1|Page
Document No:
NSN Network Planning
2. Map Location
Sectors A B C
Antenna Orientation 0 160 260
Antenna Heights 60 60 60
Mechanical Tilts 0 0 0
Electrical Tilts 2 2 2
Scrambling Codes 417 425 433
2|Page
Document No:
NSN Network Planning
3. Functionality Test
DESCRIPTION CHECKED
No COMMENTS
YES NO
1 Check Call 3G – 3G voice
2 Check Call 3G – 2G voice bothway
3 Check Handover SHO 3G – 3G
4 Check Handover ISHO 3G – 2G
5 Check F1 Serving all sector
6 Check F2 Serving all sector
7 Check F3 Serving all sector
8 Check Throughput F1, CQI, Code Modulation
9 Check Throughput F2, CQI, Code Modulation
10 Check Throughput F3, CQI, Code Modulation
3|Page
Document No:
NSN Network Planning
DESCRIPTION CHECKED
No COMMENTS
YES NO
1 Call Setup Voice Problem
2 Drop Call all Sector
3 Call Failure
4 Handover Failure 3G – 3G
5 Handover Failure 3G – 2G bothway
6 Throughput Data connection failure
7 Low Signal Streght ( CPICH RSCP )
8 Low Signal Quality (CPICH EcNO )
9 High Interference Level
10 Overshooting
11 Pilot Pollution
12 Coverage / SHO Overhead
13 Swap Feeder
4|Page
Document No:
NSN Network Planning
EcNO ploting :
KPI
Definition
Parameter
The received energy
per chip on the
primary pilot channel
divided by the power
density in the band.
The Ec/lo is identical
to RSCP/RSSI.
CPICH Ec/No Measurement shall be
performed on the
Primary CPICH. The
reference point for the
CPICH Ec/No shall be
the antenna connector
of the UE.
SC ploting :
5|Page
Document No:
NSN Network Planning
Total
Total Physical
Physical calculated
Avg. HS-SCCH Served
Served Throughput
Log # Site SC Reported Decoding throughput
Throughput Mbps from
CQI F2 F2 % with 100%
from TEMS Tabular
scheduling
CQI
6|Page
Document No:
NSN Network Planning
KPIs:
Note :
1. No swap feeder, all sector serving properly
2. Based on antenna azimuth all sectors are working properly
3. Inter Handover Failure 3G To 3G
7|Page