CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

OBRA: "CREACION DE LA PLAZA DE ARMAS"

MES 1 MES 2 MES 3

Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) % Monto S/ % Monto S/ % Monto S/

CREACION DE LA PLAZA DE ARMAS 802,028.83

01.00.00 OBRAS PROVISIONALES 59,604.77


01.01.00 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60m x 2.40m u 1.00 854.16 854.16 100.00% 854.16 0.00% 0.00 0.00% 0.00
01.02.00 MOVILIZACION Y DESMOVILIZACION glb 1.00 14,785.47 14,785.47 50.00% 7,392.74 0.00% 0.00 50.00% 7,392.74
01.03.00 ALQUILER DE CASETA PARA OFICINA , ALMACEN Y GUARDIANIA mes 3.00 250.00 750.00 33.33% 250.00 33.33% 250.00 33.33% 250.00
01.04.00 TRANSPORTE DE MATERIAL A OBRA glb 1.00 43,215.14 43,215.14 33.33% 14,405.05 33.33% 14,405.05 33.33% 14,405.05
02.00.00 OBRAS PRELIMINARES 16,993.28
02.01.00 LIMPIEZA DE TERRENO NORMAL m2 7,654.63 1.18 9,032.46 100.00% 9,032.46 0.00% 0.00 0.00% 0.00
02.02.00 TRAZO Y REPLANTEO PRELIMINAR m2 7,654.63 1.04 7,960.82 100.00% 7,960.82 0.00% 0.00 0.00% 0.00
03.00.00 MOVIMIENTO DE TIERRAS 117,133.66
03.01.00 EXCAVACION MASIVA EN TERRENO NORMAL m3 668.71 4.39 2,935.64 100.00% 2,935.64 0.00% 0.00 0.00% 0.00
03.02.00 PERFILADO, NIVELACIÓN Y COMPACTACIÓN DE SUBRASANTE m2 5,710.10 1.41 8,051.24 100.00% 8,051.24 0.00% 0.00 0.00% 0.00
03.03.00 BASE DE AFIRMADO e=0.10m PARA PISOS m2 5,498.60 12.60 69,282.36 85.00% 58,890.01 15.00% 10,392.35 0.00% 0.00
03.04.00 SUB BASE DE HORMIGON e=0.15m PARA PISOS DE ADOQUIN DE CONCRETO m2 1,372.25 16.71 22,930.30 100.00% 22,930.30 0.00% 0.00 0.00% 0.00
03.05.00 ELIMINACION DE MATERIAL EXCEDENTE m3 835.88 16.67 13,934.12 0.00% 0.00 0.00% 0.00 100.00% 13,934.12
04.00.00 CONCRETO SIMPLE 117,879.10
04.01.00 CIMIENTOS CORRIDOS 9,066.95
04.01.01 CIMIENTOS CONCRETO CICLOPEO 1:10 + 30% P.M. m3 27.26 332.61 9,066.95 0.00% 0.00 100.00% 9,066.95 0.00% 0.00
04.02.00 SARDINELES 64,993.88
04.02.01 CONCRETO f´c= 175 kg/cm2 EN SARDINELES INCL./TARRAJEO PULIDO Y PINTADO m3 91.27 355.09 32,409.06 0.00% 0.00 100.00% 32,409.06 0.00% 0.00
04.02.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 912.74 35.70 32,584.82 0.00% 0.00 100.00% 32,584.82 0.00% 0.00
04.03.00 FALSO PISO 27,362.87
04.03.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 856.16 31.96 27,362.87 0.00% 0.00 100.00% 27,362.87 0.00% 0.00
04.04.00 CONTRAPISOS 16,455.40
04.04.01 CONTRAPISO DE 25 mm. m2 856.16 19.22 16,455.40 0.00% 0.00 100.00% 16,455.40 0.00% 0.00
05.00.00 CONCRETO ARMADO 57,565.09
05.01.00 MUROS DE CONCRETO REFORZADO 3,512.83
05.01.01 CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 3.18 383.49 1,219.50 0.00% 0.00 100.00% 1,219.50 0.00% 0.00
05.01.02 ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS m2 43.02 35.70 1,535.81 0.00% 0.00 100.00% 1,535.81 0.00% 0.00
05.01.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 254.20 2.98 757.52 0.00% 0.00 100.00% 757.52 0.00% 0.00
