ID WBS Task Name Duration Start Finish decess Actual Start Actual End Date

Date 29 Oct '06 05 Nov '06


T F S S M T W T F S S M T W T F
1 1 CIC PROJECT PLAN 33 days Thu 14/07/16 Mon 29/08/16 Wed 25/05/16 Wed 25/05/16
2 1.1 Data Modeling 21 days Thu 14/07/16 Thu 11/08/16 NA NA
3 1.1.1 Analysing Source Data and Data 2 days Thu 14/07/16 Fri 15/07/16 NA NA
4 1.1.2 Creation of Data Mart 15 days Mon 18/07/16 Fri 05/08/16 1.1.1 NA NA
5 1.1.3 Data mart review and finalisation 3 days Mon 08/08/16 Wed 10/08/16 1.1.2 NA NA
6 1.1.4 future process( source data load) 1 day Thu 11/08/16 Thu 11/08/16 1.1.3 NA NA
7 1.2 Data Loading to Model 11 days Mon 18/07/16 Mon 01/08/16 NA NA
8 1.2.1 Data Loading 10 days Mon 18/07/16 Fri 29/07/16 1.2.2 NA NA
9 1.2.2 Testing and Issue Fixing 10 days Tue 19/07/16 Mon 01/08/16 NA NA
10 1.3 Report Development 16 days Tue 19/07/16 Tue 09/08/16 NA NA
11 1.3.1 Identifying the Column required fo 1 day Tue 19/07/16 Tue 19/07/16 1.1 NA NA
12 1.3.2 Building the Model required for B 3 days Wed 20/07/16 Fri 22/07/16 1.3.1 NA NA
13 1.3.3 Creation of RPD in BICS 10 days Wed 20/07/16 Tue 02/08/16 1.3.1 NA NA
14 1.3.4 Report building and catalog 13 days Fri 22/07/16 Tue 09/08/16 NA NA
15 1.3.4.1 Operation Dashboard 3 days Tue 26/07/16 Thu 28/07/16 1.3.3 NA NA
16 1.3.4.2 Product Dashboard 3 days Fri 29/07/16 Tue 02/08/16 1.3.3 NA NA
17 1.3.4.3 Customer Dashboard 3 days Fri 22/07/16 Tue 26/07/16 1.3.3 NA NA
18 1.3.4.4 Financial Dashboard 5 days Wed 03/08/16 Tue 09/08/16 1.3.3 NA NA
19 1.3.5 Security 1 day Tue 09/08/16 Tue 09/08/16 NA NA
20 1.4 UAT 12 days Fri 12/08/16 Mon 29/08/16 NA NA
21 1.4.1 Training 10 days Fri 12/08/16 Thu 25/08/16 NA NA
22 1.4.2 Testing and Bug fixing 1 day Fri 26/08/16 Fri 26/08/16 NA NA
23 1.4.3 Sign Off 1 day Mon 29/08/16 Mon 29/08/16 NA NA
24 1.5 Data Model Documnetation 5 days Mon 01/08/16 Fri 05/08/16 NA NA
28 1.6 Production Migration 2 days Fri 12/08/16 Mon 15/08/16 NA NA

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Project: MSProj11 Summary Duration-only Progress
Date: Thu 14/07/16
Project Summary Manual Summary Rollup Deadline
External Tasks Manual Summary
External Milestone Start-only