted of PVC pipes internally lined with unconsolidated formation, while preperforated liners are used
sand. Three chemicals, used in the oil industry for gas and/or for consolidated formation. The use of uncemented liners has
water shut-off, were selected for the study: a monomer, a the disadvantage that, for remedial treatments, there is no way
polyacrylamide, and a plastic. The x-ray CT scanner was used to control the injection of fluids into the formation. The use
to obtain cross-sectional images of the plug to help understand of segmented uncemented liners allow open hole evaluation of
the shear mechanisms involved. the wellbore and subsequent selective stimulation. Using
Experimental results indicate that a plug could be placed in a liners, segments of the wellbore may be isolated if port collar
horizontal wellbore with minimum slumping if the plug is tools are run in conjunction with external casing packers.
introduced into a viscous completion brine pill. For the plastic Cased and cemented completions are used for certain
plugs, the completion brine contained 100,000 ppm NaC1 and conditions. Perforation and stimulation costs are so
4 lb/bbl carboxyl methyl cellulose, Only the plastic plug had significant for this completion type that it is only used if
a suftlciently high holding pressure (343 psi for 37 in. long problems associated with the wellbore and formation can not
plug of 1 in. diameter). The experimental study indicates the be remedied in any other ways
proposed zone isolation technique to be viable. Research is Thus, more than 90% of horizontal wells have openhole
being continued to evaluate the effectiveness of the wellbore completions. Wells completed on poorly consolidated sands
plug during displacement of formation gels. are generally equipped with prepacked gravelpack, wire-

435
2 N. F. Saavedra, D. D.Mamora,D. B. Burnett,F. M, Platt SPE 39647
wrap-pealscreens, or slotted liners, to control sand production. 2. 1/4 in. plastic tubing - representing the coiled tubing -
Consequently, there is complete fluid communication at the attached to a positive displacement pump.
reservoir interface throughout the horizontal section.G 3. An electrically-heated temperature jacket which provided
An interval(s) along the horizontal section may encounter the required reservoir temperature (150 ‘F), in which the
early gas andlor water breakthrough due to cresting or plexigkiss tubing (weIlbore) was placed.
extraneous production from a high permeability streak or A typical experiment would be conducted as follows.
tlacture. Although certain intervals along the horizontal Completion brine was prepared by dissolving sodium chloride
section are affected, the totaI well production rate may be in water for the required salt concentration. If the experiment
significantly reduced for the foIlowing reasons. First, when also required the use of CMC (carboxyl methyI celluIosej as a
water breaks through in a horizontal well, water blockage may placement fluid, then a CMC mixture in water of 4 Ibibbl was
occur, since: (i) the flowing pressure differential in the prepared. The completion fluid was poured into the plexiglass
wellbore is typically very small,’ and (ii) the lows of the tube which was filled to excess. The plexiglass tube was
undulating sections of the well act as water traps. Water placed completely in a horizontal constant-temperature jacket,
blockage thus results in reduced oil production rate. Second, whose temperature had already stabilized at 150 “F for several
when early water and/or gas breakthrough occurs, oil flow hours. Liquid gel (to form the chemical wellbore plug) was
capacity into the well and in the wellbore maybe significantly prepared and placed in a reservoir connected to a- positive
reduced. Consequently, the ability to shut off high water displacement pump. Gel concentration varied depending on
and/or gas producing zones in a horizontal well would result the chemical used. The liquid gel was injected at 400 cc/rein
in increased production and profitability.* and spotted at the center of the plexiglass tube via-the 1/4 in.
However, zone isoIation in a horizontal well with open hole plastic tubing attached to the outlet of the pump. Total gel
completion or uncemented pipe is not a trivial job for two volume placed in the plexiglass tube varied between 50 to 300
main reasons. First, since there is fluid communication at the cc. The pIastic tubing was removed and the geI was Ieft to
reservoir interface, spotting and squeezing a zone isolation cross-link and age, to form the chemical wellbore plug. The
material (e.g. a gel) across the zone of interest could result in plexiglass was later removed and profile of the wellbore plug
the material being squeezed into other intervals that are to be was observed and its dimensions measured.
left untouched. Second, zone isolation materials are generally
denser than the workover brine, so that the material may Holding Pressure. Apparatus for determination of the
slump on the low side of the hole. To alleviate these holding pressure of the chemical wellbore plug consisted of
problems, inflatable straddle packers have been used to isolate the following main components (Fig. 3).
the zone to be treated. However, these packers may not seal 1. PVC pipes of various sizes md lengths, with the inside
against the wellbore wall if the hole is badly washed out or is wall lined with sand to simulate the roughness of a
very irregular in shape, For slotted-liner completions, there is wellbore in a sandstone reservoir, Sand-lining was
no mechanical way of sealing off the liner-borehole annulus.9 achieved by applying PVC cement evenly to the inside
Consequently, a zone isolation method has been developed wall of the PVC pipe, followed by sand.
which would utilize a chemical wellbore plug instead of a 2 Positive displacement pump for injecting water into the
mechanical packer. The wellbore plug gel would be spotted PVC pipe. A pressure transducer was used to measure the
using coiled tubing just upstream of the problem zone, injection fluid pressure.
penetrating the liner slots before hardening to take the shape 3. Electric oven.
of the wellbore, thus providing annular seal and holding 4. Data logger and personal computer system to record
pressure. A formation gel would be spotted across and pressure transducer readings.
squeezed into the problem zone. Upon hardening, the gel 5. HD 200 x-ray CT scanner,
would fimish an impermeable block against undesirable fluid A typical experiment would be conducted as foIlows. A
production. PVC tube (wellbore) - with one end capped - was filled with
gel and then placed vertically in an oven set at 150 ‘F. After
Experimental Apparatus and Procedure the gel had cured to form a chemical wellbore plug, the
Two main types of experiments were performed in this study, capped end was sawn off, while the other end was connected
namely, evaluation of placement techniques, and measurement to the positive displacement pump. Water was slowly injected
of holding pressure of the chemical wellbore plug. into the PVC pipe. Injection pressures were recorded at 5-
second intervals. The injection pressure would begin to fall
Gel Placement. The apparatus (Fig. 2) consisted of the after reaching a peak value that corresponded to the holding
following main components. pressure of the wellbore plug. The PVC pipe was CT scanned
1. 4 ft. long by 1.5 in. I.D. straight plexiglass tube, which to obtain a profile of the wellbore plug and the channel
represented the horizontal wellbore. One end of the tube through which the injected water traversed the wellbore plug.
was cappd. The other end had a right-angle extension
which was open to ensure the tube was completely till Chemicals Used. Chemicals used in the experiments were,
when placed in the horizontal position. namely, a monomer, a polyacrylamide, and a plastic.

