TAHUN 2011
HARGA
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
RP. RP.
1 2 3 4 5
A PEKERJAAN PERSIAPAN
1 PENGUKURAN & PEMASANGAN BOUWPLANK 1 M'
B104 0.012 Kayu Usuk Meranti M3 4,125,000.00 49,500.00
B172 0.020 Paku Usuk Kg 16,500.00 330.00
B102 0.007 Kayu Papan Meranti M3 4,675,000.00 32,725.00
u10 0.100 Tukang Kayu OH 55,000.00 5,500.00
u04 0.010 Kepala Tukang Kayu OH 60,000.00 600.00
U16 0.100 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 3,100.00
u01 0.005 Mandor Lapangan OH 66,000.00 330.00
92,085.00
23 URUGAN KEMBALI 1 M3
U16 0.192 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 5,952.00
U01 0.019 Mandor Lapangan OH 66,000.00 1,254.00
7,206.00
25 PEMADATAN TANAH 1 M3
U16 0.500 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 15,500.00
U01 0.050 Mandor Lapangan OH 66,000.00 3,300.00
18,800.00
26 URUGAN TANAH 1 M3
B016 1.200 Tanah Urug M3 82,500.00 99,000.00
U16 0.250 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 7,750.00
U01 0.010 Mandor Lapangan OH 66,000.00 660.00
107,410.00
27 URUGAN SIRTU 1 M3
B014 1.2000 Sirtu M3 72,500.00 87,000.00
U16 0.2500 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 7,750.00
U01 0.0250 Mandor Lapangan OH 66,000.00 1,650.00
96,400.00
HARGA
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
RP. RP.
1 2 3 4 5
C PEKERJAAN PASANGAN
28 PASANGAN BATU KALI ( 1 : 3 ) 1 M3
B001 1.100 Batu Kali M3 126,500.00 139,150.00
B037 202.000 Semen Kg 1,150.00 232,300.00
B011 0.485 Pasir Pasang M3 129,500.00 62,807.50
U08 0.600 Tukang Batu OH 49,500.00 29,700.00
U03 0.060 Kepala Tukang Batu OH 60,000.00 3,600.00
U16 1.500 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 46,500.00
U01 0.075 Mandor Lapangan OH 66,000.00 4,950.00
519,007.50
D PEKERJAAN PLESTERAN
43 PLESTERAN PC ( 1 : 2 ) t = 15 mm 1 M2
B037 8.520 Semen Kg 1,150.00 9,798.00
B011 0.017 Pasir Pasang M3 129,500.00 2,201.50
u08 0.150 Tukang Batu OH 49,500.00 7,425.00
u03 0.015 Kepala Tukang Batu OH 60,000.00 900.00
u16 0.200 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 6,200.00
u01 0.010 Mandor Lapangan OH 66,000.00 660.00
27,184.50
44 PLESTERAN PC ( 1 : 3 ) t = 15 mm 1 M2
B037 6.480 Semen Kg 1,150.00 7,452.00
B011 0.019 Pasir Pasang M3 129,500.00 2,460.50
u08 0.150 Tukang Batu OH 49,500.00 7,425.00
u03 0.015 Kepala Tukang Batu OH 60,000.00 900.00
u16 0.200 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 6,200.00
u01 0.010 Mandor Lapangan OH 66,000.00 660.00
HARGA
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
RP. RP.
