Anda di halaman 1dari 3

71-82HLPFIjanfeb13v1spots_HL template 16/01/2013 14:48 Page 71

SPOTCHECKSAFETY

Lifting: where two


is better than one
In the previous
article in this
series, Richard
Krabbendam
discussed the
lifting with two cranes of
horizontal pressure vessels or
beams. He continues with the
discussion of erecting a
pressure vessel from the
horizontal position into the
vertical by means of one main
lift crane and a tail crane.

T
he specific points that should be
considered and can be advantageous to
the lifting contractor include:
l Decreasing tail load due to offset of tail
lift point,
l Position of tail crane,
l Capacity of tail crane,
l Type of tail crane – for instance crawler
crane or truck crane,
l Type and capacity of main lift crane
(crawler or truck crane),
l Position and type of lifting points (lifting
lugs or lifting trunnions).
Figure 1 shows a pressure vessel of
150 tonnes in weight and an overall length of
Using two crawler cranes to
approximately 36.6 m. The lifting point ‘A’ at
erect a pressure vessel.
the base ring (skirt) of the vessel is positioned
three metres above the centre line of the vessel.

Case study
Let us look at the plot plan of the foundation
on which the pressure vessel must be
erected. The foundation is a concrete plinth
at ground level and we assume there is
ample room to position the main lift crane
and tail crane. In order to prepare the most
competitive bid, the rigging engineer should
study the most economic erection method.
It should be noted that there are a lot more Figure 1

www.heavyliftpfi.com January/February 2013 71


71-82HLPFIjanfeb13v1spots_HL template 16/01/2013 14:48 Page 72

SPOTCHECKSAFETY

Figure 2 Figure 3

TABLE 1 complex. For tailing work, one usually selects


Load variation 0° 15° 30° 45° 60° 70° 80° 85° 90° a crawler crane that can travel towards the
Lift crane ‘B’ 67.6 t 69.4 t 71.3 t 73.9 t 77.9 t 82.8 t 93.8 t 107.5 t 150 t main crane during the erection procedure.
Tail crane ‘A’ 82.4 t 80.6 t 78.7 t 76.1 t 72.1 t 67.2 t 56.2 t 42.5 t 0.0 t When a crawler crane is selected, the main
consideration is the required lifting capacity at
minimum boom length and a good travel
factors that determine the crane capacity and relocated on site. path for the crane. If a truck crane is selected,
type to be used, but to keep this case study The above points will help to evaluate the lifting capacity of the tailing truck crane
relatively simple, we will assume that the which crane type best suits the job. In greatly depends on the position of the tail
truck crane solution offers the most general, one could say that truck cranes are crane in relation to the main lift crane.
economic option. ideal for travelling between job sites for By selecting the most economic position
Although the initial raising of this relatively short work periods on each site. of lifting lugs and main lift crane, as well as
column will be carried out by means of a The mobilisation and demobilisation costs tail crane, one can greatly influence the
main lift crane and tail crane, at the end, for a crawler crane are in general higher than overall rigging cost for a particular pressure
when the column reaches its vertical a truck crane and therefore this crane type is vessel. For example some possible crane
position, the main lift crane must be usually used on job sites with longer work positions are shown in Figure 2:
capable of lifting the complete column of periods. Another great advantage of the l Behind the vessel’s base ring (the same
150 tonnes by itself, at the required radius, crawler crane is that it can easily travel position as tailing crawler crane).
onto the foundation. on-site from one location to another even l Both cranes at the side of the vessel are as
The main lifting lugs ‘B’ are placed when loaded. close as possible to each other.
20.1 m away from the centre of gravity The best position for the tail crane is
(CoG) and located on the centre line of the Case study selected by calculating the decrease of the tail
vessel. It is this so-called offset of the tail load when the vessel is lifted from
point (three metres) which could work to Let us get back to our case study. It is the task horizontal into vertical position. This tail
our advantage, provided we plan it right. of the rigging engineer to select the most load decrease is caused by the offset of the
In selecting the main lift crane, one has to economic cranes and positions of both tail point in relation to the centre line of the
find a type with sufficient lifting capacity and cranes. We have already decided, that the column. By means of a mathematical
at the same time sufficient boom length to main lift crane (‘B’) will be a truck crane. For formula one can calculate the decrease of tail
reach the required lifting height. The type of the 150 tonne pressure vessel, a 1,200-tonne load in relation to the angle with the
crane (crawler or truck crane) to be used is capacity telescopic crane with a guided main horizontal, when the vessel is erected from a
in most cases determined by other factors boom will be sufficient (ie the Liebherr horizontal into a vertical position. If we
such as: LTM11200 with Spanlift attachment could calculate the tail load and main lift load in
l Cost of mobilisation and demobilisation do the job). With a boom length of 47.5 m relation to the angle of the vessel’s centre
of the complete crane in relation to the and guided main boom, the crane has a rated line with the horizontal, one gets results as
work period on site. lifting capacity of 196 tonnes at 12 m radius, tabulated in Table 1.
l Other work that can be done with the which is more then sufficient to carry out the As can be seen from Table 1, the decrease
crane on that specific job site. lift. However, you still need to add the in tail load becomes significant when the
l Whether there is a need for the crane to weight of the main lift block and rigging gear vessel reaches an angle of approximately 70°
travel with load or not. to the load. with the horizontal. This tail load decrease
l The number of times the crane must be The selection of the tail crane is a bit more can be used to our advantage and in some
cases could lead to a smaller tail crane
TABLE 2
compared with the one originally selected.
Load variation 0° 15° 30° 45° 60° 70° 80° 85° 90°
When the main lift crane and tail crane are as
Lift crane ‘B’ 119.6 t 120.7 t 121.9 t 123.4 t 125.7 t 128.2 t 133.3 t 138.5 t 150 t configured in position one of Figure 2, then
Tail crane ‘A’ 30.4 t 29.3 t 28.1 t 26.6 t 24.3 t 21.8 t 16.7 t 11.5 t 0.0 t crane ‘A’ as well as crane ‘B’ needs to luff out