436
SPE 39647 CHEMICAL WELLBORE PLUG FOR ZONE ISOIATION IN HORIZONTAL WELLS 3
Mmmters. Monomers are the units that form a polymer, Pfaxficpkg. The plastic gel was more uniform in size and
and thus have lower molecular weight and lower viscosity no dispersion was observed (Table 2). No slumping occurred
than a polymer. Monomers are used to improve conformance, for brine concentration greater than 160,000 ppm.
thus oil-displacement efficiency, in water injection wells in
the following manner, 10 The low-viscosity monomer solution Brine yield point. A brine concentration of 160,000 ppm KC1
is injected into the formation where it polymerizes to form a for a plastic gel would result in severe fluid losses in practice.
high-viscosity gel. As more monomer solution enters the Following the cement plug placement technique.of Calvert et
higher permeability layers of the formation, more high- al.,’4 in which a high density and high yield point brine was
viscosity polymers are formed in those areas. Thus, injected used to prevent cement slumping, experiments were carried
water is diverted into the less permeable parts of the formation out to determine the brine yield point (and density) required to
that have received less water, resulting in a more uniform and prevent gel slumping.
efilcient injection profile. First, the increase in brine yield point with addition of
Poiyacrylamides. These consist of carbon-carbon chains CMC and NaC1 was studied. Experiments involved dissolving
to which are attached amine groups, possibly tens of the required amount of NaCl in 700 g of water, followed by
thousands of them, resulting in molecular weights in the the addition of CMC. After blending, yield point of the brine
millions. In its pure form, the polymer is electrically neutral, was measured. The results indicate that NaCl concentration
and would appear to preclude any crosslinking by ionic had negligible effect on brine yield point (Fig. 4).
bonding. However, when mixed with a small amount of Second, gel slumping tests were conducted in which the
alkaline solution (e.g. sodium hydroxide), or when heated to a gels were placed in horizontal tubes containing brine of
high temperature, some of the amine groups react to form different yield point and density. As the results (Table 3)
carboxylate groups that are negatively charged, thus making show, gel slumping could be avoided at considerably lower
ionic crosslinking possible to form a polymer called partially brine density if the brine yield point was increased. For
hydrolyzed polyacryhunide (PHPA).}1 The fraction of amine plastic gel, for example, no slumping occurred for a lower
groups converted to carboxylate groups is called the degree of brine density of 100,000 ppm (9 lb/gal) KCI if the brine yieId
hydrolysis @lZ), with values typically varying from Oto 60’XO. point is greater than 59 lb/100 sq.ft.
Typical cross-linkers for PHPA are trivalent metal ions such
as aluminum (A1+3)121and chromium (Cr+3). Gel placement rate. Gels were placed in horizontal tubes at
Piastics. Because of their physical strength, thermosetting various injection rates to study the effect of injection rate on
plastics are often used to seal off fractures, vugs, channels, gel slumping. Results indicate that each gel type had a
and perforations, and are aIso used for sand consolidation. minimum injection rate to prevent slumping (T’able 3).
They are also used, in less concentrated form, for zone Because of its high density, plastic gel had a minimum
isolation. Phenolic, epoxy and furfiuyl alcohol plastics are injection rate of 1450 cc/hr to prevent slumping.
commonly used for this purpose in the field. 13
Holding Pressure Experimental Results
Gel Placement Experimental Results Holding pressures were measured for the three chemical
Experiments were conducted to evaluate the effect of brine wellbore plugs, placed in PVC pipes internally lined with
density, brine yield point, and gel placement rate on gel sand. For a particular PVC pipe I.D., the length of the plug
slumping. The results are described as follows. was increased in steps, tlom as short as 1 in. to as long as 37
in. The polyacrylamide and monomer plugs were cured at
Brine density. These tests were conducted for polyacrylamide 150”F, while the plastic plug (highly exothermic curing
and plastic gels. Slumping occurred when the gel was placed reaction) was allowed to form at room temperature for safety
in a horizontal welIbore filled with water, To alleviate the reasons.
problem of gravity segregation, the use of a high-density
completion brine was investigated as follows, Sixteen 20 ml. Polyacrylamide plug. Figure 5 shows a graph of injection
test tubes were fiIIed with 15 ml of KC1 brine with KCI pressure versus time for a typical polyacrylamide plug. As
concenti”titfv@@Timr 50,000 ppm to 250,000 ppm KC1. can be seen ffom Fig. 5, the injection pressure increases up to
5 ml of gel was then placed in each of the test tubes. The 16 a maximum and then drops with continued injection. The
test tubes were placed in an oven at 150 “F for eight hours holding pressure of the plug corresponds to the maximum
atler which they were taken out to observe the gel formed. injection pressure obtained (14 psi). At the holding pressure,
Poiyacryiamide piug. The gel was formed at different the gel failed Wd water broke through the gel.
Ievek in the test tube depending on the polyacrylamide and An interesting observation was the effect of aging time on
brine concentrations (Table 1). The gel was formed at the top the holding pressure. Figure 6 shows that the optimum aging
of the test tube (i.e. no slumping) for 5 wt% polyacryhunide time for the polyacrylamide plug is about five hours. Afier
gel in brine of greater than 150,000 ppm KC1, and for 10 vvt% one to two hours, the gel was formed but after about five
polyacrylamide gel in brine of greater than 17,500 ppm KC1. hours the gel achieved optimum consistency. A conservative
Dispersion of the gel occurred at Iow brine concentrations. eight hours of aging was used in all subsequent tests. The

