b = 700 mm
h = 700 mm
D = 22 mm (Diameter Tulangan)
f'c = 24.9 Mpa
fy = 240 MPa
d = 660 mm
d' = 40 mm
n.tul = 8 bh ( Jumlah Tulangan )
y = 350 mm
Pn(max) = 0.8 x Po
= 0.8 x 11036.3407
= 8829.0726 kN
eksentrisitas minimum
emin = 0.1 x h
= 0.1 x 700
= 70 mm
= 5936782.5 N
= 5936.7825 kN
Mnb = Pnb x eb
Cb = 600 x d
600 + fy
= 600 x 660
600 + 240
= 471.4285714 mm
ab = 0.85 x Cb
= 0.85 x 471.42857
= 400.7142857 mm
= 600 x 471.4286 - 40
[ ]
471
= 549.090909
fs' ≥ fy → fs' = fy = 240
fs = Es x Ɛ's = = 600 x d - c
[ ]
c
= 240
= 1114652085 Nmm
= 1114.652085 kNm
eb = Mnb
Pnb
= 0.187753566 m
= 187.753566 mm
ɸ x Pnb = 3858.9086 kN
ɸ x Mnb = 891.72167 kN
Mn = As x fy ( d - 0.59 x As x fy )
fc' x b
= 236.3442553 kNm
2000
1000
0
0 200 400 600 800 1000 1200
MN, φMN
Dimensi Kolom
Lebar Kolom : b (mm) 700.00
Tinggi Kolom : h (mm) 700.00
Selimut Beton : d' (mm) 40.00
Tinggi Efektif Beton : d = h – d' (mm) 660.00
s ≤ smax
150.00 mm ≤ 300.00 mm … OK !!
Kuat Geser Beton dan Baja Tulangan
Kuat Geser Beton : Vc = 1/6 [ (√ fc') / (b d) ] (kN) 384.23
Kuat Geser Tulangan Geser : Vs = (Av fy ds) / s (kN) 165.88
b = 700 mm
h = 700 mm
D = 22 mm (Diameter Tulangan)
f'c = 24.9 Mpa
fy = 240 MPa
d = 660 mm
d' = 40 mm
n.tul = 16 bh ( Jumlah Tulangan )
y = 350 mm
Pn(max) = 0.8 x Po
= 0.8 x 11701.8315
= 9361.4652 kN
eksentrisitas minimum
emin = 0.1 x h
= 0.1 x 700
= 70 mm
= 5936782.5 N
= 5936.7825 kN
Mnb = Pnb x eb
Cb = 600 x d
600 + fy
= 600 x 660
600 + 240
= 471.4285714 mm
ab = 0.85 x Cb
= 0.85 x 471.42857
= 400.7142857 mm
= 600 x 471.4286 - 40
[ ]
471
= 549.090909
fs' ≥ fy → fs' = fy = 240
fs = Es x Ɛ's = = 600 x d - c
[ ]
c
= 240
= 1340907075 Nmm
= 1340.907075 kNm
eb = Mnb
Pnb
= 0.225864275 m
= 225.8642749 mm
ɸ x Pnb = 3858.9086 kN
ɸ x Mnb = 1072.7257 kN
Mn = As x fy ( d - 0.59 x As x fy )
fc' x b
= 463.6728495 kNm
7000
ɸMn vs ɸPn
6000
0 0
ɸMnb vs ɸPnb
3859
5000 1073
Data P vs M3
4000
Data P vs M2
3000
2000
1000
0
0 200 400 600 800 1000 1200 1400 1600
MN, φMN
Dimensi Kolom
Lebar Kolom : b (mm) 700.00
Tinggi Kolom : h (mm) 700.00
Selimut Beton : d' (mm) 40.00
Tinggi Efektif Beton : d = h – d' (mm) 660.00
s ≤ smax
150.00 mm ≤ 300.00 mm … OK !!
Kuat Geser Beton dan Baja Tulangan
Kuat Geser Beton : Vc = 1/6 [ (√ fc') / (b d) ] (kN) 384.23
Kuat Geser Tulangan Geser : Vs = (Av fy ds) / s (kN) 165.88
Kolom Lantai 1
b = 700 mm
h = 700 mm
D = 22 mm (Diameter Tulangan)
f'c = 24.9 Mpa
fy = 240 MPa
d = 660 mm
d' = 40 mm
n.tul = 16 bh ( Jumlah Tulangan )
y = 350 mm
Pn(max) = 0.8 x Po
= 0.8 x 11701.8315
= 9361.4652 kN
eksentrisitas minimum
emin = 0.1 x h
= 0.1 x 700
= 70 mm
= 5936782.5 N
= 5936.7825 kN
Mnb = Pnb x eb
Cb = 600 x d
600 + fy
= 600 x 660
600 + 240
= 471.4285714 mm
ab = 0.85 x Cb
= 0.85 x 471.42857
= 400.7142857 mm
= 600 x 471.4286 - 40
[ ]
471
= 549.090909
fs' ≥ fy → fs' = fy = 240
fs = Es x Ɛ's = = 600 x d - c
[ ]
c
= 240
= 1340907075 Nmm
= 1340.907075 kNm
eb = Mnb
Pnb
= 0.225864275 m
= 225.8642749 mm
ɸ x Pnb = 3858.9086 kN
ɸ x Mnb = 1072.7257 kN
Mn = As x fy ( d - 0.59 x As x fy )
fc' x b
= 463.6728495 kNm
7000
ɸMn vs ɸPn
6000
0 0
ɸMnb vs ɸPnb
3859
5000 1073
Data P vs M3
4000
Data P vs M2
3000
2000
1000
0
0 200 400 600 800 1000 1200 1400 1600
MN, φMN
Kolom Lantai1
Dimensi Kolom
Lebar Kolom : b (mm) 700.00
Tinggi Kolom : h (mm) 700.00
Selimut Beton : d' (mm) 40.00
Tinggi Efektif Beton : d = h – d' (mm) 660.00
s ≤ smax
150.00 mm ≤ 300.00 mm … OK !!
