Anda di halaman 1dari 20

news

Metallurgy & Mineral Processing

Coarse beneficiation: exploiting


a natural phenomenon
No. 53
SRK Consulting’s
International
Newsletter

Preferential grade-by-size deportment is the tendency for metal content to increase


in the fines fraction of mill feed. That is, following blasting and primary crushing the
fine particles will be much higher in grade than the coarse particles.
This characteristic is important to identify for SRK is working with clients to assess whether
each recognised ore type as coarse particles coarse beneficiation or pebble rejection is an
consume a higher proportion of energy in opportunity to not only increase mill feed grade
crushing and grinding. Eliminating the coarse but increase throughput – using the existing
fraction would lead to higher mill throughput – grinding circuit. Coarse beneficiation can be
particularly for semi-autogenous grinding (SAG) assessed at both the drillcore stage (even on drill
mills. In fact, the coarse pebbles or scats exiting cuttings) as well as during operation.
a SAG mill are an indication of this discrepancy
In the case of gold operations, the lower grade,
in energy requirements. The question is: why are
coarse material is often more suitable for lower
the pebbles returned to the SAG mill if they’ve
cost processing methods like heap leaching.
proven themselves to be more competent?
…continued
Coarse beneficiation: (continued)
Consider the diagram below which plots had the same metal content, then no
the cumulative metal content versus upgrading line would occur. For the
the cumulative mass of material, with ore type shown in blue, 85% of the
increasing size. If each size fraction metal is contained in 60% of the mass
(up to 50mm) and 94% of the metal is
contained in 80% of the mass (up to
100mm). Therefore, screening at 100mm
ADRIAN DANCE would eliminate the coarse, competent
component of the feed but retain 94%
Adrian is a Principal of the metal. For example, if the mill
Metallurgist with feed grade was 1.0g/t gold, then the
SRK Canada who finer, easier to process material would
completed a be upgraded to 1.18g/t gold. (Screening
Bachelor of Applied at 50mm would upgrade the feed to
Science degree at 1.42g/t gold.)
UBC in Canada and a
As an alternative to investing capital into
Doctorate in Mineral
plant expansions – why not consider
Processing at the
generating more metal per day at the
Julius Kruttschnitt Mineral Research
same plant capacity? Ultimately, metal
Centre in Australia. With over 25 years
per day (i.e. revenue) and not throughput
in his field, Adrian has both industrial
or recovery is the real measure of
and consulting experience, working
processing plant performance.
at operations in Australia, Canada
and Peru. He has established himself As shown in the example, coarse
as an authority in the optimisation of beneficiation offers an opportunity to
crushing/grinding circuits and adding significantly upgrade mill feed – which
value to operations through process can be used to increase revenue or
improvements. Adrian is an advocate lower the cut-off grade. For projects
of Grade Engineering® through pre- facing long haulage distances from CIL Circuit, $2,770,000
concentration methods including coarse remote deposits, it can turn such a
beneficiation to address poor mill potentially marginal project into an
feed quality. economic one.
Adrian Dance: adance@srk.com Adrian Dance: adance@srk.com
(Vancouver)
It is routine in a processing plant
to sample the feed, tailings and
product streams in order to make a
metallurgical balance – to account
for the metal processed and where it
100 ended up. For gold plants, measuring
and estimating the amount of “gold-
in-circuit” (GIC) or gold inventory
80 is also important. It represents
Cumulative % Metal

a valuable asset and has to be


evaluated regularly to ensure that all
60 of the gold is accounted for.

Graphically represented right, the


40 GIC can change over time depending
g on how much of the metal in the
radin
u pg feed is removed as product or
no in tailings. If the GIC inventory
20
measured cannot account for all
50mm 100mm
of the metal, then it needs to be
0 investigated.
0 20 40 60 80 100
Cumulative % Mass (increasing size fraction)

2
Gold-in-Circuit inventory
measurement

Gold Inventory in dollars D AV I D PAT T I N S O N


Carbon in Elution
$240,000
David, CEng,
Electrowinning MIMMM, BSc., PhD
$180,000 has over 30 years
of experience in the
Gold Room non-ferrous mining
$80,000 industry. He worked
for an engineering
Miscellaneous design company for
$460,000 23 years and was
involved in the design of a number of
Mill Scats gold plants. Since joining SRK in 2005
$160,000 he has been involved in design and due
diligence work, including assisting in
Gravity Circuit setting up a gold inventory measurement
$140,000 system for a new gold plant in
West Africa.
Thickener
David Pattinson: dpattinson@srk.co.uk
$20,000
Example Gold-in-Circuit inventory breakdown (Cardiff)