437
4 N. F. Saavedra, D. D. Mamora, D. B. Burnett, F. M. Platt SPE 39647
effect of plug length on holding pressure is shown in Figs. 7 in Table 4 and plotted in Fig. 17. Figure 17 indicates that the
and 8 for plug diameters of 0.5 in. and 1 in., respectively, for holding pressure is independent of plug diameters studied.
polyacrylamide concentration of 5 wt%. The holding pressure The linear increase in holding pressure with plug length (Figs.
increases up to an optimum length, beyond which it remains 16 and 17) maybe described by the following relationship.
constant with increasing plug length, indicating an optimum
plug length of six to eight times the plug diameter. Holding pressure (psi) = 9 x plug length (in.)
Holding pressure tests were conducted for different
polyacrylamide concentrations (5 wt% and 10 wt%) and Several cross-sectional images of a plastic plug were
polyacrylamide:cross-linker ratios (11: 1 and 5.5:1), Figure 9 obtained using a CT scanner. Figure 18 is typfca[ of these
shows that increasing polyacrylamide concentration increases images. It can be seen that the injected fluid leaks through a
the holding pressure to about 20 psi, which is still low for gap created between the plug surface and the inner ‘wallof the
practical purposes. PVC pipe, and not through a fracture in the plug as in the case
A PVC pipe cut at the outlet end revealed a shear or of polyacrylamide and monomer plugs. This explains the
fi-acture through which the injected water broke through the different behavior of the plastic plug and provides insight into
gel. The existence of a fracture throughout the plug was the different mechanisms affecting holding pressure. The
corroborated by a CT scan cross-sectional image taken at the plastic plug body is strong and does not shear with pressure.
center of the plug (Fig. 10), which clearly shows a fracture Instead, when the holding pressure is reached, part of the outer
going through the gel. It is concluded that the gel shear surface of the plug is dislodged from the inner wall of the
strength is significantly less than the gel-PVC wall adhesive pipe. This failure in plug-pipe adhesion occurs at a weak area.
strength, so that increasing the plug length beyond a certain Consequently, the adhesive force along the weak area is
(optimum) length would not increase the holding pressure. mainly a function of plug length, and hence the holding
pressure is only a fimction of plug length and not plug
Monomer plug. About half of the monomer plugs prepared diameter. This also explains why the plug does not slip but
did not form, and when formed, the plugs tended to be brittle stays in place after the holding pressure is reached.
and to have minute internal fissures which probably acted as Holding pressure tests for the plastic were conducted under
flow paths for the injected water. very unfavorable conditions compared to those found in the
Experiments were carried out for 1 in. diameter plugs with field. First, the plastic gels were cured at room temperature
the manufacturer’s recommended monomer concentration of instead of reservoir temperature. Plug strength is greater at
15 w%. When this gave a low holding pressure (Fig. 11), reservoir temperature. Second, at the high holding pressures,
plugs of 26%, 35%, and 41% monomer concentrations were the PVC pipe could have bulged slightly, contributing to a
also used. For a 15 wt% monomer plug, the maximum lower-than-actual holding pressure. Third, the pressure head
holding pressure was about 7 psi for a 12 in. long plug (Fig. applied to avoid vaporization of light components is very low
12), while a 26 wt% monomer plug had a maximum holding compared to the hydrostatic pressure in a well. Fourth, there
pressure of about 20 psi for a plug length of about 12 in. (Fig. would be some penetration of the plastic gel into a formation,
13). 35% and 41% monomer concentrations resuIted in so that the holding pressure would be greater than that
fractured plugs with no holding pressure. obtained in the study. Despite these unfavorable laboratory
conditions, a holding pressure of 343 psi was obtained for a
Plastic plug. Figure 14 shows a holding pressure test for a plug length of 37 in. and 1 in. diameter. The plastic plug thus
plastic pIug, clefily indicating a holding pressure (343 psi) hold promise for field applications.
significantly higher than those of polyacrykunide or monomer
plugs. The plug had the consistency of a very strong solid Summary and Conclusions
material. However, the plug shrank in size due to 1. GeI siumping can be avoided by using completion brine
vaporization of volatile components in the gel, reducing of sufficiently high density and viscosity.
adhesion of the plug to the pipe wall and thus the holding
2. The use of CMC to increase the viscosity of completion
pressure.
brine is particularly appropriate, since as a polymer it
To alleviate the plug-shrinking problem, the gel was
reacts with the cross-linker in the gel, preventing fiu-ther
continuously subjected to an applied pressure of 50 psig
cross-linker migration and dilution in the brine, thus
throughout the curing period (about two weeks). (In the field,
forming a stronger wellbore plug.
a favorabIy TiigXer pressure head would result from the
hydrostatic column in the well). Curing the plug in this 3. A sufficiently high injection rate is required during gel
manner resulted in an increase in holding pressure of about placement so the gel straddles the wellborej- thereby
twice that without application of pressure (Fig. 15). minimizing gel dispersion and slumping. “”
Figure 16 shows holding pressure of plastic plug (1 in.
4. For all chemicals tested, temperature was found to reduce
diameter) increases linearly with plug length. The effect of
the gelation time significantly.
plug diameter on holding pressure was studied using pipes of
1.5,2 and 4 in. I.D. The holding pressures obtained are listed 5. Polyacrylamide and monomer plugs showed an increase

438
SPE 39s47 CHEMICAL VVELLBORE PLUG FOR ZONE ISOLATION IN HORIZONTAL WELLS 5
in holding pressure with increasing length up to a References
maximum point, beyond which an increase in plug length 1, Ranney,L.: “DrilIingWells Horizontally,”Oil WeekZy (Jan. 20,
did not increase the holding pressure. This maximum 1941) 12-14.
length (and therefore the optimum plug length) was found 2. Meehan, D.N.: “Technology Vital for Horizontal Well
Success,” Oil & Gas J. (Dec. 11, 1995) 39-46.
to be about six to eight times the internal diameter of the
3. Payne, M.L., Cocking, D.A., and Hatch, A.J.: “Critical
plug. Technologies for Success in Extended Reach Drilling,” paper
6. For polyactylarnide and monomer plugs, on reaching the SPE 28293 presented at the 1994 SPE Annual Technical
holding pressure, the injected liquid leaked out of the Conference and Exhibition, New Orleans, Sep. 25-28.
4. Aguiler& R., Artindale, J.S., Cordell, G.M., Ng, M.C., Nicholl,
fracture created in the plug, without slippage of the plugs.
G.M., and Runions, G.A.: Horizontal Wells, Gulf Publishing
7. Holding pressures of the polyacrylamide and monomer Company, Houston (1991 ) 76-126.
plugs were low, making these chemicals unsuitable for 5. Economies, M.: Horizontal Wells: Completion & Evaluation,
chemical plugs that require high holding pressures, They International Human Resources Development Corporation,
Boston (1993) 19-34.
are, however, excellent candidates for use as formation
6. Mamor% D.D., Burnet4 D.B., %avedr~ N. and Platt, F., “Zone
gels, since they can penetrate deep into the formation, Isolation in Horizontal Wells,” paper CEA 88 presented at the
8. Only the plastic plug showed promise for field application Completion Engineering Association Meeting, DaIlas, Texas,
where high holding pressures are required. The Oct. 26, 1995.
7. Goode, P.A., and Thambynayagam, R.K.M.: “Pressure
maximum holding pressure obtained was 343 psi for a
Drawdown and Buildup Analysis of Horizontal WeI1s in
plug length of 37 in. and 1 in. diameter. &isotropic Medi%” SPE Formation Evaluation (Dec. 1987)
9. For plastic plugs, when the holding pressure was reached, 683-693.
the injected liquid leaked through a gap created between 8. Odosirio, V.G., and Curtis, S.C., “Operational Advances from
Field Application of Short-Radius Horizontal Drilling in the
the plug surface and inner wall of the pipe (wellbore).
Yates Field Unit,” paper SPE 24612 presented at the 67th
There was no fracture in the plug body. The holding Annual Technical Conference and Exhibition of the SPE,
pressure thus increases with increasing plug length. Washington DC, October 4-7, 1992.
10. For plastic plugs, the holding pressure increases linearly 9. Andersen, S., and Hovd~ S.: “Experience With Drilling C-26A,
A World Record Extended Reach Horizontal WeIl in the
with plug length, independent of plug diameter. The
Oseberg Field, North Se%” paper presented at the 1995 SPE
relationship indicates the holding pressure (in psi) to be AnnuaI Technical Conference and Exhibition, Dallas, Oct. 22-
equal to nine times the plug length (in inches). 25.
11 In summary, a placement technique using high-viscosity 10. “Conformance Technology,” Halliburton Services, Houston
(Dee 1993).
brine has been developed and tested to be viable, which in
11. Borling, D., Chan, K., Hughes, T., and Sydansk, R.: “Pushing
conjunction with the plastic wellbore plug, augurs well Out the Oil with Conformance Control: Oil Review (April
for the proposed zone isolation technique. Further 1994) 44-58.
research is however required, particularly in the 12. Dovan, H.T., and Hutchins, R.D.: “Development of a New
placement of the formation gel, before field testing, Aluminum/Polymer Gel System for Permeability Adjustment;
SPE Reservoir Engineering (May 1987) 177-183.
13. Sparling, D.D., and Hagen, R.W.: “Part 4-Controling Water in
Acknowledgments Production Operations,” World Oil (June 1984) 149-154.
This research was sponsored in part through industry joint 14. Calvert, D.G., Heathman, J.F. and Griffith, J.E.: “Plug
venture research project CEA 88. We wish to thank Chevron Cementing: Horizontal to Vertical Conditions,” paper 30514
Production Technology Co., Halliburton Energy Services, presented at the 1995 SPE Annual Technical Conference and
Shell Development Co., and Texaco Inc. for sponsoring the Exhibition, Texas, Oct. 22-25.30514 presented at the 1995 SPE
project. Annual Technical Conference and Exhibition, Texas, Oct. 22-
25.