Kuat Geser Beton dan Baja Tulangan
Kuat Geser Beton : Vc = 1/6 [ (√ fc') / (b d) ] (kN) 384.23
Kuat Geser Tulangan Geser : Vs = (Av fy ds) / s (kN) 165.88
Kolom Lantai 2
b = 500 mm
h = 500 mm
D = 22 mm (Diameter Tulangan)
f'c = 24.9 Mpa
fy = 240 MPa
d = 460 mm
d' = 40 mm
n.tul = 16 bh ( Jumlah Tulangan )
y = 250 mm
Pn(max) = 0.8 x Po
= 0.8 x 6622.23147
= 5297.7852 kN
eksentrisitas minimum
emin = 0.1 x h
= 0.1 x 500
= 50 mm
= 2955541.071 N
= 2955.541071 kN
Mnb = Pnb x eb
Cb = 600 x d
600 + fy
= 600 x 460
600 + 240
= 328.5714286 mm
ab = 0.85 x Cb
= 0.85 x 328.57143
= 279.2857143 mm
= 600 x 328.5714 - 40
[ ]
329
= 526.956522
fs' ≥ fy → fs' = fy = 240
fs = Es x Ɛ's = = 600 x d - c
[ ]
c
= 240
= 632704086.5 Nmm
= 632.7040865 kNm
eb = Mnb
Pnb
= 0.21407386 m
= 214.0738603 mm
ɸ x Pnb = 1921.1017 kN
ɸ x Mnb = 506.16327 kN
Mn = As x fy ( d - 0.59 x As x fy )
fc' x b
= 310.4893597 kNm
6000
5000P M ɸP ɸM
6622 0 4304 0
5298
4000 310 3444 248 Mn Vs Pn
PN,φPN
0 0 Data P vs M3
2000
1921 506 Data P vs M2
1000
0
0 100 200 300 400 500 600 700
MN, φMN
Kolom Lantai2
Dimensi Kolom
Lebar Kolom : b (mm) 500.00
Tinggi Kolom : h (mm) 500.00
Selimut Beton : d' (mm) 40.00
Tinggi Efektif Beton : d = h – d' (mm) 460.00
s ≤ smax
100.00 mm ≤ 230.00 mm … OK !!
Kuat Geser Beton dan Baja Tulangan
Kuat Geser Beton : Vc = 1/6 [ (√ fc') / (b d) ] (kN) 191.28
Kuat Geser Tulangan Geser : Vs = (Av fy ds) / s (kN) 173.42
Kolom Lantai 3
b = 500 mm
h = 500 mm
D = 22 mm (Diameter Tulangan)
f'c = 24.9 Mpa
fy = 240 MPa
d = 460 mm
d' = 40 mm
n.tul = 16 bh ( Jumlah Tulangan )
y = 250 mm
Pn(max) = 0.8 x Po
= 0.8 x 6622.23147
= 5297.7852 kN
eksentrisitas minimum
emin = 0.1 x h
= 0.1 x 500
= 50 mm
= 2955541.071 N
= 2955.541071 kN
Mnb = Pnb x eb
Cb = 600 x d
600 + fy
= 600 x 460
600 + 240
= 328.5714286 mm
ab = 0.85 x Cb
= 0.85 x 328.57143
= 279.2857143 mm
= 600 x 328.5714 - 40
[ ]
329
= 526.956522
fs' ≥ fy → fs' = fy = 240
fs = Es x Ɛ's = = 600 x d - c
[ ]
c
= 240
= 632704086.5 Nmm
= 632.7040865 kNm
eb = Mnb
Pnb
= 0.21407386 m
= 214.0738603 mm
ɸ x Pnb = 1921.1017 kN
ɸ x Mnb = 506.16327 kN
Mn = As x fy ( d - 0.59 x As x fy )
fc' x b
= 310.4893597 kNm
6000
5000P M ɸP ɸM
6622 0 4304 0
5298
4000 310 3444 248 Mn Vs Pn
PN,φPN
0 0 Data P vs M3
2000
1921 506 Data P vs M2
1000
0
0 100 200 300 400 500 600 700
MN, φMN
Kolom Lantai3
Dimensi Kolom
Lebar Kolom : b (mm) 500.00
Tinggi Kolom : h (mm) 500.00
Selimut Beton : d' (mm) 40.00
Tinggi Efektif Beton : d = h – d' (mm) 460.00
s ≤ smax
100.00 mm ≤ 230.00 mm … OK !!