1 2 3 4 5
25,097.50
45 PLESTERAN PC ( 1 : 5 ) t = 15 mm 1 M2
B037 4.320 Semen Kg 1,150.00 4,968.00
B011 0.022 Pasir Pasang M3 129,500.00 2,849.00
U08 0.150 Tukang Batu OH 49,500.00 7,425.00
U03 0.015 Kepala Tukang Batu OH 60,000.00 900.00
U16 0.200 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 6,200.00
U01 0.010 Mandor Lapangan OH 66,000.00 660.00
23,002.00
46 PLESTERAN PC ( 1 : 6 ) t = 15 mm 1 M2
B037 3.680 Semen Zak 1,150.00 4,232.00
B011 0.023 Pasir Pasang M3 129,500.00 2,978.50
U08 0.150 Tukang Batu OH 49,500.00 7,425.00
U03 0.015 Kepala Tukang Batu OH 60,000.00 900.00
U16 0.200 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 6,200.00
U01 0.010 Mandor Lapangan OH 66,000.00 660.00
22,395.50
47 BERAPEN ( 1 : 5 ) t = 15 mm 1 M2
B037 5.670 Semen Kg 1,150.00 6,520.50
B011 0.023 Pasir Pasang M3 129,500.00 2,978.50
U08 0.070 Tukang Batu OH 49,500.00 3,465.00
U03 0.007 Kepala Tukang Batu OH 60,000.00 420.00
U16 0.150 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 4,650.00
U01 0.008 Mandor Lapangan OH 66,000.00 528.00
18,562.00
48 PEKERJAAN ACIAN 1 M2
B037 10.480 Semen Kg 1,150.00 12,052.00
U08 0.010 Tukang Batu OH 49,500.00 495.00
U03 0.001 Kepala Tukang Batu OH 60,000.00 60.00
U01 0.060 Mandor Lapangan OH 66,000.00 3,960.00
16,567.00
49 PLESTERAN BETON 1 PC : 2 PSR ( t : 15 MM ) 1 M2
B037 9.300 Semen Kg 1,150.00 10,695.00
B011 0.018 Pasir Pasang M3 129,500.00 2,331.00
U08 0.200 Tukang Batu OH 49,500.00 9,900.00
U03 0.020 Kepala Tukang Batu OH 60,000.00 1,200.00
U16 0.260 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 8,060.00
U01 0.013 Mandor Lapangan OH 66,000.00 858.00
33,044.00
50 PLESTERAN BETON 1 PC : 3 PSR ( t : 15 MM ) 1 M2
B037 7.070 Semen Kg 1,150.00 8,130.50
B011 0.021 Pasir Pasang M3 129,500.00 2,719.50
U08 0.200 Tukang Batu OH 49,500.00 9,900.00
U03 0.020 Kepala Tukang Batu OH 60,000.00 1,200.00
U16 0.260 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 8,060.00
U01 0.013 Mandor Lapangan OH 66,000.00 858.00
30,868.00
51 PLESTERAN SIAR ADUKAN ( 1PC : 2PS ) 1 M2
B037 4.320 Semen Kg 1,150.00 4,968.00
B011 0.016 Pasir Pasang M3 129,500.00 2,072.00
U08 0.070 Tukang Batu OH 49,500.00 3,465.00
U03 0.007 Kepala Tukang Batu OH 60,000.00 420.00
U16 0.150 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 4,650.00
U01 0.008 Mandor Lapangan OH 66,000.00 528.00
16,103.00
E PEKERJAAN BETON
52 MEMBUAT BETON NON STRUKTUR KLAS K.125
B012 0.5000 Pasir Beton M3 125,000.00 62,500.00