The main components of the GIC are starting GIC plus the estimated metal in a high risk area for theft. In some cases,
shown in the figure above. the feed: how can this happen? where practical, these high risk areas
will result in some form of modification
Significant imbalances in the GIC In the figure above, a typical monthly
to equipment or security systems.
inventory suggest problems with the GIC report shows that this plant
metallurgical balance method. Perhaps had 99kg of gold in inventory – this At the end of the accounting period,
the main feed weightometer is not represents about $4 million in locked- the plant operations team will make
calibrated properly or the measurement/ up value. Of this total, most of it was a concerted effort to minimise the
sampling methodology of inventory in the leach tanks; however, 11% or inventory by converting as much of the
components is not correct or gold is $460,000 in gold was associated with GIC into doré in the gold room so that it
being lost by theft. “miscellaneous”: caught up behind mill can be reported as final product.
liners, in spillage sumps and various
Sometimes, the amount of gold David Pattinson: dpattinson@srk.co.uk
items of equipment. Careful steps are
accounted for in the GIC inventory is
taken to minimise this miscellaneous
less than what is calculated from the
gold lock-up, which is often considered

Metal Metal Metal Metal


Metal IN
Inventory OUT in OUT in Inventory
Feed
at START Product Tailings at END

3
Improving mill feed: a miner’s
perspective

Waste Crusher

Sensors
Blasted Ore
Mineralised material

Waste

-50mm
Sensors Sensor
Particle
Separators
Blasted Ore NAG
PAG

Mill

SX/EW

BOB MCCARTHY

Bob is a professional Over the decades, with decreasing Ore deposits are found in many forms;
mining engineer ore deposit grades, miners have turned they can be vein hosted hydrothermal
with over 30 years’ to economies of scale and bulk mining deposits, with short-range spatial
experience in mine to gain advantage. This has resulted in variation in grade, or porphyry deposits,
operations, mine an inherent dilution of feed to the mill. which are more disseminated and
planning, asset However, a point is being reached for smoothed in grade. Another way of
management, most ore deposits where the mill feed considering a deposit’s disposition of
technology grades for the selective mining unit grade is to refer to its heterogeneity.
development and (SMU) sizes are too low to be deemed Heterogeneity is the degree to which
implementation, and consulting. He economic. So what can we do to waste and mineralised material are
has worked at numerous mines, across improve mill feed? distinguished in a deposit. SRK has
different departments, in a variety developed methods to assess the
Mineral processers have long had to
of technical and management roles. heterogeneity of deposits which can then
consider “mineral liberation”. The smaller
Bob’s technical strengths are in project be exploited to determine how waste can
the grain size, the more likely a particle
evaluation, mine planning, mine site and be liberated.
will contain pure or near pure mineral,
project reviews (audits), and technology which can then be separated and However, knowing deposit heterogeneity
implementation. He is particularly retrieved by various methods. However, is only part of an assessment for
specialised in In-Pit Crushing and what now needs to be considered by improving mill feed. It is also important
Conveying evaluations as well as both mineral processers and miners is to have an understanding of the relative
assessments for the application of pre- “waste liberation”. At what size does a hardness of mineralised and gangue
concentration using various approaches. particle have insufficient mineralisation material, as well as the deportment of
Bob McCarthy: bmccarthy@srk.com to exceed the cut-off grade and can no mineralised material to the coarser or
(Vancouver) longer be deemed “ore”? finer size fraction in the mill feed.

