Anda di halaman 1dari 5

AFTER LAYING TESTS OF 400 kV XLPE CABLE SYSTEMS FOR BEWAG BERLIN

R. Plath; U. Herrmann K. Polster J. Spiegelberg; P. Coors

Institut „Prüffeld für elektrische Bewag-Berliner HIGHVOLT Prüftechnik


Hochleistungstechnik“ Berlin Kraft-und Licht AG Dresden GmbH

Abstract. The after laying tests carried out on a testing of the 6.3 km long cable link was only possible
400 kV XLPE cable double-system (length 6.3 km) by using the world-wide most powerful mobile
used AC test voltage combined with partial resonant test system. At the maximum test voltage level
discharges (PD) measurement on joints and sealing of 400 kV RMS (√3 U0), the available test power
ends for the first time. The approx. 30 MVA test reached approx. 32 MVA at 25 Hz.
power was delivered by the two-stage mobile
resonant test system of variable frequency which 2. Frequency-tuned resonant test systems
was specifically designed for this duty. The
requirements to be met by the test system as well as 2.1 Principle of voltage generation
the test arrangement and its connection technology
are explained. For the PD measurements, For commissioning HV testing of extruded HV cables
directional couplers were integrated into each joint. AC voltage of variable frequency (25 ... 300 Hz)
The data measured on all joints were became the preferred test voltage within few years
simultaneously recorded and centrally evaluated. /2/,/3/, because of the realistic simulation of the
The voltage tests carried out up to 400 kV and the operational stress and the advantages of its generation
high-sensitive PD measurements done on the joints by frequency-tuned test systems, which are among
with a PD detection level of 2 pC confirm that such others:
test and measuring systems allow to achieve - the minimal specific weight (approx. 1kg/kVA) in
informative commissioning and diagnostic tests on comparison with resonant circuit with adjustable
extra high-voltage cables also under difficult on-site inductance (approx. 5kg/kVA) as well as test
conditions transformers with compensation (more than
10kg/kVA),
1. 400-kV cable installation - the lower feeding power (at least factor two in
comparison with resonant circuits with adjustable
To enhance the long-term secure and economical inductance),
power supply of Berlin, Bewag is building a 400 kV - the three-phase power supply, and
diagonal interconnection through Berlin's load - the simple mechanic construction especially the
centres. resonant reactor has no movable parts.
For the section between the substations of Mitte and
Friedrichshain, Bewag decided to use 400 kV XLPE The frequency-tuned resonant test system works as a
insulated cables for the first time /1/. They were series resonant circuit. The resonant point is reached by
assembled in the continuous cable tunnel running at a tuning the frequency converter to the natural frequency
depth of approx. 25 m beneath the surface. The cable of the series oscillation circuit (resonant reactor and
suppliers were to successfully pass a one-year long- capacitive load). The frequency range of 30 ... 300 Hz
time test and a type test. (1 :10) is generally accepted which means a
To assure the reliable and safe service life of the permissible load range between minimum and
cable installation as a whole, quality assurance maximum test object capacitance of 1 : 100. The load
measures were an additional part of the project. They range can be increased up to 1 : 144 if the minimal
included tests during the manufacturing process and frequency of 25 Hz is permitted. In comparison with
routine tests conducted on every essential component them the resonant systems with adjustable inductance
of the cable installation. Quality assurance was have only an operating range of 1 : 20. Furthermore an
completed by commissioning tests carried out after important characteristic is the frequency-dependent
assembling. It was checked whether there were any quality factor which can be described as the
defects produced during on-site assembling. comparison of the capacitive test power PP to the active
Therefore, the XLPE-insulated cable installation was power PL. The power loss is mainly caused by the
subjected to AC testing after assembling and at the losses of the reactor and the exciter transformer. By
same time high-sensitive partial discharge (PD) using a suitable construction of the resonant reactor a Q
measurements were done on all accessories factor greater than 100 can be achieved at least. In this
simultaneously. case the feeding power is lower than one percent of the
Due to the very high capacitive load, on-site AC test power.
C:\Webpages\HVTech\CIGRE SC 21, St. Petersburg 1999 400 kV XLPE Bewag.doc
2.2 Rating of the test systems

