Job Name: Foxtel Iron Throne Tour 2014 Client Contact (Name): Simon Hayward
High Visibility Clothing Y Safety Boots Powered Plant N Working at Height (above 2M) N
Work where Asbestos could be
Hard Hat with Brim Safety Eyewear/Goggles Energised Electricity N N
disturbed
Hearing Protection Gloves Work in confined space/s N Work near/with pressurised gas N
Work near roads or where
Harness kit Dust masks Work in or near Excavations N N
pedestrians may be affected
Wet Weather Clothing Sunscreen Y Hazardous Noise N Temporary load bearing structures N
Has the SWMS been Have workers been
developed based on a site- No consulted about the Yes
specific risk assessment? SWMS?
SWMS developed by: Staging Rentals WHS Committee SR Project Manager onsite: Jason Steffen
Person responsible for
Michael Stokes Toolbox talk carried out: Yes/No
reviewing the SWMS:
SR Project Manager ensure
Next SWMS review date: 01/07/2014 Yes/No
compliance with SWMS:
Page 1 of 5
SAFE WORK METHOD STATEMENT
11 - Staging Installation, Construction and Dismantle
Personal Qualifications and Experience: Personnel, Duties and Training Required to Complete Work:
Responsibilities:
Experience in reading stage plans Read this SWMS and comply with its Staging Rentals Staging Installation, Construction and
Experience in executing plans as per client guidelines. Dismantle Induction
and manufacturer requests Communicate with and follow Emergency & First Aid training
Experience with lifting or moving objects. reasonable instructions from your
Read and follow this SWMS. Supervisor
Page 3 of 5
SAFE WORK METHOD STATEMENT
11 - Staging Installation, Construction and Dismantle
Page 4 of 5
SAFE WORK METHOD STATEMENT
11 - Staging Installation, Construction and Dismantle