4
Metallurgical challenges or
opportunities
In conducting technical due diligences, How were these domains derived and
SRK’s recent experience has found the are they metallurgically-relevant? What
majority of projects to be “metallurgically- will happen in the middle of the mine life
challenged”. This is often due to low when Domain 4 arrives at the mill? Does
grade or complex mineralogy or at it justify a change in process flowsheet
Miners can play a role in improving times, ore hardness; sometimes it is a or an expectation that problems will be
mill feed. Armed with knowledge of matter of inadequate power, water or dealt with at that time?
the deposit heterogeneity, material tailings handling.
SRK is assisting clients stuck with a
hardness, and mineral deportment, Problems arise when the selected fixed flowsheet and anticipating variable
certain processes and technology flowsheet is not appropriate for the range feed conditions: can feed quality be
can be introduced ahead of the of ore properties – a “one size does not improved (e.g. blast fragmentation)
mill to remove waste from the fit all” situation. Very often, companies or can the principles of Grade
feed or to segregate the mill feed do not appreciate or acknowledge the Engineering® be applied? That is, by
into different streams for alternate potential for variations in metallurgical blending/sorting ahead of the process
processing methods. performance, expecting the operations plant or methods of pre-concentration,
Methods being investigated and team to make the best of it. including coarse beneficiation.
developed by SRK include: How often does a company truly SRK is advocating flexible process
• SMU size definition – refine understand their ore variability – both flowsheet design including “staged
the SMU size to maximise now and in the future? Can they predict reduction in size and progressive
opportunities to segregate waste (to a reasonable level of accuracy) the upgrade” – recovery of product at every
from ore at that scale; expected changes in performance and opportunity and removal of waste at
have a plan in place to mitigate them? every stage.
• Differential blasting of ore – target This may not be the case as confidence
zones of gangue and mineralisation Remember: all ore is not created
in these predictions is low and therefore,
in an ore block to exploit differences equal and equal grade does not mean
can be ignored.
in hardness and mineral deportment, equivalent performance. One thing is for
and thereby create coarser waste Of course, the common term for certain – with an inflexible flowsheet,
particles; this is geometallurgy – but does this your metal recovery will not remain
include the potential for changes in the constant for the life of mine.
• Screening of mill feed – exploit
process flowsheet? In the figure below,
mineral deportment to create Adrian Dance: adance@srk.com
a typical 16-year mine plan shows six
different ore streams at different
metallurgical domains.
size fractions or to allow outright
rejection of waste. This can be done
on blasted ore or after crushing; Example mine plan
100
• In-pit crushing and conveying (IPCC)
– though regarded as a means to 90
reduce haul trucks, it also presents domain 6
opportunities to segregate conveyed 80
material through mineral sensing domain 5
and sorting; and 70
• Mineral sensing and sorting – exploit 60
% of Mill Feed

certain characteristics of conveyed domain 4


material to identify opportunities 50
for bulk or particle sorting. Such
sorting can operate in pre- 40
concentration (waste rejection) or
scavenger (mineral retrieval) mode 30 domain 3
Stay tuned for more details on 20
these topics.
10 domain 1 domain 2
Bob McCarthy: bmccarthy@srk.com
0
#-$# Y2
Y1 #-%# Y3
#-&# #-'#
Y4 #-(#
Y5 #-)#
Y6 #-*#
Y7 #-+#
Y8 #-,# -$!# -$$# -$%# -$&# -$'# -$(# -$)#
Y9 Y10 Y11 Y12 Y13 Y14 Y15 Y16

5
Grinding circuit improvements at
Gold Fields Granny Smith operation
T he Gold Fields Granny Smith mine lack of pre-leach thickening). One of the
in Western Australia has a long history reasons for their circuit stability is the
of collecting high quality, grinding very fine secondary crushed product
survey data from which to make circuit size they are sending to their grinding
improvements. This started when circuit. This allowed them to reduce
the semi-autogenous grinding (SAG) the SAG mill media size and operate at
mill was originally operating at the a slower speed without the rock load
Placer Dome Kidston mine, after being building and destabilising the mill. In
relocated to Granny Smith for Barrick turn, this provided spare mill capacity
Gold and continuing now under Gold which can be used to assist the ball mill.
Fields Australia ownership. One of SRK’s recommendations under Lime Lime
Air
consideration is returning a portion of
With the assistance of SRK, Granny
the cyclone underflow back to the SAG
Smith achieved incremental crushing
mill. The spare mill capacity can then be
and grinding circuit improvements based
applied to the material without the need
on frequent survey data as well as
for dilution water – and maintaining the Feed
stabilising/optimising control methods.
required leach feed % solids.
They have operated their circuit under
a wide variety of configurations, After each stage of optimisation, SRK
tonnages and feed sizes over the past conducted full surveys of the grinding
eight years and met expectations when circuit to confirm the improvements
benchmarked against theoretical specific and to benchmark current operational
energy estimates. efficiency against historical performance.
It is safe to say that the Granny
To date, they can directly attribute
Smith comminution circuit has a well-
an increase in gold recovery to these
documented history with further plans
grinding circuit changes, while having
for improvements in the future.
Take a look at the flowsheet above.
to operate within a limitation on the Can you tell if this is a step in the
cyclone overflow % solids (due to a Adrian Dance: adance@srk.com process plant or a water treatment
plant? Mining operations are building
dedicated water treatment plants
costing between 10s and 100s of
Granny Smith grinding circuit millions of dollars, when it is possible
that these are wasted expenses if the
complete process is considered.