B037 6.6667 PC. Gresik 40 Kg Zak 46,000.00 306,666.67
B010 0.8333 Koral Beton / Kerikil M3 132,000.00 110,000.00
B111 0.0333 Papan Bakesting setarap Meranti M3 2,112,000.00 70,400.00
U01 0.1667 Mandor Lapangan OH 66,000.00 11,000.00
U08 0.1667 Tukang Batu OH 49,500.00 8,250.00
U15 0.3333 Pekerja Semi Terlatih OH 33,000.00 11,000.00
U16 2.0000 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 62,000.00
U43 0.1000 Alat Bantu Kerja Set 66,000.00 6,600.00
0.8333 Concrete Vibrator ( 4 HP ) (E.089) Jam 9,342.00 7,785.00
0.8333 Conc. Mixer 0,125 M3 / 6 HP (E.251) Jam 9,292.00 7,743.33
0.8333 Pump Water 30 M3 / hr ( 8 HP ) (E.341) Jam 11,860.00 9,883.33
673,828.33
53 MEMBUAT BETON TUMBUK ( 1 PC : 3 PS : 5 KR ) 1 M3
B037 218.000 Semen Kg 1,150.00 250,700.00
B012 0.520 Pasir Beton M3 125,000.00 65,000.00
B010 0.870 Koral Beton / Kerikil M3 132,000.00 114,840.00
U08 0.250 Tukang Batu OH 49,500.00 12,375.00
U03 0.025 Kepala Tukang Batu OH 60,000.00 1,500.00
U16 1.650 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 51,150.00
U01 0.080 Mandor Lapangan OH 66,000.00 5,280.00
500,845.00
54 MEMBUAT BETON BERTULANG CAMPURAN (1PC : 2PS : 3KR) 1 M3
B037 336.000 PC. Gresik 40 Kg Kg 1,150.00 386,400.00
B012 0.540 Pasir Beton M3 125,000.00 67,500.00
B010 0.810 Koral Beton M3 132,000.00 106,920.00
HARGA
NO. URAIAN PEKERJAAN SATUAN SATUAN HARGA
RP. RP.
1 2 3 4 5
U08 0.350 Tukang Batu OH 49,500.00 17,325.00
U03 0.035 Kepala Tukang Batu OH 60,000.00 2,100.00
U16 2.000 Pekerja / Pekerja Tidak Terlatih OH 31,000.00 62,000.00
U01 1.000 Mandor Lapangan OH 66,000.00 66,000.00
708,245.00
PEKERJAAN JALAN
74 PENYEDIAAN KERIKIL SUNGAI (TIDAK DISARING) M3
(Menggunakan Alat)
B010 1.0000 Kerikil Sungai M3 132,000.00 132,000.00
U01 0.0063 Mandor Lapangan OH 66,000.00 415.80
U30 0.0125 Operator - Trampil OH 49,500.00 618.75
U27 0.0500 Sopir Trampil OH 44,000.00 2,200.00
U16 0.0063 Pekerja / Pekerja Tak Terlatih OH 31,000.00 195.30
U43 0.0025 Alat Bantu Kerja Set 66,000.00 165.00
0.0188 Bulldoser ( 110 HP ) (E.001) Jam 370,459.00 6,964.63
0.0375 Loader Wheeled (115 HP ) (E.052) Jam 293,311.00 10,999.16
0.3000 Dump Truck 5 T ( 145 HP ) (E.212) Jam 177,892.00 53,367.60
206,926.24
BATU KALI
1 B001 Batu Kali M3 126,500.00
2 B002 Batu Pecah Besar 15/25 cm M3 137,500.00
3 B003 Batu Pecah 5/7 cm M3 137,500.00
4 B004 Batu Pecah 3/4 cm M3 187,000.00
5 B005 Batu Pecah 2/3 cm M3 154,000.00
6 B006 Batu Pecah Mesin 1 - 2 cm M3 159,500.00
7 B007 Batu Pecah 0,5 - 1 M3 165,000.00