05.02.00 JARDINERAS DE CONCRETO REFORZADO 39,467.75
05.02.01 CONCRETO f´c=210 kg/cm2 PARA JARDINERAS DE CONCRETO REFORZADO INCL./TARRAJEO Y PINTADO m3 41.82 383.49 16,037.55 0.00% 0.00 100.00% 16,037.55 0.00% 0.00
05.02.02 ENCOFRADO Y DESENCOFRADO EN JARDINERAS DE CONCRETO REFORZADO m2 466.97 39.07 18,244.52 0.00% 0.00 100.00% 18,244.52 0.00% 0.00
05.02.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 1,740.16 2.98 5,185.68 0.00% 0.00 100.00% 5,185.68 0.00% 0.00
05.03.00 PILETA DE CONCRETO REFORZADO 11,162.36
05.03.01 CONCRETO f´c=210 kg/cm2 CON GRANITO COLOR GRIS PARA PILETA DE CONCRETO REFORZADO m3 17.39 383.49 6,668.89 0.00% 0.00 100.00% 6,668.89 0.00% 0.00
05.03.02 ENCOFRADO Y DESENCOFRADO EN PILETA DE CONCRETO REFORZADO m2 72.48 39.07 2,831.79 0.00% 0.00 100.00% 2,831.79 0.00% 0.00
05.03.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 557.61 2.98 1,661.68 0.00% 0.00 100.00% 1,661.68 0.00% 0.00
05.04.00 CISTERNA 3,422.15
05.04.01 CISTERNA DE CONCRETO f´c=175Kg/cm2 m3 3.28 355.09 1,164.70 0.00% 0.00 100.00% 1,164.70 0.00% 0.00
05.04.02 ENCOFRADO Y DESENCOFRADO EN CISTERNA m2 31.47 39.07 1,229.53 0.00% 0.00 100.00% 1,229.53 0.00% 0.00
05.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 344.94 2.98 1,027.92 0.00% 0.00 100.00% 1,027.92 0.00% 0.00
06.00.00 CARPINTERIA DE MADERA 45,268.40
06.01.00 PERGOLAS SEGÚN DISEÑO glb 4.00 5,000.00 20,000.00 0.00% 0.00 20.00% 4,000.00 80.00% 16,000.00
06.02.00 BANCAS (1.60m x 0.56m) u 60.00 421.14 25,268.40 0.00% 0.00 25.00% 6,317.10 75.00% 18,951.30
07.00.00 PISOS Y PAVIMENTOS 306,272.24
07.01.00 PISO DE ADOQUÍN 111,742.32
07.01.01 CAMA DE ARENA DE e=5cm m2 1,372.25 10.12 13,887.17 0.00% 0.00 0.00% 0.00 100.00% 13,887.17
07.01.02 CORTE Y SELLADO DE JUNTAS m2 1,372.25 13.30 18,250.93 0.00% 0.00 0.00% 0.00 100.00% 18,250.93
07.01.03 PISO DE ADOQUIN COLOR GRIS DE e=8cm m2 1,372.25 58.01 79,604.22 0.00% 0.00 0.00% 0.00 100.00% 79,604.22
07.02.00 PISO DE CEMENTO PULIDO 145,163.73
07.02.01 PISO DE CEMENTO PULIDO COLOR GRIS INCL./ENCOFRADO m2 3,270.19 44.39 145,163.73 0.00% 0.00 20.00% 29,032.75 80.00% 116,130.98
07.03.00 PISO DE CERAMICO 49,366.19
07.03.01 PISO DE CERAMICO TIPO RUSTICO m2 856.16 57.66 49,366.19 0.00% 0.00 25.00% 12,341.55 75.00% 37,024.64
08.00.00 JARDINERIA Y AREAS VERDES 7,490.95
08.01.00 SEMBRADO DE GRASS m2 1,789.86 2.75 4,922.12 0.00% 0.00 0.00% 0.00 100.00% 4,922.12
08.02.00 SEMBRADO DE ARBOLES u 12.00 22.90 274.80 0.00% 0.00 0.00% 0.00 100.00% 274.80
08.03.00 SEMBRADO DE PLANTONES u 148.00 13.92 2,060.16 0.00% 0.00 0.00% 0.00 100.00% 2,060.16
08.04.00 SEMBRADO DE GINGER m2 182.71 1.28 233.87 0.00% 0.00 0.00% 0.00 100.00% 233.87
09.00.00 REVOQUES, ENLUCIDOS Y MOLDURAS 975.61
09.01.00 TARRAJEO FINO CON CEMENTO-CAL-ARENA m2 37.06 16.39 607.41 0.00% 0.00 100.00% 607.41 0.00% 0.00