439
6 N. F. Sazsvedra, D. D, Mamora, D. B. Burnett, F. M. Platt “SPE 39647

TABLE 1- FLOTATION TESTS FOR POLYACRYLAMIDE GELS

PolymerConcentration I
5%

BrineConcentration Gel Position Brine Concentration Gel Position


(%) (%)
2.5 Bottom 2.5 NtA
5,0 Bottom, Dispersed 5.0 Bottom
8.5 Bottom, Dispmed 7.5 Bottom
10.0 Top, Dkpersed 10.0 Bottom
12.5 Top 12.5 Bottom
15,0 Top 15.0 Bottom, Dispersed
17.5 Top 17.5 Top, Dispersed
20.0 Top 20.0 Top

TABLE 2- FLOTATION TESTS FOR PLASTIC GELS

BrineConcentration(ppm) Gel Position


100,000 Bottom
150,000 Bottom
160,000 Middle-top
I70,000 Top
175,000 Top
180,000 Top
190,000 Top
200,000 Top

TABLE 3- PARAMETERS FOR SUCCESSFUL PLACEMENT TECHNIQUE

PlasticViscosity Yield Point Mud Density Inj. Rate


Chemical Plug (Cp) (lb/100 sq ft) (lb/gal) (cc/trr)

Polyacryhunide >31 >26 >8.7 >800


Monomer >14 >17 ~8.7 >800
Plastic >53 >59 >9.0 >1450

440
SPE 39647 CHEMICAL WELLBORE PLUG FOR ZONE ISOLATION IN HORIZONTAL WELLS 7

TABLE 4- HOLDING PRESSURE OF PLASTIC PLUGS

Diameter (in) Length (in) HoldingPressure(psig)


55.8
I 7.5 80
1 14.5 126
1 37 347
1.5 7.5 66
2.0 7.25 40
2.0 14.5 110
4.0 13.75 114

-..-....-.<”; . ;.- . . ..—.


,,,, .? ,....=:.. . ... .

,W%r.. w- - .-

(a) True open hole (b) Slotted liner

(c) Uncementedsegmented liner (d) Cased, cemented and


perforated liner
Fig. 1- Common horizontal well completions

Inject chemical plug


1 ,

+ -

Horizontal pi% (wellbom)

Wellbore (PVC pipe lined insidewith sand) Chemicalplug


Constant \ h
-v=
Positive displacementpump
Rotation

(0-309

(
Transducer
Chemical WdlbO~ phlS
Coiled Tubing

n~
Completion fluid

Data logger

Fig. 2- Schematic of gei piacement apparatus Fig. 3- Schematic of hoiding pressure apparatus

441
8 N. F. Saavedra, D. D. Mamora, D. B. Burnett, F. M. Platt SPE 39647

140
Diameter= 0.5”
25.

lm
m. ●

f 15.

E
~
10-
? ●
n
5.

o 0
0 2 4 6 a 0 5 10 15 20
CMC concentration (lb/bbl) Length, in.

Fig. 4- Effect of NaCl on yield point (68”F)


Fig. 7 - Effect of piug iength on hoiding pressure
(polyacryiamide)

Length = 15“, Diameter= 1”


D = 1’1
14.

12.
12.

10
D
“ 10.
!i s. ‘ii
: 8. ●
ii t!
; 6.
t? j 8“
n 4. 4.
2. 2.

0 0
0 m 40U eoo m Im lzm 0 5 to 15 )
Time, S6C. Length, In.

Fig. 8 - Effect of piug iength on hoiding pressure


Fig. 5- Hoiding pressure test (poiyacryiamide) (poiyacryiamide)

8 In
20. 4 A*
7
● n
=6
Lk5 ~15. ●
l?!- e

i4 :10.


a.3 c ●
●5% 11:1
n
~ 10% 11:1
2 5. .0
A 10% 5.5:1
1
/
0 01”
0 1 2 3 4 5 6 7 8 0 5 10 15
Time, hr
Length, in.

Fig. 6 - Effect of aging time on hoiding pressure Fig. 9 - Effect of cross-i inker concentration on
(poiyacrylamide) hoiding pressure (poiyacryiamide)

442
SPE 39647 Chemical Wellbore Plug for Zone Isolation in Horizontal Wells 9

Monomer 26%
Diameter = 1“
Fracture 25

I
20
PVC pipe

PVC cap

Sand lining
5
Gel

0
o 5 10 15 20

Length, in.

Fig. 10 - CT scan cross-sectional image showing Fig. 13- Effect of plug length on holding pressure
shear in polyac@amide plug (monomer)

Monomer 15%
Length = 6.5” Diameter= 1“ Length = 37” Oiametar= 1“
3,5 350
00

3. 300
Q 00000

2.5. 250
o
g
0
22 200
$ 0
0
450
: 1.5
o o
?!
&
1
103
0

0.5 5a
0
0 A o
o 20 40 60 so Ifxl 0 2(XI 400 600 800 1000 1200 1400

Time, eec.
Time, sec.

Fig. 11- Holding pressure test (monomer)


Fig. 14- Holding pressure test (plastic)

Monomer 1570
Diameter = 1“
10 140

9
120
8
10U



● “

I
2
20 0
1

0
0 5 10 15 20 o 2 4 6 8 10 12 14 16

Lwrgth, In. Length, in.

