Demolition & Dismantling Works (Non-Heritage Block)

Bracing of Heritage Block (Peripheral Wall)


Al Shafi Enterprises Commencement Date: December 15, 2017
Daily Construction Report
Site Info:
Site Name Silk Bank Tower
Owner JCL Reporting Date DATE: 21-12-2017

Subcontractor No. Contractor Al-Shafi Enterprises


Daily Job Report # 7 Day of Week Thursday

Weather
Weather type (Sunny/Cloudy/Rainy) Time Temperature C
Sunny 1200PM Max. 28`

Site Visitor
Name Organization Time In Time Out
Nasima Sadiol Arcop

ASE Site Staff:


Designation No. Work Hours Designation No. Work Hours
Project Manager 01

Project Engineer 01
Site Supervisor 01

Guard 02

Total 05
Demolition & Dismantling Works (Non-Heritage Block)
Bracing of Heritage Block (Peripheral Wall)
Al Shafi Enterprises Commencement Date: December 15, 2017

Daily Construction Report

Description of Works:
Current Week Targets:
Target Work Done Total Labor Details
Activity Job Today Achieved

Fencing – State Bank Side General Labors from


Fencing is in progress ASE
Folder (01)
Labor (03)
Dismantling Contractor Skilled (09)
Dismantling of GF Floor and Roof are in
progress

Support Formwork for Heritage Building Welder (02)


Pipes for Formwork cutting in progress

Demarcation of Intermediate Walls by Arcop


Ms Nasima (Arcop) visited the site and placed
names on the intermediate walls (b/w HB and
NHB)

Skilled Labor 12 Unskilled Labor 03 NOS Total Manpower 15 NOS.

Back Log Activities


Back Log:
Activity Target Work Done Total Achieved Labor Details
Quantum Today
Preparation of Variation Order
for GI sheet Fencing
-
-
-
-
-