Kuat Geser Beton dan Baja Tulangan
Kuat Geser Beton : Vc = 1/6 [ (√ fc') / (b d) ] (kN) 191.28
Kuat Geser Tulangan Geser : Vs = (Av fy ds) / s (kN) 173.42
Kolom Lantai 4
b = 500 mm
h = 500 mm
D = 22 mm (Diameter Tulangan)
f'c = 24.9 Mpa
fy = 240 MPa
d = 460 mm
d' = 40 mm
n.tul = 16 bh ( Jumlah Tulangan )
y = 250 mm
Pn(max) = 0.8 x Po
= 0.8 x 6622.23147
= 5297.7852 kN
eksentrisitas minimum
emin = 0.1 x h
= 0.1 x 500
= 50 mm
= 2955541.071 N
= 2955.541071 kN
Mnb = Pnb x eb
Cb = 600 x d
600 + fy
= 600 x 460
600 + 240
= 328.5714286 mm
ab = 0.85 x Cb
= 0.85 x 328.57143
= 279.2857143 mm
= 600 x 328.5714 - 40
[ ]
329
= 526.956522
fs' ≥ fy → fs' = fy = 240
fs = Es x Ɛ's = = 600 x d - c
[ ]
c
= 240
= 632704086.5 Nmm
= 632.7040865 kNm
eb = Mnb
Pnb
= 0.21407386 m
= 214.0738603 mm
ɸ x Pnb = 1921.1017 kN
ɸ x Mnb = 506.16327 kN
Mn = As x fy ( d - 0.59 x As x fy )
fc' x b
= 310.4893597 kNm
6000
5000P M ɸP ɸM
6622 0 4304 0
5298
4000 310 3444 248 Mn Vs Pn
PN,φPN
0 0 Data P vs M3
2000
1921 506 Data P vs M2
1000
0
0 100 200 300 400 500 600 700
MN, φMN
Kolom Lantai 4
Dimensi Kolom
Lebar Kolom : b (mm) 500.00
Tinggi Kolom : h (mm) 500.00
Selimut Beton : d' (mm) 40.00
Tinggi Efektif Beton : d = h – d' (mm) 460.00
s ≤ smax
100.00 mm ≤ 230.00 mm … OK !!
Kuat Geser Beton dan Baja Tulangan
Kuat Geser Beton : Vc = 1/6 [ (√ fc') / (b d) ] (kN) 191.28
Kuat Geser Tulangan Geser : Vs = (Av fy ds) / s (kN) 173.42
b = 500 mm
h = 500 mm
D = 22 mm (Diameter Tulangan)
f'c = 24.9 Mpa
fy = 240 MPa
d = 460 mm
d' = 40 mm
n.tul = 16 bh ( Jumlah Tulangan )
y = 250 mm
Pn(max) = 0.8 x Po
= 0.8 x 6622.23147
= 5297.7852 kN
eksentrisitas minimum
emin = 0.1 x h
= 0.1 x 500
= 50 mm
= 2955541.071 N
= 2955.541071 kN
Mnb = Pnb x eb
Cb = 600 x d
600 + fy
= 600 x 460
600 + 240
= 328.5714286 mm
ab = 0.85 x Cb
= 0.85 x 328.57143
= 279.2857143 mm
= 600 x 328.5714 - 40
[ ]
329
= 526.956522
fs' ≥ fy → fs' = fy = 240
fs = Es x Ɛ's = = 600 x d - c
[ ]
c
= 240
= 632704086.5 Nmm
= 632.7040865 kNm
eb = Mnb
Pnb
= 0.21407386 m
= 214.0738603 mm
ɸ x Pnb = 1921.1017 kN
ɸ x Mnb = 506.16327 kN
Mn = As x fy ( d - 0.59 x As x fy )
fc' x b
= 310.4893597 kNm
6000
5000P M ɸP ɸM
6622 0 4304 0
5298
4000 310 3444 248 Mn Vs Pn
PN,φPN
0 0 Data P vs M3
2000
1921 506 Data P vs M2
1000
0
0 100 200 300 400 500 600 700
MN, φMN
Dimensi Kolom
Lebar Kolom : b (mm) 500.00
Tinggi Kolom : h (mm) 500.00
Selimut Beton : d' (mm) 40.00
Tinggi Efektif Beton : d = h – d' (mm) 460.00
s ≤ smax
150.00 mm ≤ 230.00 mm … OK !!
Kuat Geser Beton dan Baja Tulangan
Kuat Geser Beton : Vc = 1/6 [ (√ fc') / (b d) ] (kN) 191.28
Kuat Geser Tulangan Geser : Vs = (Av fy ds) / s (kN) 115.61