09.02.00 TARRAJEO CON IMPERMEABILIZANTES m2 16.89 21.80 368.20 0.00% 0.00 100.00% 368.20 0.00% 0.00
10.00.00 PINTURA 481.41
10.01.00 PINTURA LATEX 02 MANOS m2 37.06 12.99 481.41 0.00% 0.00 0.00% 0.00 100.00% 481.41
11.00.00 INSTALACIONES SANITARIAS 1,862.32
11.01.00 RED DE AGUA TUBERIA PVC SAP Ø=3/4" m 2.71 2.61 7.07 0.00% 0.00 100.00% 7.07 0.00% 0.00
11.02.00 RED DE AGUA TUBERIA PVC SAP Ø=3/4" CON AGUJEROS Ø=1/4" m 11.00 4.98 54.78 0.00% 0.00 100.00% 54.78 0.00% 0.00
11.03.00 RED DE AGUA TUBERIA PVC SAP Ø=1" m 83.66 2.64 220.86 0.00% 0.00 100.00% 220.86 0.00% 0.00
11.04.00 VALVULA DE COMPUERTA DE BRONCE DE 3/4" u 1.00 80.15 80.15 0.00% 0.00 100.00% 80.15 0.00% 0.00
11.05.00 CAJA DE CONCRETO DE 12"x24" PARA AGUA u 1.00 71.55 71.55 0.00% 0.00 100.00% 71.55 0.00% 0.00
11.06.00 ELECTROBOMBA SUMERGIBLE 0.5 HP u 1.00 471.50 471.50 0.00% 0.00 0.00% 0.00 100.00% 471.50
11.07.00 SUMINISTRO E INSTALACION DE ACCESORIOS PARA CISTERNA glb 1.00 763.64 763.64 0.00% 0.00 0.00% 0.00 100.00% 763.64
11.08.00 PRUEBA HIDRAULICA m 97.36 1.98 192.77 0.00% 0.00 0.00% 0.00 100.00% 192.77
12.00.00 INSTALACIONES ELECTRICAS 54,218.26
12.01.00 SALIDA PARA FAROLAS ORNAMENTALES u 66.00 111.69 7,371.54 0.00% 0.00 100.00% 7,371.54 0.00% 0.00
12.02.00 SALIDA DE FUERZA PARA ELECTROBOMBA SUMERGIBLE u 1.00 111.64 111.64 0.00% 0.00 0.00% 0.00 100.00% 111.64
12.03.00 FAROLAS ORNAMENTALES u 66.00 682.95 45,074.70 0.00% 0.00 100.00% 45,074.70 0.00% 0.00
12.04.00 MURO DE CONCRETO PARA TABLERO ELECTRICO u 1.00 820.61 820.61 0.00% 0.00 100.00% 820.61 0.00% 0.00
12.05.00 TABLERO ELECTRICO DE 12 POLOS u 1.00 276.25 276.25 0.00% 0.00 100.00% 276.25 0.00% 0.00
12.06.00 INTERRUPTOR THERMOMAGNETICO 2X125A u 1.00 136.87 136.87 0.00% 0.00 100.00% 136.87 0.00% 0.00
12.07.00 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 30A pza 2.00 55.40 110.80 0.00% 0.00 100.00% 110.80 0.00% 0.00
12.08.00 TUBERIA PVC-P Ø 25mm m 15.00 5.37 80.55 0.00% 0.00 100.00% 80.55 0.00% 0.00
12.09.00 CABLE NYY 2X1X4 mm2 m 15.00 8.82 132.30 0.00% 0.00 100.00% 132.30 0.00% 0.00
12.10.00 PRUEBA ELECTRICA glb 1.00 103.00 103.00 0.00% 0.00 0.00% 0.00 100.00% 103.00
13.00.00 VARIOS 16,283.74
13.01.00 BOTADERO PARA BASURA u 8.00 396.50 3,172.00 0.00% 0.00 100.00% 3,172.00 0.00% 0.00
13.02.00 PLACA RECORDATORIA glb 1.00 385.20 385.20 0.00% 0.00 0.00% 0.00 100.00% 385.20
13.03.00 REJA METALICA m2 40.41 92.38 3,733.08 0.00% 0.00 100.00% 3,733.08 0.00% 0.00
13.04.00 SUJETADORES METÁLICOS PARA TUBERÍA EN PILETA u 6.00 13.72 82.32 0.00% 0.00 0.00% 0.00 100.00% 82.32
13.05.00 ESTATUA PATO DE LAGUNA u 4.00 600.00 2,400.00 0.00% 0.00 100.00% 2,400.00 0.00% 0.00
13.06.00 ESTATUA DE CISNE u 8.00 800.00 6,400.00 0.00% 0.00 100.00% 6,400.00 0.00% 0.00
13.07.00 TAPA SANITARIA 0.60m x 0.60m, e=1/8" u 1.00 111.14 111.14 0.00% 0.00 0.00% 0.00 100.00% 111.14
COSTO DIRECTO 802,028.83 132,702.41 323,301.70 346,024.72