8 B008 Split kasar M3 130,500.00
9 B009 Split Halus M3 198,000.00
10 B010 Koral Beton / Kerikil M3 132,000.00
Koral Sikat Zak 44,000.00
11 B011 Pasir Pasang M3 129,500.00
12 B012 Pasir Beton M3 125,000.00
13 B013 Pasir Urug M3 110,000.00
14 B014 Sirtu M3 72,500.00
15 B015 Batu Karang Bukit M3 116,000.00
16 B016 Tanah Urug M3 82,500.00
17 B017 Limestone M3 110,000.00
18 B018 Bata Merah Klas I Bj 1,300.00
19 B019 Bata Merah Klas II Bj 1,100.00
20 B020 Bata Merah Klas III Bj 850.00
21 B021 Bata Merah Super ( Pripian ) Bj 2,300.00
22 B022 Paras Ukir Silakarang Klas I Tipis (3x15x40) Bj 118,500.00
23 B023 Paras Ukir Silakarang Klas I Tebal (4x15x40) Bh 137,500.00
24 B024 Paras Krobokan Bh 137,500.00
25 B025 Batako Lubang Bj 1,700.00
26 B026 Batako Padat Bj 1,850.00
27 B027 Bentala Exs Kapal Bj 55,400.00
28 B028 Ikut Celedu Bj 165,000.00
29 B029 Batu Tabas Eks Karangasem (3x15x40) Bj 17,000.00
30 B030 Karung Plastik Bh 5,500.00
31 B031 Batu Gosok Bh 5,500.00
32 B032 Murda / Puntal Paras Bh 176,000.00
33 B033 Filler Kg 1,350.00
B034 SEMEN
34 B035 PC. Tiga Roda 50 Kg Zak 56,650.00
35 B036 PC. Tonasa 50 Kg / Busoa 50 Kg Zak 55,000.00
36 B037 PC. Gresik 40 Kg Zak 46,000.00
37 B038 PC. Gresik 50 Kg Zak 57,500.00
38 B039 PC Tiga Roda 40 Kg Zak 45,320.00
39 B040 PC Tonasa 40 Kg Zak 44,000.00
40 B041 Semen Warna Kg 13,000.00
B042 BAHAN ATAP
41 B043 Genteng Pejaten Mini Bj 1,400.00
42 B044 Genteng Plentong Pejaten / Darmasaba Bj 1,650.00
43 B045 Genteng Bambe Kecil Bj 4,200.00
44 B046 Genteng Plentong Pejaten / Jatiwangi / Surabaya Bj 3,300.00
45 B047 Genteng Bambe Karang Pilang Bj 3,850.00
46 B048 Genteng Kodok Lokal Bj 2,200.00
47 B049 Genteng Kodok Karang Pilang (Surabaya) Bj 3,300.00
48 B050 Genteng Gerard Polos M2 187,500.00
49 B051 Bubungan Bambe Kecil Bj 4,400.00
50 B052 Bubungan Karang Pilang Bj 13,750.00
51 B053 Bubungan Plentong Jatiwangi Bj 10,500.00
52 B054 Bubungan Besar Bj 4,400.00
53 B055 Bubungan Kecil Bj 2,750.00
54 B056 Bubungan Gerad Lbr 49,500.00
55 B057 Sirap Lbr 3,850.00
56 B058 Seng BJLS 0,18 gelombang Lbr 49,500.00
57 B059 Seng BJLS 0,22 gelombang Lbr 57,000.00
58 B060 Seng BJLS 0,30 gelombang Lbr 68,000.00
59 B061 Seng Plat Lebar 0,90 M Lbr 30,000.00
60 B062 Seng Plat Aluminium Lbr 82,500.00
NO NAMA BAHAN SATUAN HARGA SATUAN KETERANGAN
(RP)
1 2 3 4 5
B198
NO NAMA BAHAN SATUAN HARGA SATUAN KETERANGAN
(RP)
1 2 3 4 5
B199 CAT
191 B200 Cat Marka Jalan Kg 16,500.00
192 B201 Glas Bit Kg 17,000.00
193 B202 Cat Menie besi Kg 27,500.00