Fig. 12- Effect of plug length on holding pressure Fig. 15- Effect of plug length on holding pressure
(monomer) (gel cured at O psig and 50 psig)

443
10 N. F. Saavedra, D. D. Mamora, D. B. Burnett, F. M. Platt SPE 39647

350 350
m’

300 3(KJ
I
El
y = 9J3049X
t?= o.9e37
250

E?
g 150
!! .*:
n 100
1# $:
so

o
50
I ■

0 10 20 30 40 o 10 20 30 40
Lmgth, In. Length, In.

Fig. 16- Effect of plug length on holding pressure Fig. 17 - Effect of plug diameter (figure next to
(plastic) symbol) on holding pressure (plastic)

PLASTICPLUG

Fracture I PVC pipe

Fig. 18 -CT scan cross-sectional image showing shear in plastic plug

444
Foamed Cement for Zonal
Isolation: Case Histories
Data from six deep gas wells in rate of the base slurry, foamer, and sta- density cements ideal for zonal isola-
Wyoming indicate that foamed bilizer injection rates and nitrogen tion in many hydraulic-fracturing
cement outperforms conventional rate. The gas used to foam the system operations. The low compressive
cement for zonal isolation. Two continues to expand while the cement strength of foamed cement does not
wells that were cemented across the volume decreases, allowing slurry increase the risk for fracture initiation
production zones with conventional pressure to remain almost constant and propagation during hydraulic-
nonnitrified cements experienced during the transition period. The sys- fracturing treatments. Stresses induced
outer-zone communication after tem effectively controls gas migration in the cement sheath by increased
stimulation treatments. In the other and formation fluid influx, which lim- wellbore pressures during casing pres-
four wells, the foamed-cement its migration channels in the set sure tests or fracture stimulation treat-
sheath provided zonal isolation even cement sheath. ments are tensile. The ability to with-
after the sheath was perforated and stand these stresses is determined by
stimulation treatments were per- Ductility. Brittleness or lack of ductil- the mechanical properties of the
formed. Case histories described in ity of conventional cement has been cement (Young’s modulus and
the full-length paper compare identified as one of the primary failure Poisson’s ratio) and tensile strength.
foamed-cement performance with mechanisms of primary cement jobs. The compressive strength of the
C e m e n t i n g Te c h n o l o g y

conventional cement performance Flexible cement systems have been cement is of minimal importance.
in similar wells in the same geo- used successfully to combat and pre-
graphic area. vent cement sheath cracking. Economy. Although flexible cement
However, flexible cement systems that systems such as vulcanized rubber sys-
Properties and Applications contain vulcanized rubber are very tems offer longer life in sour-well
Introduction. The tensile strength, costly and require extreme conditions applications, foamed-cement systems
ductility, and displacement properties to justify their use. are less expensive. Foamed cement
of foamed cement have made it espe- Foamed-cement systems also exhib- may add incrementally to the initial
cially useful in several zonal-isolation it improved ductility. Testing has cost of the primary cement job, but the
scenarios. Though the cost of foamed shown that systems made with foamed useful life of a foamed cement sheath
cement is greater than that of conven- 20- to 30-quality cement remain at to provide zonal isolation is measured
tional cement, the improved zonal-iso- least one magnitude more ductile than in hundreds of stress-relaxation cycles
lation capability of foamed cement conventional cements. This ductility compared with conventional cement
often provides substantial cost savings allows the cement sheath to withstand which will crack in two to ten stress-
over the life of the well. higher hoop stresses from casing pres- relaxation cycles.
sure and/or temperature cycling. This
Mud Displacement and Migration feature allows the cement sheath to Case Studies
Control. During pumping operations, give as the well casing expands, help- Project Requirements. The operator’s
foamed cement can develop higher ing prevent long-term cement-sheath drilling/completion program required
dynamic-flow shear stress than con- cracking. Cement with quality greater cementing liners in six nearly-vertical
ventional cement, increasing its mud- than 35 is too porous to provide isola- wellbores. These jobs, cementing 7-in.
displacement capabilities. A system tion, and cement with quality less than casing in 81/2-in. wellbores, required
that consists of cement slurry injected 20 becomes brittle. Fig. 1 shows a complete drilling mud displacement.
with nitrogen gas can be optimized for photomicrograph of 20-quality In addition, the cement had to pro-
individual well conditions. Slurry den- foamed cement. vide good zonal isolation in the well-
sity, which is determined by gas con- In sandstone reservoirs, in-
tent or quality, depends on the pump creased stress caused by reservoir
pressure depletion can cause large
This article is a synopsis of paper compaction strain that can severely
SPE 62895, “Foamed Cement vs. deform the casing. Foamed cement
Conventional Cement for Zonal is one of several solutions that can
Isolation: Case Histories,” by Kevin be used to deal with the damage
Kopp, SPE, Chevron, and Shawn mechanism associated with forma-
Reed, Jay Foreman, SPE, Brian tion compaction caused by reser-
Carty, SPE, and James Griffith, SPE, voir depletion.
Halliburton Energy Services Inc., origi-
nally presented at the 2000 SPE Annual Tensile Strength. The tensile
Technical Conference and Exhibition, strength and mechanical properties Fig. 1—Twenty-quality foamed cement.
Dallas, 1–4 October. of foamed cements make these low-

72
AUGUST 2001
bores because different producing Job Execution. Water analysis was was to cement the third through sixth
horizons were targeted for zonal performed in the laboratory and again wells with foamed cement and to eval-
stimulation treatments. Reduced- on location. When the 7-in. liner was uate each well before proceeding with
density cements were required to run in the well, the rig pump circulat- the next well. Criteria for success
prevent cement losses to the primary ed the well with drilling fluid, which included cement evaluation logs, liner-
zone of interest. Production from was monitored for the lowest possible top integrity, measured stimulation
this zone had reduced reservoir pres- plastic viscosity and yield point. pressures, and initial production rates.
sure drastically, and drilling and Controlling these properties helped Because of the poor acoustic prop-
cementing operations were required ensure the best possible fluid move- erties of foamed cement, a cement
to keep equivalent circulating densi- ment in the annulus. When the bond log will only indicate marginal
ties (ECD’s) as low as possible. drilling fluid was properly condi- zonal isolation when 100% mud dis-
tioned, the foamed-cement job began. placement is achieved. An alternative
Job Design. The first two wells were The premium cement base was method for evaluating foamed cement
cemented with a hollow-sphere mixed in a batch mixer until the with ultrasonic logging tools has been
cement lead and a conventional tail weight was 15.7 lbm/gal. The spacer developed that evaluates the imped-
system. Prejob laboratory testing was mixed on the fly. After the nitrified ance variation exhibited by the
and design were complicated by the spacer was pumped, the base cement foamed cement instead of the meas-
fact that the hollow spheres crush slurry and nitrogen were pumped. ured value of the cement impedance.
with increased hydrostatic pressure. Foamer and nitrogen concentrations Sonic and ultrasonic logs were used to
The foamed cement job design were controlled automatically by com- gather cement integrity data. The
was based on the actual hole condi- puter-controlled pumping equipment. cement evaluation logs from the four
tion, drilling-fluid properties, and Foamer concentrations were constant, foam-cemented wells showed ade-
cementing materials. Jobs were and nitrogen rates were ramped to quate zonal isolation between the
designed for a constant downhole maintain a constant downhole density low- and higher-pressure zones.
C e m e n t i n g Te c h n o l o g y