GASTOS GENERALES(10%) 80,202.88 13,270.24 32,330.17 34,602.47

UTILIDADES(5%) 40,101.44 6,635.12 16,165.09 17,301.23

SUBTOTAL 922,333.15 152,607.77 371,796.96 397,928.42

IGV(18%) 166,019.97 27,469.40 66,923.45 71,627.12

PRESUPUESTO TOTAL DE OBRA 1,088,353.12


16.55% 40.31% 43.14%
CRONOGRAMA DE DESEMBOLSO
OBRA: "CREACION DE LA PLAZA DE ARMAS"

MES 1 MES 2 MES 3 TOTAL


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) % % % %
CREACION DE LA PLAZA DE ARMAS 802,028.83
01.00.00 OBRAS PROVISIONALES 59,604.77
01.01.00 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60m x 2.40m u 1.00 854.16 854.16 100.00% 0.00% 0.00% 100.00%
01.02.00 MOVILIZACION Y DESMOVILIZACION glb 1.00 14,785.47 14,785.47 50.00% 0.00% 50.00% 100.00%
01.03.00 ALQUILER DE CASETA PARA OFICINA , ALMACEN Y GUARDIANIA mes 3.00 250.00 750.00 33.33% 33.33% 33.33% 100.00%
01.04.00 TRANSPORTE DE MATERIAL A OBRA glb 1.00 43,215.14 43,215.14 33.33% 33.33% 33.33% 100.00%
02.00.00 OBRAS PRELIMINARES 16,993.28
02.01.00 LIMPIEZA DE TERRENO NORMAL m2 7,654.63 1.18 9,032.46 100.00% 0.00% 0.00% 100.00%
02.02.00 TRAZO Y REPLANTEO PRELIMINAR m2 7,654.63 1.04 7,960.82 100.00% 0.00% 0.00% 100.00%
03.00.00 MOVIMIENTO DE TIERRAS 117,133.66
03.01.00 EXCAVACION MASIVA EN TERRENO NORMAL m3 668.71 4.39 2,935.64 100.00% 0.00% 0.00% 100.00%
03.02.00 PERFILADO, NIVELACIÓN Y COMPACTACIÓN DE SUBRASANTE m2 5,710.10 1.41 8,051.24 100.00% 0.00% 0.00% 100.00%
03.03.00 BASE DE AFIRMADO e=0.10m PARA PISOS m2 5,498.60 12.60 69,282.36 85.00% 15.00% 0.00% 100.00%
03.04.00 SUB BASE DE HORMIGON e=0.15m PARA PISOS DE ADOQUIN DE CONCRETO m2 1,372.25 16.71 22,930.30 100.00% 0.00% 0.00% 100.00%
03.05.00 ELIMINACION DE MATERIAL EXCEDENTE m3 835.88 16.67 13,934.12 0.00% 0.00% 100.00% 100.00%
04.00.00 CONCRETO SIMPLE 117,879.10
04.01.00 CIMIENTOS CORRIDOS 9,066.95
04.01.01 CIMIENTOS CONCRETO CICLOPEO 1:10 + 30% P.M. m3 27.26 332.61 9,066.95 0.00% 100.00% 0.00% 100.00%
04.02.00 SARDINELES 64,993.88
04.02.01 CONCRETO f´c= 175 kg/cm2 EN SARDINELES INCL./TARRAJEO PULIDO Y PINTADO m3 91.27 355.09 32,409.06 0.00% 100.00% 0.00% 100.00%
