VERSUS
CORAM:
HON‟BLE MR. JUSTICE SANJAY KISHAN KAUL
HON‟BLE MR. JUSTICE VALMIKI J.MEHTA
VALMIKI J. MEHTA, J.
2. The facts of the case are that the respondent No.1 floated a
Request for Proposal (RFP) for 20 Fast Patrol Vessels (FPVs) for the
proposal and a commercial proposal. The need for this RFP arose
because the ICG was formed in 1978 as an armed force of the union
for the security of maritime zones of India. The ICG is responsible for
Terrorist attack in the year 2008 revealed that India‘s long coastline
and Sea areas have become more vulnerable to terrorists and other
sanitise the vast sea area, additional vessels were sanctioned for
avail of the exchange rate variation benefit. The petitioner and four
technical bid and they were subsequently called upon to submit their
representatives.
4. Though, the petitioner‘s offer was for the lowest price (L-1)
conditions, though the price was to be firm and fixed for the entire
duration of the contract and was not subject to escalation yet the
The estimated cost of the project was more than Rs.300 crores and
W.P.(C) No. 3231/2010 Page 3 of 32
therefore, a Technical Oversight Committee (TOC) was constituted by
already stated, that the price quoted by the petitioner had a variable
the petitioner had attached a copy of the SBI rate card with the
the commercial bid. Since the commercial offers had to be firm and
fixed, and since the petitioner had claimed the FERV component, CNC
15.1.2010 withdrew its earlier offer and offered the quoted price
without FERV content. The object of this letter therefore was to make
the petitioner by CNC was valid or not. CVC in its Office Memorandum
Xxxxxxx‖
petition:
responsive?
the bid; putting it differently can the price of respondent No.4 be not
award to a successful bidder although the petitioner was not the next
lower bidder (L-2) who would be entitled to the contract if the bid of
that the respondent No.1 may scrap the tender process on the
(v) Whether the respondent No.1 was bound to apply the Discounted
Cash Flow (DCF) method in arriving at the final price of each bidder or
that this requirement of applying the DCF method was an only option
assuming the petitioner was entitled to put the FERV condition, yet,
the petitioner did not specify any one particular foreign currency but
simply attached an SBI rate card for various rates of different foreign
its convenience?
entitled to alter and amend a bid condition. The price of the FPVs to
Indian rupee varies, the respondent No.1 could have faced a situation
that in case the Indian rupee was weaker as compared to the quoted
the price, the bid document made it more than abundantly clear that
no escalation will be permitted and the prices will be firm and fixed.
The contract was to be performed over a period of six and half years
schedule laid out over this period of six and half years for construction
and supply of FPVs and the payment during such period. Being a long
taken place and therefore the respondent No.1 was careful to make
clear and insert a term in the bid documents that the price shall
therefore, when the petitioner asked not only for a fixed price in
obviously not be firm and fixed. In fact, it is not even disputed by the
learned senior counsel for the petitioner that inclusion of the term of
W.P.(C) No. 3231/2010 Page 8 of 32
seeking foreign exchange rate variation made the price quotation of
the petitioner to be not firm and fixed. Since the term and condition
above, the writ petition is liable to be thrown out by this court on this
ground alone as there does not arise any question of the petitioner
but, the same cannot give a valid legal basis to the petitioner to argue
10. Respondent No.4 while submitting its bid specified that its
of its bid. The issue is that can it be said that by making such a bid,
the respondent No.4 has violated the condition of its price not being
firm and fixed. In order to appreciate this issue, one would have to go
to the intent of such a clause which requires the price to be firm and
price being firm and fixed and not subject to escalation, in a contract
of the present type, obviously means that the price will be firm and
performance period of the contract. The intent of the price being firm