Mineral processing plants are generally


designed to achieve the highest
recovery of valuable material,
with limited regard for the cost of
managing waste products—both solid
and water components. The highest
recovery processing route can, in fact,
lead to costly issues downstream,
which can include water treatment.
In addition, handling storage of mine
waste to eliminate environmental
impacts from acid rock drainage and
neutral pH contaminant leaching. This
is particularly true considering the
significant mine closure costs that can
remain in perpetuity.

Often the design and selection of


metallurgical and waste management
Granny Smith grinding circuit including secondary crusher, SAG mill and ball mill engineering solutions take place

6
Unlocking potential water quality
improvements in the process mill
C H R I S K E N N E DY

Do these stages belong in the process plant or water treatment plant?


C hris is a Principal
Geochemist in
SRK’s Vancouver
Flocculant office with 15 years
of experience in
Product
geochemistry and
microbiology. He
graduated with the
degree of Bachelor of
Science in Geology and Zoology (2000)
and a PhD in Geology specialising in
Microbial Geochemistry (2003) from the
University of Toronto. His experience
Recycle includes water quality predictions
(for developing, operating and closed
mines), waste management planning,
mine waste microbial geochemistry
in technical ‘silos’ and do not consider water treatment plants, include the investigations, and economic
synergistic opportunities. However, by Kitsault project in northern British evaluations of re-processing abandoned
having geochemists, water management Columbia, Canada, and the Sisson project mine tailings.
engineers and metallurgists work together, in central New Brunswick, Canada.
there exists potential for improved project Chris Kennedy: ckennedy@srk.com
At Kitsault, cadmium sorption in (Vancouver)
economics and reduced environmental
tailings slurry was demonstrated. The
risk without the need to design and build
Sisson project is using lime to clarify
dedicated water treatment plants and,
water for the process plant, but it
instead, use the processes in the mill to
also demonstrated that arsenic co-
manage water quality.
precipitation after lime addition in the
Typical mineral processing steps, such as mill could off-set the need to construct a
grinding and lime addition, provide the dedicated arsenic water treatment plant.
potential to either remove contaminant Waste Rock
While not every mining project may have
metals through surface sorption (i.e.
the potential to realise these benefits,
higher surface area from ground ore) or
the number of potential opportunities
contaminant co-precipitation from lime
is likely extensive, given how rarely
addition. These mill processes are the
environmental and metallurgical teams
same strategies used in water treatment
collaborate. For a small amount of
plants and, given the high throughput of
investment, significant gains could Mill + WTP
most processing plants, reclaim water Tailings
be realised.
volumes are also high and the ability to Management
‘treat’ significant volumes of water is Chris Kennedy: ckennedy@srk.com Facility
possible.

To ensure that discharge water meets


receiving water quality guidelines, two Process flow diagram of a Mill to also
act as a Water Treatment Plant (WTP)
recent examples of using in-plant water
treatment, as opposed to dedicated Environment