04.02.02 ENCOFRADO Y DESENCOFRADO DE SARDINELES m2 912.74 35.70 32,584.82 0.00% 100.00% 0.00% 100.00%
04.03.00 FALSO PISO 27,362.87
04.03.01 FALSO PISO DE 4" DE CONCRETO 1:10 m2 856.16 31.96 27,362.87 0.00% 100.00% 0.00% 100.00%
04.04.00 CONTRAPISOS 16,455.40
04.04.01 CONTRAPISO DE 25 mm. m2 856.16 19.22 16,455.40 0.00% 100.00% 0.00% 100.00%
05.00.00 CONCRETO ARMADO 57,565.09
05.01.00 MUROS DE CONCRETO REFORZADO 3,512.83
05.01.01 CONCRETO f'c=210 kg/cm2 PARA MUROS REFORZADOS m3 3.18 383.49 1,219.50 0.00% 100.00% 0.00% 100.00%
05.01.02 ENCOFRADO Y DESENCOFRADO EN MUROS REFORZADOS m2 43.02 35.70 1,535.81 0.00% 100.00% 0.00% 100.00%
05.01.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 254.20 2.98 757.52 0.00% 100.00% 0.00% 100.00%
05.02.00 JARDINERAS DE CONCRETO REFORZADO 39,467.75
05.02.01 CONCRETO f´c=210 kg/cm2 PARA JARDINERAS DE CONCRETO REFORZADO INCL./TARRAJEO Y PINTADO m3 41.82 383.49 16,037.55 0.00% 100.00% 0.00% 100.00%
05.02.02 ENCOFRADO Y DESENCOFRADO EN JARDINERAS DE CONCRETO REFORZADO m2 466.97 39.07 18,244.52 0.00% 100.00% 0.00% 100.00%
05.02.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 1,740.16 2.98 5,185.68 0.00% 100.00% 0.00% 100.00%
05.03.00 PILETA DE CONCRETO REFORZADO 11,162.36
05.03.01 CONCRETO f´c=210 kg/cm2 CON GRANITO COLOR GRIS PARA PILETA DE CONCRETO REFORZADO m3 17.39 383.49 6,668.89 0.00% 100.00% 0.00% 100.00%
05.03.02 ENCOFRADO Y DESENCOFRADO EN PILETA DE CONCRETO REFORZADO m2 72.48 39.07 2,831.79 0.00% 100.00% 0.00% 100.00%
05.03.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 557.61 2.98 1,661.68 0.00% 100.00% 0.00% 100.00%
05.04.00 CISTERNA 3,422.15
05.04.01 CISTERNA DE CONCRETO f´c=175Kg/cm2 m3 3.28 355.09 1,164.70 0.00% 100.00% 0.00% 100.00%
05.04.02 ENCOFRADO Y DESENCOFRADO EN CISTERNA m2 31.47 39.07 1,229.53 0.00% 100.00% 0.00% 100.00%
05.04.03 ACERO CORRUGADO fy=4200 kg/cm2 GRADO 60 kg 344.94 2.98 1,027.92 0.00% 100.00% 0.00% 100.00%
06.00.00 CARPINTERIA DE MADERA 45,268.40
06.01.00 PERGOLAS SEGÚN DISEÑO glb 4.00 5,000.00 20,000.00 0.00% 20.00% 80.00% 100.00%
06.02.00 BANCAS (1.60m x 0.56m) u 60.00 421.14 25,268.40 0.00% 25.00% 75.00% 100.00%
07.00.00 PISOS Y PAVIMENTOS 306,272.24