slurry density over the entire throughout the entire cement column. All jobs had circulated cement
cemented interval. A wiper plug was then pumped. The above the liner tops. The liner tops
Because improper mud removal has plug was designed to land; then the were pressure tested with successful
been well documented as a cause of displacement pressure was exceeded results, and no liner-top remediation
primary cement job failures, the fol- by 500 to 1,000 psi. After the plug was was required. Individually stimulated
lowing steps were scrutinized closely set, the pressure was bled off, and perforations showed distinctive
to enhance mud displacement. operators checked for indications of breakdown pressure, indicating a
• Pipe centralization practices flowback. The liner hanger was set and diversion of the acid treatments and
were reviewed and changed appro- drillpipe was stung out of the liner. zonal isolation of the high- and low-
priately. The “U-tube” of the cement over the pressure formation. No evidence of
• Casing centralization and liner liner top was monitored to ensure that zonal communication has been
drag programs were run to improve cement had returned to the required observed to date. In general, initial
centralization and mud displace- height over the top of the liner. Finally, production rates from the four foam-
ment to ensure that the liner would the drillpipe was pulled out of the cemented wells were 2.5 to 5 times
go to the bottom of the hole with the hole, leaving the stable nitrified higher than the two wells cemented
required number of centralizers. cement on top of the liner. After the with conventional cement.
• In oversized openhole sections, foamed cement set, the rig dressed off
oversized bow-spring centralizers the liner top and ran a tieback string. Conclusions
were run. 1. The excellent displacement quali-
• Mobility of drilling fluid samples Project Review and Results. After ties of foamed cement and the result-
was measured because mobility the first well was cemented with the ing cement bond make it an excellent
determines the shear rate or amount hollow-sphere and conventional choice for primary cementing of pro-
of force required to displace the cement systems, acid fracture treat- duction casing.
drilling fluid from the wellbore. ments were performed. Radioactive 2. Deep liners can be cemented
With this information, proper tracer logs indicated communication effectively with foamed cement.
pumping and displacement rates on most of the zones. The second well 3. Pressure and radioactive-tracer
could be designed to remove the that was cemented with hollow- data of stimulation treatments show
drilling mud. sphere and conventional cement that zonal isolation is maintained with
Cement materials from the base experienced casing damage during the a foamed cement sheath.
camp also were tested. Laboratory per- completion phase that caused a lower 4. Foamed cement costs approxi-
sonnel generated rheology values for zone to be abandoned. mately one-third less than other non-
the mud and cement systems as well as After the first two wells were com- foamed, premium lightweight slurry
thickening time, fluid loss, and com- pleted, the cementing program was systems. JPT
pressive stress at downhole condi- thoroughly evaluated to determine
tions. Cementing simulation software ways to improve results. Foamed Please read the full-length paper for
was used to generate values for cement was reviewed and determined additional detail, illustrations, and ref-
required nitrogen rates, ECD’s based to be the best alternative for success- erences. The paper from which the
on the drilling-fluid weight, wellhead fully achieving effective zonal isolation synopsis has been taken has not been
pressure, and fluid-pumping rate. on this completion program. The plan peer reviewed.

74
AUGUST 2001
SPE 71055

Foamed Cement Selection for Horizontal Liners Proves Effective for Zonal
Isolation—Case History
Tony D. Harlan, SPE, Chevron, USA; Jay M. Foreman, SPE, Shawn D. Reed, SPE, and James E. Griffith, SPE,
Halliburton Energy Services, Inc.

Copyright 2001, Society of Petroleum Engineers, Inc. conventional cement can be less than that of foamed cement,
This paper was prepared for presentation at the 2001 Rocky Mountain Petroleum Technol-
the improved zonal-isolation capabilities of foamed cement
ogy Conference held in Keystone, Colorado, 21-23 May 2001. often provide substantial cost savings over the life of the well.
This paper was selected for presentation by an SPE Program Committee following review The following section discusses both the advantages of using
of information contained in an abstract submitted by the author(s). Contents of the paper, foamed cement for zonal isolation and its economic value
as presented, have not been reviewed by the Society of Petroleum Engineers and are
subject to correction by the author(s). The material, as presented, does not necessarily compared to flexible cement.
reflect any position of the Society of Petroleum Engineers, its officers, or members. Papers
presented at SPE meetings are subject to publication review by Editorial Committees of the
Society of Petroleum Engineers. Permission to copy is restricted to an abstract of not more Mud Displacement and Fluid Loss. During pumping opera-
than 300 words. Illustrations may not be copied. The abstract should contain conspicuous
acknowledgment of where and by whom the paper is presented. Write Librarian, SPE, P.O. tions, foamed cement can develop higher dynamic-flow shear
Box 833836, Richardson, TX 75083-3836, U.S.A, fax 01-972-952-9435.
stress than conventional cements, increasing its mud-dis-
placement capabilities. A system that consists of cement
slurry injected with nitrogen gas can be optimized for indi-
Abstract vidual well conditions. Slurry density, which is determined by
This paper describes the reasons for and execution of four gas content or quality (the porosity of the set cement), depends
foamed cement jobs to provide zonal isolation for a 4 ½-in. on the pump rate of the base slurry, foamer and stabilizer
horizontal liner. Foamed cement was selected as the most injection rates, and nitrogen rate. Computer programs help
effective means to help achieve all of the following objectives: optimize slurry design and predict job-placement pressures.
The gas used to foam the system continues to expand
• High mud displacement in a small annulus while the cement volume decreases,1-5 allowing the slurry
pressure to remain almost constant during the system’s tran-
• Hole cleaning on the low side of the hole
sition period. Consequently, the system effectively controls
• No free water or gas channel development gas migration and formation-fluid influx, which limits migra-
• Low slurry fluid loss tion channels in the set cement sheath.
• Containment of stimulation treatment in selected
porosity streaks Ductility. Foamed cement is resistant to both temperature-
• Prevention of cement sheath cracking and pressure-induced sheath stresses.6 Foamed cement is at
least one order of magnitude more ductile than other ce-
ments. Testing has shown that a foamed, 20- to 35-quality,
The benefits of foamed cement vs. non-nitrified cement as Class H cement remains more ductile than other cements,
they relate to the above objectives are explained in the body of the allowing the cement sheath to withstand higher internal
paper. From the analysis, foamed cement can be a far superior and casing pressures.7 This feature permits the cement sheath to
effective means of providing long-term zonal isolation when yield while the well casing expands. Consequently, the
compared to conventional, non-nitrified cements. cement sheath has less potential for cracking on a long-term
The paper also outlines steps taken to execute the foamed basis. Fig. 1 is a photomicrograph of a foamed-cement
cementing operation on horizontal liners of four Wyoming system consisting of 25-quality, foamed premium cement.
wells. Included are best practices for pre-job analysis and Above 35-quality, the cement is generally too porous to
planning, job execution, and post-job evaluation. provide isolation, and below 20-quality, it is generally too
brittle to provide the required ductility.
Foamed Cement Advantages
Introduction. Foamed cement’s tensile strength, ductility,
Tensile Strength. The tensile strength and mechanical prop-
and displacement properties have made it especially useful in
erties of foamed cement can make it ideal for zonal isolation
several zonal-isolation scenarios. Although the initial cost of