The technical data and the mechanic design of the


resonant reactor affect the parameters and
characteristics of the test systems. The test conditions
of the 400 kV cable installation of BEWAG have
been determined the nominal parameter of the test
systems which are as follows:
Vtest = 1.73 U0 = 400 kV
C = 0.190 µF/km 6.3 km ≈ 2.2 µF
fmin = 25 Hz
I = 80 A, 8 h ON/16 h OFF
P = 32 MVA (!)
Additionally the test system should also suitable for Fig. 1: Load-frequency and voltage characteristics
testing of cables in a rated voltage range of 110 kV to
220 kV as well as for 400 kV gas insulated tors (ONAN). According to the BEWAG test
transmission lines (GIL) at 80% of the routine test conditions which request a test duration of 8 hours it is
level Vtest = 0.8*630 kV = 504 kV. Furthermore the necessary to cool the radiators with a ventilator
weight of the transportation unit including trailer and (ONAF).
truck shall be taken into consideration because a A minimum quality factor (design quality factor) of
weight of not more than 40 tons avoids a special more than 100 at a frequency f = 25 Hz needs a feeding
permission for the road traffic. These conditions power of only 200 kVA for a test power of 20 MVA.
require to separate the resonant reactor into two units. This is equal to the rated power of the frequency
Consequently, the frequency converter and the converter. Therefore the two frequency converters
exciter transformer are separated too. As a result, work in a master-slave operation if the two resonant
there are two independent test systems which can reactors are connected in a series or parallel circuit.
operate separately or be connected in parallel (higher Additionally the two exciter transformers are circuited
test power) or in series (higher test voltage) as well. on the primary side in parallel (Fig. 2) and on the
Hence, the second resonant reactor is installed on a secondary side in series.
insulating construction which is rated for 254 kV (see
also Fig. 5). Thereby, the covered test cases are
shown in Table 1 and Fig.1.

rated test capa- cable test test


volt. voltage citance length current power
kV kV µF km A MVA
110 160 (2.5Uo) 2.5 12.5 64 10.3
132 190 2.5 12.5 75 14.3
a) 150 220 2.1 10.5 80 17.6

220 254 (2.0Uo) 1.6 8.0 80 20.3


110 160 (2.5Uo) 5.0 25 128 20.5
132 190 5.0 25 150 28.5
b) 150 220 4.2 21 160 32.2

220 254 (2.0Uo) 3.2 16 160 40.6


c) 400 400 (1.73Uo) 1.25 6.5 78.5 31.4 Fig. 2: Test circuit with 2 reactors in series
504 (0.8Up) 0.8 11.5* 80 40.3
* 70 nF/km 2.3 Acceptance test of the resonant test system

Table 1: Test system 2 x 80 A / 254 kV Before the resonant test system was used for the on-site
Maximum parameters of cable testing tests, it had been carefully tested at its rated voltage
a) single test system 254 kV (1 hour including PD measurement) at voltages
b) two test systems in parallel up to 120% of this value, at test object punctures and so
c) two test systems in series on. These tests were repeated for the series and parallel
connection of two test systems.
The oil insulated resonant reactor is especially By means of switchable load capacitors and therefore
designed for outdoor conditions with a steel tank and different resonant frequencies the semiautomatic
an oil-to-air bushing of composite insulation (fibre- operation up to the test voltage was proven. The
glass tube with silicon rubber sheds). Its nearly load voltage measuring system was calibrated for the
independent inductance of 16 H is realised by an iron operating frequency range from 25 Hz to 300 Hz. The
core with multiple gaps which enable a linear harmonic content of the test voltage meets the
magnetization. The high quality factor is caused by a requirements of the international standard IEC 60060-1
special design of this core and of the winding to and is always less than 5 percent. The measured quality
guarantee minimum losses. During the 1 hour test factor confirms the calculated frequency response (Fig.
operation the dissipation heat can usually drawed off 3) and exceeds its design value (Q = 100) remarkably.
by self-cooling from the surfaces of vessel and radia- Therefore the requested test power of approximately
32 MVA can be generated by a feeding power of blocking impedance was mounted to a capacitive
approx. 200 kVA. voltage divider on one side and to a support on the
other side. The voltage signal of the voltage divider is
used by the control and supply unit for voltage
regulation and simultaneously for voltage
measurement. The test voltage was furthermore
measured by the integrated capacitive pick-up at the
outgoing bushing of the resonant reactor. The safety for
the tested cables was improved by providing a second
independent switch-off device. To synchronise the PD
measurement system to the test voltage phase, the AC
signal was transmitted via an optical link to the control
room.
The resonant reactor was supplied by an excitation
transformer placed next to the resonant reactor on the
Fig. 3: Quality factor Q and test power P trailer.
characteristics (design value Q = 100) The 400 kV tests need two AC test systems. A 254 kV
test system identical to that of IPH was therefore
measured values
provided by KEMA. One of the two resonant reactors
was mounted to an insulating construction and both AC
3. Tests
test systems were series-connected (Fig. 2 and 5).
3.1 Test arrangement

The AC voltage test and the PD measurement on the


400-kV cable installation was awarded to IPH, the
high-voltage and high-power test laboratory situated
at Berlin-Marzahn. The tests took place at the
substation (GIS) of Friedrichsfelde.
Due to its large dimensions the AC test system had to
be placed outside the cable installation and connected
by an additional test cable of 120 m length. One of its
ends was equipped with an SF6-sealing end for
connecting the test object. On the other side of the
test cable an SF6 sealing end was fitted in an SF6
tank, to which an outdoor sealing end was mounted.
The voltage connection to the AC test system was
realised by an aluminium tube (Fig. 4). Fig. 5: Arrangement for 400-kV test

The voltage connection was arranged from the resonant


reactor on high-voltage potential to the test cable via
the blocking impedance which, in this case, was
mounted on a capacitive 500 kV voltage divider and a
500 kV support.