194 B203 Cat Menie Fako Kg 31,000.00
195 B204 Cat Menie Kg 31,000.00
196 B205 Cat Menie Altek Kg 31,000.00
197 B206 Cat Emco Lux Biasa Kg 44,000.00
198 B207 Cat Emco Lux Warna Kg 49,500.00
199 B208 Cat Emco Lux Warna Tua Kg 55,000.00
200 B209 Cat Dasar Kg 33,000.00
201 B210 Cat Galvanis Kg 48,000.00
202 B211 Tinner Spesial Ltr 30,500.00
203 B212 Dempul / Plamur Kg 22,000.00
204 B213 Dempul / Plamur Altik Kg 23,000.00
205 B214 Politur Jadi Kg 27,500.00
206 B215 Politur Vernis Ltr 37,000.00
207 B216 Politur Ltr 56,000.00
208 B217 Politur tua Ltr 62,500.00
209 B218 Teack Oil Ltr 49,500.00
210 B219 Wood Filer Ltr 23,000.00
211 B220 Sending Seaker Ltr 55,000.00
212 B221 Plamur Kayu Kg 20,500.00
213 B222 Plamur Tembok Kg 11,000.00
214 B223 Oker / Veap Kg 22,000.00
215 B224 Melamine lack Ltr 34,000.00
216 B225 Cat Tembok ( Vinilex) Kg 22,000.00
217 B226 Cat Tembok ( Docolit ) Kg 26,500.00
218 B227 Cat Tembok ( Paragon ) Kg 18,500.00
219 B228 Cat Tembok ( Vinipaint ) Kg 13,500.00
220 B229 Cat Tembok ( Bintang ) Kg 23,500.00
221 B230 Cat Tembok ( Sunlex ) Gln 247,500.00
222 B231 Residu / Teer Gln 42,300.00
223 B232 Minyak Cat Afduner Ltr 9,500.00
224 B233 Amplas Ltr 3,800.00
225 B234 Lem Aica Aibon Kg 47,500.00
226 B235 Lem Fox Gln 121,000.00
227 B236 Politur Ultran Kg 46,000.00
228 B237 Kuas Bh 5,500.00
B238 KUNCI
229 B239 Kunci kuda 1 x putar Bh 55,000.00
230 B240 Kunci kuda 2 x putar Bh 66,000.00
231 B241 Kunci shang hae 2 x putar Bh 121,000.00
232 B242 Kunci lif 1 x putar Bh 93,500.00
233 B243 Kunci lif 2 x putar Bh 104,500.00
234 B244 Kunci alfa bundar 2 x putar Bh 110,000.00
235 B245 Kunci Union 1 x putar Bh 137,500.00
236 B246 Kunci Union 2 x putar Bh 148,500.00
237 B247 Kunci Yale 2 x putar Bh 192,500.00
238 B248 Kait angin lipat Bh 38,500.00
239 B249 Kait angin biasa Bh 22,000.00
240 B250 Kait angin tarik Bh 33,000.00
241 B251 Grendel Biasa Bh 13,200.00
242 B252 Grendel tanam Bh 31,500.00
243 B253 Engsel H Ps 16,500.00
244 B254 Engsel pintu nylon Ps 38,500.00
245 B255 Engsel jendela nylon Ps 31,500.00
246 B256 Espanolet Bh 66,000.00
247 B257 Rolling door plaat M2 81,500.00
248 B258 Rolling door aluminium M2 623,000.00
B259 KABEL
250 B260 Kabel NYM 2 x 1 1/2 mm M1 7,700.00
251 B261 Kabel NYM 2 x 2 1/2 mm M1 8,800.00
252 B262 Kabel NYM 3 x 2 1/2 mm M1 11,000.00
253 B263 Kabel NYM 2 x 1 1/2 mm warna hitam M1 7,700.00
254 B264 Kabel NYM 3 x 1 1/2 mm warna hitam M1 11,000.00
255 B265 Kabel NYM 3 x 2 1/2 mm warna hitam M1 13,200.00