7
Lithium extraction: a question of
being in the right neighbourhood

R O B B OW E L L
Lithium-rich brine source, South America
Rob is SRK’s
Corporate Consultant
in Geochemistry & O ne of the few positive commodities salt in brines and evaporates when
Geometallurgy (PhD) in 2015 was lithium. Improvements associated with volcanically active areas.
with internationally in the performance and durability of Lithium can be extracted from its mineral
recognised expertise lithium powered batteries have made hosts by: water soluble extraction from
in the geometallurgy electric cars a reality. The search for salts; and acid leaching from resistant
of complex ores. He suitable raw materials has galvanised silicate minerals.
spent over 28 years many junior mining companies to switch
specialising in applying geochemistry Obviously, the brine-associated lithium
from uranium, gold, nickel or copper to
and mineralogy to diverse mining is easier to extract from lithium bearing
searching for lithium.
and engineering projects, including salts. However, magnesium and chloride
characterising oxide ores amenable to Lithium is the lightest metal in the are also extracted. For use in batteries,
in situ recovery (ISR), solution mining periodic table and the lightest solid. lithium carbonate requires several steps
and heap leaching, refractory gold ores, Its chemistry is similar to sodium of concentration, separating the salt
autoclave mill residues, complex base and displays an aggressive reaction components, purifying the lithium to
metal and uranium ores and Rare Earth with water. This reactive chemistry remove impurities and carbonation to
Element mineralogy. Rob has worked on and light weight reflect the fact that produce a useable high-purity lithium
ISR projects for copper, uranium, lithium lithium has only one layer (or shell) of carbonate product. When processing
recovery from brines, mine waters and ISR electrons around the atom’s core thus, calcium, sodium, potassium and
fluids and potash solution mining on nearly it has virtually no insulation (or loss of particularly magnesium must be
every continent. conductivity) as other elements. This separated for product purity.
makes it an ideal battery component.
Rob Bowell: rbowell@srk.co.uk Broadly, two styles of hard rock lithium
Lithium batteries are lighter, smaller,
(Cardiff) exist, pegmatite and volcanic-associated
provide more power than lead, copper,
rocks. Lithium occurs in pegmatites
vanadium or nickel-zinc alloys, and they
often as attractive, collectable crystals
last longer. Lithium is relatively abundant
showing a wide range of colour from
in nature. It occurs mainly in silicate
white through pink to a purple and even
minerals in hard rocks often as a trace
forming gemstones such as kunzite.
component, or it occurs as a chloride

8
Vanadium-uranium separation:
or is it just good chemistry?
In cooking, some ingredients have such and separation of uranium from
an inherently strong taste that a few vanadium and in producing high-purity
grains can be detected on even the most vanadium polyelectrolyte for use in
insensitive of palates. Chili peppers vanadium batteries. Working as part of
are a good example and whereas in a the owners’ team, SRK was involved
stew they can provide a balanced taste, in the design and interpretation of
in a sweet cake the taste is less than testwork and helped develop a suitable
desirable. So it is with some chemical flowsheet to promote vanadium
elements; for example, uranium. extraction and separate uranium that
was leached along with the vanadium.
Typically, uranium occurs along with
Working with chemical reagent
similar elements as a function of
suppliers, a novel flowsheet was
geological and geochemical processes.
developed that will allow the company
For the metallurgist this can present
to produce a suitable quality vanadium
challenges when looking to isolate
product to sell into the battery industry
and generate uranium compounds and
and a uranium by-product that can
products or isolate associated elements.
also be sold. Applying good chemical
Even a few parts per million of uranium
knowledge and experience in process
can result in a product being considered
engineering, SRK assisted the client in
“contaminated” or radioactive.
achieving their goals.
In defining a new source of battery-
Rob Bowell: rbowell@srk.co.uk
quality vanadium, American Vanadium
involved SRK to advise on the chemistry

Extraction begins with physically


separating the ore-bearing minerals
through crushing and milling.

Once separated, the lithium minerals


require destabilisation at high
temperatures with an aggressive
leaching agent, such as sulfuric
acid. The lithium sulfate produced
is segregated from the acid by ion
exchange or solvent extraction before
finally being neutralised and exposed
to air and carbon dioxide to form
lithium carbonate. As with brines,
other constituents such as magnesium
and chloride are removed to avoid
contaminating the product.

Selecting a suitable process for lithium


requires good understanding of the
geological occurrence of the element
and its neighbours. Some, like tin and
tantalum, can be valuable by-products;
others, such as magnesium, are
undesirable neighbours that need to
be separated to avoid contamination.