72 January/February 2013 www.heavyliftpfi.com


71-82HLPFIjanfeb13v1spots_HL template 16/01/2013 14:48 Page 73

SPOTCHECKSAFETY

much more – as shown in position two of the lifting blocks should remain exactly
Figure 2. Even position two is not the best above the lifting points – and do not forget
position with regards to crane capacity. to check the verticality of the lifting tackle.
The case study described is just an
Better main lifting lugs position example of how a lifting lug and tail lifting
lugs can influence the positions and sizes of
A more significant reduction in tail load (thus the cranes needed to execute the job. The
crane capacity) can be achieved by a change of same principles can be used for larger and
position of the main lifting lugs. The shape of longer columns.
this pressure vessel makes it relatively easy to In the next issue of HLPFI, we will look
install the main lifting lugs in the conical at important points when lifting a heavy
shaped transition zone approximately 4.2 m pressure vessel in the 400 to 500-tonne
A 1,400-tonne heavy pressure vessel being erected at
above the CoG. See Figure 3. Train 5 Qatar.
range, with two main lift cranes and one tail
Position one is not the ideal location for crane. HLPFI
both cranes. When both cranes are placed as the CoG, the change in tail load and main Please note, this article is intended for guidance only.
shown in position two, one gets the best lift load during the erection procedure are as Whilst every care has been taken to ensure the
results. The optimal position can be tabulated in Table 2. accuracy of the contents, no responsibility will be
established by comparing the crane capacity Instead of the required 200-tonne accepted by the publishers for any errors.
charts and decrease in tail load. capacity telescopic crane (such as a Liebherr
Richard Krabbendam has been a heavy lift specialist
Due to the position of the main lifting LTM-1200) for tailing, one can now do the during his whole working career after which he formed
lugs we greatly reduce the tail load and job with a 70-tonne telescopic crane such as Krabbendam Advies Service. A Master of Mechanical
therefore the capacity of the tail crane. The a Krupp KMK 4070, with significant cost Engineering from Delft University of Technology, he has
capacity of the main lift crane remains the reductions in mobilisation and worked with BigLift and Mammoet, and was a co-founder of
ITREC. He helped to set up Jumbo Offshore and was involved
same as the total weight of the pressure demobilisation costs, as well as rental costs.
in the development of its super heavy lift carrier fleet, the
vessel does not change. In case the offset of It should be emphasised that lifting jobs, J-Class, which uses two 900-tonne mast cranes for subsea
the tail point is increased, the decrease in tail as described, allow a very small margin of installation works. Since his retirement from Jumbo he has
load during erection will be greater as well. error and can only be carried out under been working as a freelance trainer/engineering consultant.
With main lifting lugs only 4.2 m above expert supervision and with detailed load
www.jumbo-offshore.com www.heavyliftspecialist.com
calculations and rigging studies. At all times

half page
advert

www.heavyliftpfi.com January/February 2013 73

Anda mungkin juga menyukai