same does not have any bearing or co-relation with respect to a bid
document stating that the foreign exchange conversion rate for the
stretching it too far to contend and argue that such a bid of the
learned senior counsel for the petitioner that the price of respondent
No.4 should be held not to be firm and fixed merely because a bid
prevalent on the date of opening of the bid. This in our opinion would
accordingly the price is not firm and fixed. In any case, this is one
plausible interpretation of the term of the contract that the firm and
performance of the contract and not the date of opening of the bid. By
11. Learned senior counsel for the petitioner relied upon the
following Clause 31 in the Part III Section of the RFP to support his
argument that price had to be firm even during the bid validity
period:-
that commercial offer of the respondent No.4 ought to have been firm
and fixed for the entire period of 18 months—the bid validity period. It
was contended that the commercial offer of the respondent No.4 was
not firm and fixed for this 18 months period because foreign exchange
rate would fluctuate for the foreign exchange component during this
offered by respondent No.4 would therefore be not firm and fixed and
the aspect that the bid should be firm and fixed for the 18 months bid
validity period. We have already stated, a firm and fixed aspect of the
price i.e. price not being subject to escalation is an issue with respect
to the price being fixed during the contract performance period and
xxxxxx‖
important because the basic price will be the price which will be
demanded on the date of the opening of the bid. It is this basic price
date of opening of the price bid is the relevant date for the conversion
Therefore, the bid which has been submitted by the respondent No.4
in accordance with the intent of the contract and so made clear from
the extracted portion of Para 5(b) above. Once, a bidder can submit a
Indian rupees as on the date of opening of the bid can surely and only
violation of the same. In our opinion, it is stretching it too far for the
not been referred to any clause in the RFP that the bid to be
stand upon becomes clear from the fact that the petitioner‘s bid also
W.P.(C) No. 3231/2010 Page 14 of 32
contained foreign currency component and thus its claim for FERV.
contract and not with respect to the date of opening of the bid and
also because the contract itself clearly specifies in Para 5(b) of the
quite clear that it cannot be held that the bid of the respondent No.4
been accepted. Since the petitioner is not L-2, it has no locus standi
scrapped and therefore bids will be invited. We have not been given
and which has been accepted by respondent No.1 after due scrutiny
per the bid documents, the DCF method was to be used to arrive at the
actual and final cost which would be payable by the respondent Nos.1
are relied upon by the counsel for the petitioner to advance the present
contention:
Xxxxxx
Xxxxxx‖
“ Appendix-F
[Refers to Para 1(d) and 35 of RFP]
FORMAT FOR COMMERCIAL ORDER
XXXX
2. Following details should also be given in commercial
offers:-
(a) Payment schedule.
xxxxx‖
DCF technique.
the contract which is spread out over the period of six and half years of
the contract, it was necessary to give specific dates for payment (and
which was done by the petitioner) and on the basis of these dates
and that once the DCF formula is applied, it would have been clear that
not only the petitioner would have been the lowest bidder but more
importantly, the respondent No.4 who had not given the schedule of
because of this reason the DCF formula cannot be applied to the bid
“ IV. Notes
1. DCF method for evaluation of commercial
proposals: CSL complies and agrees to the application of
DCF technique for commercial evaluation of the offers. In
such case, Suppliers with late deliveries or late clubbed
deliveries (like two ships every six months) would get
commercial advantage by the application of DCF
technique. Therefore, we wish to point out that in order to
apply this clause, the delivery schedule as in para 4 of the
RFP is to be strictly enforced among all suppliers, to ensure
fair level commercial grounds.