Rob Bowell: rbowell@srk.co.uk Vanadinite Pb-Cl-vanadate mineral, also an ore of vanadium, Atlas project, Morocco

9
Iron ore beneficiation testwork
Iron ores come in come in many In a West African context this material
shapes and sizes (and mineralogies), so is typically called Saprolite; in the
there is no one size fits all approach to Brazilian context this is Itabirite,
beneficiation. and the Brazilian industry has very
successfully developed flowsheets for
For magnetite ores, it is typically
this material using combinations of
necessary to liberate the individual
gravity separation, magnetic separation
magnetite grains from the host rocks,
and flotation. For the most part they
after which beneficiation is relatively
have exploited friable itabirite – material
straightforward due to the magnetic
that requires little if any grinding; while
properties of magnetite. However,
compact itabirites have been less
flotation may be required as a final stage
frequently exploited as they require
to remove residual silica, phosphorous
grinding at a higher process cost.
and/or sulphide minerals following
magnetic separation. For West African type deposits, SRK’s
experience is that there is no guarantee
However, for other iron ore types, full
of successfully developing a viable
liberation of the iron minerals may not
flowsheet. Ores can often respond to
be required. Direct Shipping Ores, as the
gravity and/or magnetic separation.
name suggests, require no beneficiation,
However, due to the presence of
although frequently wet screening
lower-iron content, iron minerals such
is required, (particularly for tropical
as goethite, mass yields and recoveries
deposits), to minimise adhesion of fines
to high grade concentrates can be low.
to a potential Lump product. Removal
Trade-offs are then required between
of slimes can also be desirable both
recovery and product quality (iron grade
from a product quality perspective (less
and penalty element content).
for iron upgrading than for aluminum

reduction), and to reduce the material’s As with any metallurgical flowsheet
Transportable Moisture Limit. The other development, mineralogy is key. SRK
key aspect to test is whether a potential has looked at a deposit where the
Lump product has sufficient mechanical mineralogy consists of ten micron T he AMIRA “Metal Accounting
strength to remain as Lump from mine plates of hematite cemented by quartz, Code of Practice and Guidelines”
site through to market. proving an insurmountable challenge (2007) has established best practice
for both liberation and separation, and a in process plant metal accounting.
Note that it is the material in between The code is based on the “check
disappointing outcome for the client!
these two iron ore type end members in, check out” concept; sampling
that can prove the most problematic. John Willis: jwillis@srk.co.uk the mass flow of the commodity
of interest (e.g. gold) as it crosses
a Transfer of Custody boundary,
such as the feed of a plant and
the different product points of the
plant (including tailings). Measuring
the mass flow of the commodity
requires measuring the stream flow
and collecting an assay of the stream
via a sample.

Classic sampling theory defines


seven sampling errors. These range
from errors fundamental to the
material being sampled (e.g. bulk
particle size, grain size of the mineral
of interest), to those relating to
how the material is presented to
be sampled (variations in time and
space) to those relating to how the
sample is taken (how the sample cut
Iron ore particles, Zanaga Project, Republic of Congo is defined and removed).

10
Pitfalls of sampling

Plant sampling installations


JOHN WILLIS

John is a Principal
The fundamental error is related to are entirely inappropriate for sampling Consultant BE(Met),
the weight of the sample that needs a slurry. The best method for sampling PhD, MAusIMM(CP)
to be taken. This weight increases a slurry is still to use a cutter cutting with SRK and has 30
with increasing crush size and with across a falling stream. years’ experience in
decreasing grade, but decreases with the minerals industry.
Other pitfalls include not taking time His expertise lies
increasing liberation of the mineral of
lags into account, such as taking a in the development
interest. This error becomes particularly
sample ahead of a thickener to represent and management
problematic when sampling a coarse
the feed to the subsequent process. of metallurgical testwork, flowsheet
feed in a gold plant (such as to a SAG
mill). While there are some sampling Despite the check in, check out development, comminution circuit
devices on the market, which can take philosophy of the code, it states that modelling and simulation, plant auditing,
a good representative sample of ore in cases such as gold and base metal due diligence and feasibility studies and
on a conveyor, the weight of sample plants, the recommended strategy plant design. John joined SRK in early
required to arrive at an acceptable error is to reconcile based on: tailings, 2008, and works in commodity areas,
often makes us question the merit of feedrate and production (gold) or feed, including gold, copper, molybdenum, iron
taking such a sample – a sample of a concentrate and tailings assays (base ore, phosphate and potash.
manageable size is likely to produce an metals). While this approach can be John Willis: jwillis@srk.co.uk
assay with a large degree of uncertainty somewhat clumsy in a gold plant (Cardiff)
associated with it. with a significant gravity-recovered
component, the focus should be on
With the trend of plants being built
taking samples of high quality rather
by engineering companies coming
than generating poor quality data.
from a petrochemical background, we
find numerous examples of samplers, John Willis: jwillis@srk.co.uk
especially pipe samplers, which are
Reference: AMIRA P754, 2007. Metal Accounting
probably perfectly suited to sampling
Code of Practice and Guidelines: Release 3 AMIRA
a well-mixed liquid stream, but which International, February 2007.

