Abstract. The after laying tests carried out on a testing of the 6.3 km long cable link was only possible
400 kV XLPE cable double-system (length 6.3 km) by using the world-wide most powerful mobile
used AC test voltage combined with partial resonant test system. At the maximum test voltage level
discharges (PD) measurement on joints and sealing of 400 kV RMS (√3 U0), the available test power
ends for the first time. The approx. 30 MVA test reached approx. 32 MVA at 25 Hz.
power was delivered by the two-stage mobile
resonant test system of variable frequency which 2. Frequency-tuned resonant test systems
was specifically designed for this duty. The
requirements to be met by the test system as well as 2.1 Principle of voltage generation
the test arrangement and its connection technology
are explained. For the PD measurements, For commissioning HV testing of extruded HV cables
directional couplers were integrated into each joint. AC voltage of variable frequency (25 ... 300 Hz)
The data measured on all joints were became the preferred test voltage within few years
simultaneously recorded and centrally evaluated. /2/,/3/, because of the realistic simulation of the
The voltage tests carried out up to 400 kV and the operational stress and the advantages of its generation
high-sensitive PD measurements done on the joints by frequency-tuned test systems, which are among
with a PD detection level of 2 pC confirm that such others:
test and measuring systems allow to achieve - the minimal specific weight (approx. 1kg/kVA) in
informative commissioning and diagnostic tests on comparison with resonant circuit with adjustable
extra high-voltage cables also under difficult on-site inductance (approx. 5kg/kVA) as well as test
conditions transformers with compensation (more than
10kg/kVA),
1. 400-kV cable installation - the lower feeding power (at least factor two in
comparison with resonant circuits with adjustable
To enhance the long-term secure and economical inductance),
power supply of Berlin, Bewag is building a 400 kV - the three-phase power supply, and
diagonal interconnection through Berlin's load - the simple mechanic construction especially the
centres. resonant reactor has no movable parts.
For the section between the substations of Mitte and
Friedrichshain, Bewag decided to use 400 kV XLPE The frequency-tuned resonant test system works as a
insulated cables for the first time /1/. They were series resonant circuit. The resonant point is reached by
assembled in the continuous cable tunnel running at a tuning the frequency converter to the natural frequency
depth of approx. 25 m beneath the surface. The cable of the series oscillation circuit (resonant reactor and
suppliers were to successfully pass a one-year long- capacitive load). The frequency range of 30 ... 300 Hz
time test and a type test. (1 :10) is generally accepted which means a
To assure the reliable and safe service life of the permissible load range between minimum and
cable installation as a whole, quality assurance maximum test object capacitance of 1 : 100. The load
measures were an additional part of the project. They range can be increased up to 1 : 144 if the minimal
included tests during the manufacturing process and frequency of 25 Hz is permitted. In comparison with
routine tests conducted on every essential component them the resonant systems with adjustable inductance
of the cable installation. Quality assurance was have only an operating range of 1 : 20. Furthermore an
completed by commissioning tests carried out after important characteristic is the frequency-dependent
assembling. It was checked whether there were any quality factor which can be described as the
defects produced during on-site assembling. comparison of the capacitive test power PP to the active
Therefore, the XLPE-insulated cable installation was power PL. The power loss is mainly caused by the
subjected to AC testing after assembling and at the losses of the reactor and the exciter transformer. By
same time high-sensitive partial discharge (PD) using a suitable construction of the resonant reactor a Q
measurements were done on all accessories factor greater than 100 can be achieved at least. In this
simultaneously. case the feeding power is lower than one percent of the
Due to the very high capacitive load, on-site AC test power.
C:\Webpages\HVTech\CIGRE SC 21, St. Petersburg 1999 400 kV XLPE Bewag.doc
2.2 Rating of the test systems
Table 1: Test system 2 x 80 A / 254 kV Before the resonant test system was used for the on-site
Maximum parameters of cable testing tests, it had been carefully tested at its rated voltage
a) single test system 254 kV (1 hour including PD measurement) at voltages
b) two test systems in parallel up to 120% of this value, at test object punctures and so
c) two test systems in series on. These tests were repeated for the series and parallel
connection of two test systems.
The oil insulated resonant reactor is especially By means of switchable load capacitors and therefore
designed for outdoor conditions with a steel tank and different resonant frequencies the semiautomatic
an oil-to-air bushing of composite insulation (fibre- operation up to the test voltage was proven. The
glass tube with silicon rubber sheds). Its nearly load voltage measuring system was calibrated for the
independent inductance of 16 H is realised by an iron operating frequency range from 25 Hz to 300 Hz. The
core with multiple gaps which enable a linear harmonic content of the test voltage meets the
magnetization. The high quality factor is caused by a requirements of the international standard IEC 60060-1
special design of this core and of the winding to and is always less than 5 percent. The measured quality
guarantee minimum losses. During the 1 hour test factor confirms the calculated frequency response (Fig.
operation the dissipation heat can usually drawed off 3) and exceeds its design value (Q = 100) remarkably.
by self-cooling from the surfaces of vessel and radia- Therefore the requested test power of approximately
32 MVA can be generated by a feeding power of blocking impedance was mounted to a capacitive
approx. 200 kVA. voltage divider on one side and to a support on the
other side. The voltage signal of the voltage divider is
used by the control and supply unit for voltage
regulation and simultaneously for voltage
measurement. The test voltage was furthermore
measured by the integrated capacitive pick-up at the
outgoing bushing of the resonant reactor. The safety for
the tested cables was improved by providing a second
independent switch-off device. To synchronise the PD
measurement system to the test voltage phase, the AC
signal was transmitted via an optical link to the control
room.
The resonant reactor was supplied by an excitation
transformer placed next to the resonant reactor on the
Fig. 3: Quality factor Q and test power P trailer.
characteristics (design value Q = 100) The 400 kV tests need two AC test systems. A 254 kV
test system identical to that of IPH was therefore
measured values
provided by KEMA. One of the two resonant reactors
was mounted to an insulating construction and both AC
3. Tests
test systems were series-connected (Fig. 2 and 5).
3.1 Test arrangement
4. Conclusions