Dedi Sandra; Dibimbing oleh Prof. Dr. Ir. H. M. Taufik Toha, DEA dan Ir.
Muhammad Amin, MS
RINGKASAN
Kata Kunci : Tambang Air Laya, Penambangan Air Laya 1, Hour Meter,
Working Hour, Excavator Backhoe
Dedi Sandra; supervised by Prof. Dr. Ir. H. M. Taufik Toha, DEA and Ir.
Muhammad Amin, MS
Evaluasi Efektifitas Penggunaan Hour Meter dan Biaya Sewa Alat Excavator
Backhoe Komatsu PC 400 dan PC 800 Terhadap Produksi Batubara Periode
February 2015 – Februari 2016 di Lokasi PAL. 1 PT. Bukit Asam (Persero), Tbk.
SUMMARY
ix Universitas Sriwijaya
total of increasing working hour for PC 400 on February 2015 – February 2016
period is 731,25 hours/13 months and PC 800 is 564,12 hours/13 months. The
increasing of working hour also generate the increasing productivity of the coal
for excavator backhoe which is 991.777,70 ton/13 months and renting cost
excavator backhoefor 13 months is Rp. 2.678.962.132 for the same period. The
realization of coal productivity is 7.295.395,69 ton/13 months so the target
production for February 2015 - February 2016 is reached.
Key Words: Tambang Air Laya, Penambangan Air Laya 1, Hour Meter, Working
Hour, Excavator Backhoe
x Universitas Sriwijaya