References at the end of the paper.


2 FOAMED CEMENT SELECTION FOR HORIZONTAL LINERS PROVES EFFECTIVE FOR ZONAL ISOLATION SPE 71055

in many hydraulic-fracturing operations. However, the low Program Objectives. The operator’s drilling/completion
compressive strength of this cement is a concern for some program required cementing liners in four horizontal wellbores
operators who have considered compressive strength a leading in order to produce from the matrix rather than the fracture
indicator of cement sheath integrity in high-pressure fracturing network, while reducing GORs and N2 breakout. These jobs,
conditions. which included cementing 4 ½-in. casing in 6-in. wellbores,
The lower compressive strength of foamed cement does required complete drilling-mud displacement. In addition,
not increase the risk for fracture initiation and propagation the foamed cement had to provide complete zonal isolation in
during hydraulic-fracturing treatments. The stresses induced the wellbores. This allows selective perforating and will
in the cement sheath by increased wellbore pressures during allow remedial treatments to accomplish the sweep of matrix
casing pressure tests or fracture stimulation treatments are reserves, maintain low GOR’s, and help prevent N2 break-
tensile in nature. The sheath’s ability to withstand these stresses through. Reduced-density cements were required to help
is predominantly determined by the cement’s mechanical prevent cement losses to the primary zone of interest. Drill-
properties (Young’s modulus and Poisson’s ratio) and tensile ing and cementing operations were required to help keep
strength. The cement’s compressive strength is of minimal equivalent circulating densities (ECDs) as low as possible
importance.8 (less than 0.55 psi/ft).

Economy. Although foamed cement may add incrementally to Design. Solids-free fluid replaced the polymers of the original
the initial cost of the primary cement job, the useful life of a drilling program, with a sodium formate base fluid. This
foamed-cement sheath to provide zonal isolation is measured change was driven by the need to limit possible formation
in hundreds of stress-relaxation cycles compared to conven- damage. Drilling fluid cleanup was simplified and sodium
tional cement, which will usually crack in two to ten cycles.6 In formate return permeability tests indicated that the fluid would
a marginal or mature field, the economic life of a well can not damage the formation. Nitrogen was used to control fluid
justify the use of foamed cement for providing long-term zonal losses because previous wells lost between 500 to 10,000 bbl
isolation where it could not justify the installation of a flexible of polymer fluid.
sheath. ECP’s and sliding sleeves were replaced by a fully ce-
mented liner (Fig. 2). Foamed cement was used to help
Case Study minimize cement losses in the fractured formation. The foamed-
The current drilling program began in 1996. Since then, six cement job design was based on the actual hole conditions,
new wells and twelve sidetracks have been drilled. Field drilling-fluid properties, and cementing materials. Jobs were
conditions for these wells include retrograde condensate, designed for a constant downhole slurry density over the entire
water drive, gas cap, and nitrogen injection for pressure cemented interval. Because improper mud removal has been
maintenance. The reservoir parameters include: well documented in industry literature as a cause for primary
cement job failures, the following steps were closely scruti-
• 7.6 lb/gal reservoir nized to enhance mud displacement:9,10
• 11,500 ft total vertical depth (TVD)
• 190°F reservoir temperature • Previous pipe centralization practices were reviewed and
• Productive nugget sandstone changed appropriately, including the use of ridged
turbolizers.
The previous drilling program set whipstock and the cut • Casing centralization and liner drag programs were run
window between 10,000 and 11,000 ft in a 7-in. casing with a extensively to help improve centralization and mud dis-
5 7/8- to 6 1/8-in. hole. A 4 ½-in. liner with sliding sleeves and placement and to help ensure that the liner would go to the
ECP’s were installed throughout production zone. Wells aver- bottom of the hole with the required number of centraliz-
age four ECP’s and sleeves, and ECP’s inflated with cement ers (2/jt).
slurry. The curve and nugget gas caps were typically cemented • A sample of the drilling fluid was sent to a laboratory for
into the liner lap. Drilling fluid was displaced with 2% KCL testing. In addition to the measurement of mud weight and
ahead of the installation job, and an acid soak was used on rheologies, the drilling fluid’s mobility, which determines
some wells to remove drilling damage. the shear rate (amount of force required for displacing the
Several changes were made to drill four sidetract wells in drilling fluid from the wellbore), was determined.
the 2000 drilling program. The program moved from sliding
sleeves/ECP’s because of high N2 cuts and gas-to-oil ratios
(GOR). The operator could not effectively isolate intervals With this information, proper job pumping and displace-
with this setup. The previous drilling program was replaced ment rates could be designed to effectively remove the drilling
with a near-balance drilling approach, the drilling fluid density mud.
was lowered from 8.5 to 7.6 lb/gal, and the horizontal liners Only 5% excess cement was used to reduce ECD’s while
were to be cemented with foamed cement. N2 rates were ramped, which required automated control and
SPE 71055 HARLAN, FOREMAN, REED, GRIFFITH 3