07.01.00 PISO DE ADOQUÍN 111,742.32
07.01.01 CAMA DE ARENA DE e=5cm m2 1,372.25 10.12 13,887.17 0.00% 0.00% 100.00% 100.00%
07.01.02 CORTE Y SELLADO DE JUNTAS m2 1,372.25 13.30 18,250.93 0.00% 0.00% 100.00% 100.00%
07.01.03 PISO DE ADOQUIN COLOR GRIS DE e=8cm m2 1,372.25 58.01 79,604.22 0.00% 0.00% 100.00% 100.00%
07.02.00 PISO DE CEMENTO PULIDO 145,163.73
07.02.01 PISO DE CEMENTO PULIDO COLOR GRIS INCL./ENCOFRADO m2 3,270.19 44.39 145,163.73 0.00% 20.00% 80.00% 100.00%
07.03.00 PISO DE CERAMICO 49,366.19
07.03.01 PISO DE CERAMICO TIPO RUSTICO m2 856.16 57.66 49,366.19 0.00% 25.00% 75.00% 100.00%
08.00.00 JARDINERIA Y AREAS VERDES 7,490.95
08.01.00 SEMBRADO DE GRASS m2 1,789.86 2.75 4,922.12 0.00% 0.00% 100.00% 100.00%
08.02.00 SEMBRADO DE ARBOLES u 12.00 22.90 274.80 0.00% 0.00% 100.00% 100.00%
08.03.00 SEMBRADO DE PLANTONES u 148.00 13.92 2,060.16 0.00% 0.00% 100.00% 100.00%
08.04.00 SEMBRADO DE GINGER m2 182.71 1.28 233.87 0.00% 0.00% 100.00% 100.00%
09.00.00 REVOQUES, ENLUCIDOS Y MOLDURAS 975.61
09.01.00 TARRAJEO FINO CON CEMENTO-CAL-ARENA m2 37.06 16.39 607.41 0.00% 100.00% 0.00% 100.00%
09.02.00 TARRAJEO CON IMPERMEABILIZANTES m2 16.89 21.80 368.20 0.00% 100.00% 0.00% 100.00%
10.00.00 PINTURA 481.41
10.01.00 PINTURA LATEX 02 MANOS m2 37.06 12.99 481.41 0.00% 0.00% 100.00% 100.00%
11.00.00 INSTALACIONES SANITARIAS 1,862.32
11.01.00 RED DE AGUA TUBERIA PVC SAP Ø=3/4" m 2.71 2.61 7.07 0.00% 100.00% 0.00% 100.00%
11.02.00 RED DE AGUA TUBERIA PVC SAP Ø=3/4" CON AGUJEROS Ø=1/4" m 11.00 4.98 54.78 0.00% 100.00% 0.00% 100.00%
11.03.00 RED DE AGUA TUBERIA PVC SAP Ø=1" m 83.66 2.64 220.86 0.00% 100.00% 0.00% 100.00%
11.04.00 VALVULA DE COMPUERTA DE BRONCE DE 3/4" u 1.00 80.15 80.15 0.00% 100.00% 0.00% 100.00%
11.05.00 CAJA DE CONCRETO DE 12"x24" PARA AGUA u 1.00 71.55 71.55 0.00% 100.00% 0.00% 100.00%
11.06.00 ELECTROBOMBA SUMERGIBLE 0.5 HP u 1.00 471.50 471.50 0.00% 0.00% 100.00% 100.00%
11.07.00 SUMINISTRO E INSTALACION DE ACCESORIOS PARA CISTERNA glb 1.00 763.64 763.64 0.00% 0.00% 100.00% 100.00%
11.08.00 PRUEBA HIDRAULICA m 97.36 1.98 192.77 0.00% 0.00% 100.00% 100.00%
12.00.00 INSTALACIONES ELECTRICAS 54,218.26