256 B266 Kabel Twisteed 2 x 16 mm M' 68,200.00
257 B267 Kabel NYY 2 x 2,5 mm M' 11,200.00
NO NAMA BAHAN SATUAN HARGA SATUAN KETERANGAN
(RP)
1 2 3 4 5
B337 TALAN G
326 B338 Talang Karet L = 0,50 M1 11,000.00
327 B339 Talang Karet L = 0,90 M1 18,500.00
B340 ASPAL, BBM DAN PELUMAS
328 B341 Aspal Penetrasi 60/70 Kg 8,500.00
329 B342 Aspal Curah Kg 7,500.00
330 B343 Aspal RC Ltr 7,500.00
Aspal Emulsi Ltr 8,000.00
331 B344 Minyak Aspal ( fluck oil ) Ltr 14,000.00
332 B345 Minyak Tanah Ltr 6,000.00
333 B346 Minyak Tanah Industri Ltr 6,000.00
334 B347 Solar Ltr 4,500.00
335 B348 Solar Industri Ltr 5,500.00
336 B349 Premium Ltr 4,500.00
337 B350 Pelumas ( olie ) Ltr 30,500.00
338 B351 Kayu Api M3 275,000.00
339 B352 Gas elpiji Kg 6,500.00
340 B353 Minyak Begesting Ltr
Denpasar,
UPAH KERJA
1 U01 Mandor Lapangan 66,000.00 OH
2 U02 Kepala Tukang Besi 66,000.00 OH
3 U03 Kepala Tukang Batu 60,000.00 OH
4 U04 Kepala Tukang Kayu 60,000.00 OH
5 U05 Kepala Tukang Cat 60,000.00 OH
6 U06 Kepala Tukang Paras Bali 60,000.00 OH
7 U07 Kepala Tukang Ukir 77,000.00 OH
8 U08 Tukang Batu 49,500.00 OH
9 U09 Tukang Besi 55,000.00 OH
10 U10 Tukang Kayu 55,000.00 OH
11 U11 Tukang Cat 49,500.00 OH
12 U12 Tukang Ukir 60,000.00 OH
13 U13 Tukang Paras Bali 55,000.00 OH
14 U14 Pekerja Terlatih 38,500.00 OH
15 U15 Pekerja Semi Terlatih 33,000.00 OH
15 U16 Pekerja / Pekerja Tidak Terlatih 31,000.00 OH
16 U17 Tukang Bongkar Bekesting 31,000.00 OH
17 U18 Tukang Gali 46,000.00 OH
18 U19 Tukang Listrik 49,500.00 OH
19 U20 Tukang Ledeng 49,500.00 OH
20 U21 Kepala Tukang Ledeng 55,000.00 OH
21 U22 Tukang Las 44,000.00 OH
22 U23 Tukang Masak Aspal 44,000.00 OH
23 U24 Tukang Cor Aspal 44,000.00 OH
24 U25 Pekerja Pembantu Tukang Aspal 27,500.00 OH
25 U26 Penjaga Api 27,500.00 OH
26 U27 Sopir SIM. A 44,000.00 OH
27 U28 Sopir SIM. B1 44,000.00 OH
28 U29 Sopir SIM. B2 44,000.00 OH
29 U30 Operator Terampil 49,500.00 OH
30 U31 Operator Semi Trampil 44,000.00 OH
30 U32 Pembantu Operator 38,500.00 OH
31 U33 Pembantu Sopir 38,500.00 OH
32 U34 Mekanik Trampil 38,500.00 OH
32 U35 Masinis 49,500.00 OH
33 U36 Pembantu Masinis 38,500.00 OH
34 U37 Sewa Wales 198,000.00 OH
35 U38 Ongkos Kerja Pemasangan dan Pengelasan 11,500.00 OH
36 U39 Ongkos Potong Besi 11,500.00 OH
37 U40 Wheel Loader 198,000.00 Jam
38 U41 Dump Truck 110,000.00 Jam
39 U42 Aspal Apayer 60,000.00 Jam
40 U43 Alat Bantu 66,000.00 Set
41 U44 Ongkos Pemasangan Lampu 220,000.00 Ls
42 U45 Ongkos Pemasangan Panel 275,000.00 Ls
Denpasar,