11
Leveraging your rock mass
characterisation

Several in-field
empirical, field-based
and laboratory methods
are used to determine
intact strength: for example,
point-load, unconfined
compressive and triaxial strength testing.
The ‘toughness’ of the intact rock is related
to the grain-size, shape, and bond-strength
between grains. These strength measures
are related to (but do not necessarily
A N T O N B LO E M M ining involves extracting a desired correlate with) work-indices used to
commodity, like gold, from a rock quantify energy expenditure using different
mass – in which the volume of waste types of milling methods.
A nton is a Senior significantly exceeds that of the mill
Consultant on Rock feed. Within the mill feed, there are On a larger scale, joints separate individual
Mechanics (BSc) some fractions that are more desirable rock blocks. The joints form a pre-existing
who has more than others (e.g. low intact strength, network of discontinuities, which affect the
than twenty years small fragment size, and/or low-clay gravity and confinement-driven strength of
of mining-industry composition). The less time, energy, the material.
experience in rock and cost it takes to mine, move, and
mass characterisation process the ore to release the desired
aimed primarily at mine minerals, the more profitable the
design. This experience is geared towards operation will be. An industry-proven
open-pit slope design and implementation. way to decide how the rock is handled,
Anton’s current interests and work include is to know and understand the physico-
primary data collection methods, rock mass mechanical properties of the rock
damage and dilation, in situ parameter mass within the mine and where the
estimation, parameter verification using ore is drawn – this is called rock mass
down-hole geophysical tools, geotechnical characterisation.
model development, and operational open-
Within the in situ rock mass there
pit slope modelling and design adjustments.
are two main components to be
Anton Bloem: abloem@srk.com considered: the intact rock, and the
(Vancouver) discontinuities that separate the
individual rock blocks. Intact rock
strength is a measure of the ‘hardness’
of the material.
Rock mass strength domains for an open-pit

12
Hydrogeochemical mining
The two extremes of the joint-network W hen water contacts a solid, a portion copper and uranium through boreholes
phenomenon can be thought of as of the solid can be dispersed or even drilled into a deposit, into which weak
the rock mass that is observed in an dissolved within the water (depending solutions of chemical reagents such
intensely altered porphyry-style deposit, on the chemistry and solid form). as sulfuric acid, ammonia or sodium
with intact weak rock-blocks of less than This reaction has challenged many carbonate are pumped to preferentially
0.1m3 compared to the widely spaced miners over the centuries and, back in extract metals
joints seen in marble dimension-stone 1558, Georgius Agricola commented
As attractive as such processes
operations, in which block sizes of 100m3 on “poisonous waters that spew
sound they do have drawbacks. The
or more are not uncommon. from mines”.
hydrogeological and geochemistry
The spacing, orientation, and properties Although this environmental risk can of the leached formation needs to
of the ‘sets’ of joints affect the direction present a serious challenge to mining be adequately understood to ensure
of blast-energy effectiveness (and the projects, in other places the passive leaching solutions can be managed and
stability of the final excavation). Within release of metals or mineral components do not migrate into the environment
that fabric, faults form macro-scale planes from an ore or mineral formation can uncontrolled. Complex hydrogeochemical
of structural weakness, which affect present an opportunity for cost-effective reactions at the leaching front cannot
the mine design and influence the mining. Managing and even enhancing be easily controlled, unlike in a process
hydraulic conductivity of the the dissolution of soluble components plant or even heap leach, and these need
rock mass. that have value can present an economic to be predicted prior to operations and
means to process ore deposits that may monitored to maximise efficiency during
Leveraging the
not be economic by conventional mining. the life of mine.
available knowledge
This could reflect stringent environmental
of the rock mass, SRK has considerable experience
controls, depth of the mineral deposit or
in the form of the in hydrogeochemical mining of salt,
perhaps low grade. Mining by injection
domain models potash, boron, uranium and copper.
can be divided into two forms:
built using robust SRK has completed hydrogeological
quantification methods, assists with One form is solution mining by which and geochemical characterisation and
planning and scheduling to minimise water-soluble minerals, usually using prediction studies as a basis for well
the energy expenditure and maximise one or more drilled wells to dissolve field design and operation. We have
the realised dollar-value of the rock and the minerals with water in a congruent undertaken infrastructure and financial
ore being processed. This is an iterative dissolution process assessment of such operations, as well
process, one which should be refined as environmental baseline and clean-up
The other form is in-situ leaching (also
at each level of study (scoping, PFS, post-mining studies.
called in-situ recovery or ISR) a mining
FS, and into production), and which
process used to recover minerals such as Rob Bowell: rbowell@srk.co.uk
ultimately leads to a bench or face-scale
characterisation of the rock properties
within the mine.