3.2 AC voltage tests

Since the tests anyway included the observation of the


PD level, the test voltage was increased by steps of 50
kV/5 min until the final test voltage was reached.
In the first part of the tests, the individual phases of
each system were tested one after the other at the test
voltage of 254 kV requested by Bewag over a period of
15 min and after that at 230 kV over a 45-min period.
With the cable capacitance being approx. 0.190 µF/km,
the resulting resonant frequency of the test circuit was
approx. 37 Hz.
The second part of the commissioning test was a load
Fig. 4: Outdoor sealing end with test cable test for conditioning the cable installation with elevated
operating current (1685 - 1900 A). Over a 20-day pe-
One resonant reactor was used for the test up to 254 riod a cyclic load was applied to simulate potential ser-
kV. It was mounted onto a trailer. Between resonant vice conditions that may occur in future service life.
reactor and test cable terminal a blocking impedance Furthermore, the load test served to verify the effec-
was arranged to reduce interferences for the PD tiveness of the cable installation's forced air cooling.
measurement and to protect the resonant reactor In the last part of the tests, the test voltages of 1,73·U0
against fast transients in case of breakdown. The = 400 kV during 15 minutes and of 350 kV during 45
minutes were applied one after the other to each of the joint. After dismantling the joint, the PD causing
the cable conductors. The result was a resonant failure was found. The PD location executed before the
frequency of approx. 26 Hz for the test voltage. Fig. 6 opening showed a displacement to the real failure
shows the time characteristic of the 400-kV voltage location of approx. 2 cm, confirming the high accuracy
test, delivered by the computer control of the test of UHF measurement techniques. After repair, the joint
system. reassembling was done exactly in the same place,
because practically no damage on the cable insulation
occurred due to early fault recognition.

4. Conclusions

The experience from after laying tests of 400 kV XLEP


cables with frequency-tuned resonant test systems
confirms their simple erection on site, their easy
handling as well as their high reliability. Such test
systems for test voltages up to 500 kV and test power
up to 40 MVA are available.
The test results confirm also the high overall quality
Fig. 6: Time characteristic level of the 400-kV-XLPE cable system. Nevertheless,
besides all routine tests on cables before laying and the
3.3 PD measurement use of prefabricated and pretested accessories, a small
risk remains due to assembling work on accessories on
PD measurement was carried out only on the site. On-site AC testing combined with sensitive PD
accessories, because all cables were already tested measurements reduces this risk noticeably.
during the routine test.
Each phase of both three-phase systems of the 6.3-km 5. References
cable installation included 8 joints and 2 GIS sealing
ends. On all of these accessories directional couplers /1/ Henningsen, C. H., Polster, K., Müller, K. B.,
/4/ for the decoupling of PD impulses were Schroth, R. G.:
additionally fitted. New 400 kV XLEP long distance cable systems,
Bewag required simultaneous PD measurements on their first application for the power supply of
all these accessories to detect any PD as early as Berlin,
possible. This was to minimise the risk of CIGRE Session (1998), paper 21-109
breakdown. During voltage testing no staff was
needed inside the tunnel because the distributed /2/ Schufft, W. et al.:
measurement system was under remote control by Powerful frequency-tuned resonant test systems
optical links. for after-laying tests of 110 kV XLPE cables.
Preliminary investigation showed that the noise level 9th ISH Graz 1995, paper 49.86
in the tunnel was low as compared to typical on-site
conditions. The tunnel depth of 25 m and the large /3/ Hauschild, W., Schufft, W., Spiegelberg J.:
length of cable between two joints attenuated high Alternating voltage on-site testing of XLPE
frequency noise components very well. IPH designed cables: The parameter selection of frequency-
and applied a PD measurement system fulfilling tuned resonant test systems.
Bewag requirements including a PD detection level 10th ISH Montreal (1997),Vol. 4, pp. 75-78
of ≤ 2 pC on site. Furthermore, two directional
couplers left- and right-hand side of each joint /4/ Pommerenke, D., Strehl, T., Kalkner, W.:
enabled on-site calibration and even high-precision Directional coupler sensor for partial discharge
PD location. recognition in high voltage cable systems.
Capacitive sensors instead of directional couplers 10. ISH Montreal 1997
were used for the GIS sealing ends of one of the two
three-phase cable systems. These sensors did not
reach the same selectivity like the directional
couplers. Even at the far end, outer noise (e.g. PD
from rain) superimposed the PD measurement at the
GIS sealing end. Address of author:

3.4 Test results Dr. Ing. R. Plath


Institut Prüffeld f. Hochleistungstechnik Berlin (IPH)
No breakdown occurred during all voltage tests. PD Landsberger Allee 376
measurements on 60 accessories (12 GIS sealing ends 12632 Berlin
and 48 joints) showed PD in only one single
case. Due to the low PD level (approx. 5 pC, single
pulses up to 7 pC) additional measurements were
carried out in order to be very sure before opening
C:\Webpages\HVTech\CIGRE SC 21, St. Petersburg 1999 400 kV XLPE Bewag.doc

Anda mungkin juga menyukai