12.01.00 SALIDA PARA FAROLAS ORNAMENTALES u 66.00 111.69 7,371.54 0.00% 100.00% 0.00% 100.00%
12.02.00 SALIDA DE FUERZA PARA ELECTROBOMBA SUMERGIBLE u 1.00 111.64 111.64 0.00% 0.00% 100.00% 100.00%
12.03.00 FAROLAS ORNAMENTALES u 66.00 682.95 45,074.70 0.00% 100.00% 0.00% 100.00%
12.04.00 MURO DE CONCRETO PARA TABLERO ELECTRICO u 1.00 820.61 820.61 0.00% 100.00% 0.00% 100.00%
12.05.00 TABLERO ELECTRICO DE 12 POLOS u 1.00 276.25 276.25 0.00% 100.00% 0.00% 100.00%
12.06.00 INTERRUPTOR THERMOMAGNETICO 2X125A u 1.00 136.87 136.87 0.00% 100.00% 0.00% 100.00%
12.07.00 INTERRUPTOR THERMOMAGNETICO MONOFASICA 2 X 30A pza 2.00 55.40 110.80 0.00% 100.00% 0.00% 100.00%
12.08.00 TUBERIA PVC-P Ø 25mm m 15.00 5.37 80.55 0.00% 100.00% 0.00% 100.00%
12.09.00 CABLE NYY 2X1X4 mm2 m 15.00 8.82 132.30 0.00% 100.00% 0.00% 100.00%
12.10.00 PRUEBA ELECTRICA glb 1.00 103.00 103.00 0.00% 0.00% 100.00% 100.00%
13.00.00 VARIOS 16,283.74
13.01.00 BOTADERO PARA BASURA u 8.00 396.50 3,172.00 0.00% 100.00% 0.00% 100.00%
13.02.00 PLACA RECORDATORIA glb 1.00 385.20 385.20 0.00% 0.00% 100.00% 100.00%
13.03.00 REJA METALICA m2 40.41 92.38 3,733.08 0.00% 100.00% 0.00% 100.00%
13.04.00 SUJETADORES METÁLICOS PARA TUBERÍA EN PILETA u 6.00 13.72 82.32 0.00% 0.00% 100.00% 100.00%
13.05.00 ESTATUA PATO DE LAGUNA u 4.00 600.00 2,400.00 0.00% 100.00% 0.00% 100.00%
13.06.00 ESTATUA DE CISNE u 8.00 800.00 6,400.00 0.00% 100.00% 0.00% 100.00%
13.07.00 TAPA SANITARIA 0.60m x 0.60m, e=1/8" u 1.00 111.14 111.14 0.00% 0.00% 100.00% 100.00%
COSTO DIRECTO 802,028.83 132,702.41 323,301.70 346,024.72 802,028.83
GASTOS GENERALES(10%) 80,202.88 13,270.24 32,330.17 34,602.47 80,202.88
UTILIDAD(5%) 40,101.44 6,635.12 16,165.09 17,301.23 40,101.44

SUBTOTAL 922,333.15 152,607.77 371,796.96 397,928.42 922,333.15

IGV(18%) 166,019.97 27,469.40 66,923.45 71,627.12 166,019.97

TOTAL 1,088,353.12 180,077.17 438,720.41 469,555.54 1,088,353.12

TOTAL PRESUPUESTO DE OBRA 1,088,353.12 180,077.17 438,720.41 469,555.54 1,088,353.12


% DE AVANCE DE OBRA PROGRAMADO 16.55% 40.31% 43.14% 100.00%
% DE AVANCE DE OBRA ACUMULADO 16.55% 56.86% 100.00% 100.00%