2. Stage Payments: After the prebid meeting, an
amended Appendix E with a revised stage payment pattern
has been issued. As this is considered a mandatory
requirement, we comply with the same. However, we wish
to point out that, any other offer from our competitors
which is not as per these stages and percentages would
not be comparable as the same would lead to serious
commercial inequalities. We are not clear as to how the
DCF technique of evaluation would be applied in the case
of 15 stages for all the twenty vessels as the requested
stages could work out to 262 payments (2+13X20)
being made over a period of 5 years (i.e. 52 year or one
per week). To apply the DCF, the various completion dates
of these stages would also be required to be known.‖
petitioner, the counsel appearing for the respondent No.1 has relied on
the same very clauses and pointed out that since the relevant clauses
pertaining to DCF uses the expression that ―the buyer reserves the
was not mandatory to apply the DCF method. It was also contended
payment terms was there need for applying the DCF method, however,
there were no different payment terms for different bidders under the
stages of payments which were common to all the bidders and which
would finally apply for payment under the contract and thereby there
would not have been different payment terms to any of the party
specific payments stages have been set out in the contract in Annexure
the DCF method. It was also further contended that the expression ‗as
(ii) In the counter affidavit filed by the respondent No.4 it has been
averred that even after respondent No.4 was found to be L-1, further
reduced price of Rs.67.4 crores per vessel was finally agreed between
the parties. In para 10 of its counter affidavit, the respondent No.4 has
defended the stand of respondent No.1 in not applying the DCF method
―10. With regard to Points (ii) and (iii), the RFP had
stated that MoD reserves the right to use DCF
method for evaluating the price, in case,
different payment terms and advance payment
were requested by different bidders, so as to
bring all of them to a common denomination.
This due to the fact that, all yards were asked to
quote their own payment terms in the initial
RFP. However, later on, after the tender was
issued, during the pre bid meeting, the payment
terms and stages were also fixed and made
mandatory by MoD and all bidders accepted the
same in their offers. A new amended Annexure
E was issued by Mod (enclosed as Annexure-R-
3). Therefore there was no requirement to
apply DCF method and MoD did not apply the
same for evaluating the price offers to decide
L1. The RFP also did not request for the
payment stages to be shown.
This respondent would also like to bring to the notice
of this Hon‘ble Court, the following facts:-
said to be mandatory. The relevant clause clearly says that ―the buyer
reserves the right to apply DCF method‖ clearly indicating that it was
of the present case, there was no need to apply the DCF formula
therefore will turn in not applying the DCF method by the respondent
such ground. The expression ‗as applicable‘ in para 39 also shows that
DCF formula may be applied ‗if applicable‘ and which need not have
been as there are fixed fifteen stages of payment under the contract
the petitioner in its writ petition above and which relief only is that the
This court in exercise of its jurisdiction in such a case under Article 226
of the Constitution of India will not interfere unless the authorities act
contract i.e the reading is such a reading which no reasonable man can
the contracting authorities because they are in the best position to judge
There was no argument of mala fides in the facts of the present case
and nor can there be any mala fides in awarding the contract. The
therefore the petitioner in any case was not entitled to the grant of the
the other get the award of the contract is inexplicable. The petitioner
because, not the respondents, but, it is the petitioner who has acted
has drawn our attention to the fact that the bids submitted by the
been submitted with a single foreign currency for the foreign exchange
one currency in its bid but simply attached an SBI rate card giving
petitioner:
“xxxxxx
Any revision in the FE rates shall be paid at actuals, based
on the base exchange rates highlighted in the SBI rate
card, against documentary evidence, as and when
incurred. The modalities for the same would be worked out
during contract negotiations. L&T has intention to
maximize indigenous content to reduce the FE.
xxxxxx‖
The SBI rate card is contained at page 98 of the writ petition and the
EXT./CAN. RATES
clear that the petitioner has sought to play fast and loose. To its
have appreciated qua the Indian rupee during the performance of the
contract by quoting any one of the 19 currencies given in the SBI rate
although its bid was rightly rejected. We have already stated that the
ground of the idea that tender would have been scrapped if the
respective parties to file their bill of costs and we had indicated that
costs in a case like this must follow the event. In fact the Supreme
Union of India (2005) 6 SCC 344 in para 37 has said that it is high
time that actual costs must be awarded. We find the present case to
respondent No.4 and against the petitioner. Costs shall be paid within a
VALMIKI J. MEHTA, J.