local area network communication. The displacement rate was placement simulator output with the final positions of the
reduced at the end to reduce ECD’s while lifting cement, fluids when the plug was bumped.
resulting in a 9.0-lb/gal lead and a 12.5-lb/gal tail on all wells. In some cases, getting the liner to the bottom of the
Only N2 rate was changed to obtain the desired downhole wellbore was difficult, but nitrogen was pumped to move the
density. No additional slurry modifications were required. liner, and all liners successfully reached the bottom. Job data
Cement materials from the base camp were also tested. for one of the foamed-cement operations appears in Fig. 5.
Laboratory personnel generated rheology values for the mud
and cement systems as well as API thickening time, fluid loss, Results. Criteria for success were based on several factors,
and compressive strength at downhole conditions. Service including cement evaluation logs, liner-top integrity, and
company engineers used cementing-simulation software to sustained low N2 and GOR’s. For these four horizontal liners,
predict job results. This software generated values for required the detailed criteria were met. The operator had previously
nitrogen rates, ECDs based on the weight of the drilling fluid, used foamed cement to help ensure proper isolation in devi-
wellhead pressure, and fluid-pumping rate. When digital cali- ated sidetracked liners. In that case, communication between
per data were available, actual caliper logs were downloaded zones during subsequent hydraulic fracturing operations had
into the simulator to improve overall accuracy of the job been alleviated. Costs were compared, and the foamed-cement
design. When all of the correct data were used in the simulator jobs were comparable with the previous specialized conven-
models, the actual job parameters (such as cement tops and tional cement job.
spacer volume circulated from well) very closely matched the Because of poor acoustic properties of foamed cement, a
simulator predictions. The output from software runs in one of cement bond log (CBL) will only indicate marginal zonal
the four wells with the foamed liner appears in Fig. 3. isolation when 100% mud displacement is achieved. This
logged response is not unusual, and an alternative method of
Equipment. The cementing equipment used for this job in- evaluating foamed cement with ultrasonic logging tools has
cluded the following items: been developed.11 This method evaluates the impedance varia-
tion exhibited by the foamed cement instead of the measured
value of the cement’s impedance. The sonic and ultrasonic
• truck-mounted recirculating cement mixer
logs were used to gather cement-integrity data, and the refer-
• downhole pump truck enced processing was conducted. The cement-evaluation logs
• cement batch mixer from the foam-cemented wells showed adequate zonal isola-
• nitrogen pumper tion between the low- and higher-permeability zones.
• automated chemical truck The wells experienced no lost circulation during the
cement job, with foamy spacer and a trace of foamed cement
• real-time job-monitoring van
when dressing off the liner top. Production history shows low
GOR’s and nitrogen breakout as compared to previous ECP
Execution. Water analysis was performed in the laboratory type completions.
and again on location. When the 4 ½-in. liner was run in the
well, the rig pump circulated the well to achieve a wellbore Conclusions
condition as with drilling operations. Controlling the mud The displacement qualities of foamed cement and the resulting
properties helped ensure the best possible fluid movement in cement bond can make it an excellent choice for primary
the annulus. When the drilling fluid was properly conditioned, cementing of horizontal liners. Because of the success of this
the foamed cementing job began. foamed-cementing program, the foamed-cement process along
Foamer and nitrogen concentrations were automatically with other best practices for mud removal and pipe centraliza-
controlled by computer-guided pumping equipment. Foamer tion has become the first choice for horizontal liner cementing
concentrations were constant and nitrogen rates were “ramped” where zonal isolation is critical.
to maintain a constant downhole density throughout the lead The well construction program met its objectives of ob-
and tail cement section. A wiper plug, designed to land, was taining a matrix sweep of the gases, as evident in the low
then pumped. Then, the displacement pressure was exceeded GOR’s and little N2 breakthrough. The drilling program also
by 500 to 1,000 psi. After the plug was set, the pressure was found success in:
bled off and operators checked for indications of flowback.
The liner hanger was set, and the drillpipe was stung out of the
liner. The U-tube of the cement-over-liner top was monitored
• Reduced total well costs by 25%
to help ensure that cement had returned to the required height • Reduced total fluid loss by 70%
over the top of the liner. Finally, the drillpipe was pulled out
of the hole, leaving the stable nitrified cement on top of the Acknowledgements
liner. After the foamed cement set, the rig dressed off the liner The authors thank both the management of Chevron, USA, and
top and ran a tieback string. Fig. 4 shows the cementing Halliburton Energy Services, Inc. for allowing the publication
of this paper.
4 FOAMED CEMENT SELECTION FOR HORIZONTAL LINERS PROVES EFFECTIVE FOR ZONAL ISOLATION SPE 71055

References 7. Goodwin, K.J. and Crook, R.J.: “Cement Sheath Stress Fail-
1. Harms, W.M. and Febus, J.: “Cementing of Fragile Formations ure,” paper SPE 20453 presented at the 1990 Annual Technical
Wells with Foamed Cement Slurries,” paper SPE 12755 pre- Conference and Exhibition, New Orleans, Sept. 23-26.
sented at the 1984 Annual California Regional Meeting, Long 8. Deeg, W.F., Griffith, J.E., Crook, R.J., and Benge, G.: “How
Beach, April 11-13. Foamed Cement Advantages Extend to Hydraulic Fracturing
2. Montman, R. and Harms, W.M.: “Oil Field Application of Low Operations,” World Oil (Nov. 1999) 51-53.
Density Foamed Portland Cements,” Southwestern Petroleum 9. Smith, T.R. and Ravi, K.M.: “Investigation of Drilling Fluid
Short Course, Lubbock, April 22-23. Properties to Maximize Cement Displacement Efficiency,”
3. “Low Density Foamed Cements Solve Many Oilfield Prob- paper SPE 22775 presented at the 1991 Annual Technical
lems,” World Oil (1982) 171. Conference and Exhibition.
4. Aldrich, C.H. and Mitchell, B.J.: “Strength, Permeabilities, and 10. Beirute, R.M., Sabins, F.L., and Ravi, K.M.: “Large-Scale
Porosities of Oilwell Foam Cement,” 1975 ASME, Tulsa, Sept. Experiments Show Proper Hole Conditioning–A Critical Re-
21-25. quirement for Successful Cementing Operations,” paper SPE
5. Creel, P.G. and Kulakofsky, D.S.: “Computer Simulation Pro- 22774 presented at the 1991 Annual Technical Conference and
gram for Cement Squeeze Applications,” paper presented at the Exhibition.
1987 Southwestern Petroleum Short Course, Texas Tech Uni- 11. Harness, P.E., Sabins, F.L., and Griffith, J.E.: “New Technique
versity, Lubbock, April 22-23. Provides Better Low-Density Cement Evaluation,” paper SPE
6. Benge, O.G., McDermott, J.R., Langlinais, J.C., and Griffith, 24050 presented at the 1992 Western Regional Meeting, Bakers-
J.E.: “Foamed Cement Job Successful in Deep HTHP Offshore field, March 30-April 1.
Well,” Oil & Gas J (March 1996) 58.

Fig. 1—25-quality foamed cement at 600x magnification.


SPE 71055 HARLAN, FOREMAN, REED, GRIFFITH 5

Fig. 2—Cemented liner schematic.

Fig. 3—Output from software runs in one of four foamed liner wells.
6 FOAMED CEMENT SELECTION FOR HORIZONTAL LINERS PROVES EFFECTIVE FOR ZONAL ISOLATION SPE 71055

Fig. 4—Cement-placement simulator output after the plug was bumped.


SPE 71055 HARLAN, FOREMAN, REED, GRIFFITH 7

Fig. 5—Job data for one of the four foamed-cement operations.

Anda mungkin juga menyukai