Anton Bloem: abloem@srk.com

Solution mining well, Africa

13
Incorporating geometallurgy into
strategic mine planning
The objective of strategic mine planning block to mine first. On a tonnage basis the
is to maximise the near-term cash flow of first block may be worth $100/t and the
a mining project. A mine operator needs second is $75/t. Is the first block the smart
to maximise the discounted cash flow choice? Suppose that further metallurgical
and net present value to help secure low testing indicates that the second block will
cost financing for mine construction. The grind twice as fast as the first. Now the
operator selects a mining direction and a second block will actually generate a better
pit phasing strategy. cash flow.

Conventionally, the value of each block of It is not necessary to model a unique


ore is calculated from the metal grade, processing rate for each block for this
recovery and processing costs and that methodology to have a positive impact
value drives the strategic mine planning on the mine plan. Simply identifying
process. Processing costs are estimated on broader zones of harder or softer ore, be
a per tonne basis and combined with the it alteration zones, rock types or mining
estimated mineral revenue to determine a areas, can materially improve a mine plan.
value per tonne. The areas with the highest
In addition to strategic mine planning, this
value on a per tonne basis are deemed the
same philosophy can be applied to pit
most desirable to mine first.
optimisation. Many processing costs and
However, this process does not account general and administrative costs are fixed
for the fact that not all rock types, alteration on a time basis. When we acknowledge
zones or mining areas necessarily have that the plant will process more tonnes of
the same hardness and grind at the one rock type in a day than another, we can
same rate. This mine planning strategy see that the effective processing costs will
Crushed heap leach pads of copper ore
can be improved by incorporating more differ. Applying a time based block value in
geometallurgical modelling practices. pit optimisation results in an ultimate pit
shell which accounts for the higher real
To maximise the revenue generated in a
cost of hard zones. At first glance, heap leaching
finite period of time, the comparative value can appear an extremely simple
of each ore block should be estimated on a Incorporating geometallurgy into strategic technology; however, without proper
time basis rather than a tonnage basis: the mine planning creates the opportunity characterisation, engineering and
value could be calculated as cash flow per to exploit softer ores which will produce design, heap leaching faces significant
day, instead of cash flow per tonne. better cash flow than harder ores. issues that can affect the overall
Consider that a mine planner has two Grant Carlson: gcarlson@srk.com economic viability of the project.
blocks of ore and wants to select the best Combined with compartmentalising
the project and pressures to skip
conventional steps in the normal
project development process
(advancing from the conceptual or
scoping study phase to feasibility
or final design), the overall project
viability and economics can be
inadvertently affected or constrained
during operations.

With lessons learned from the


design, construction and operation of
numerous heap leach pads worldwide,
SRK recommends the following for a
successful heap leach facility:

14
Experience based approach to
T E R RY M A N D Z I A K
successful heap leach pad design
Terry has over
26 years of
responsibility and
technical experience
for mining projects,
in both industry
and consulting. A
registered professional
engineer, Terry has
managed tailings and heap leach design
projects, with responsibilities that included
site selection, site investigation, data
interpretation, laboratory analysis, slope
stability assessment, costing analysis,
and development of specifications and
construction documents. He has also
managed multi-disciplinary engineering
teams on NI 43-101 compliant conceptual,
pre-feasibility and feasibility studies. Terry
has worked on projects throughout the
world, including North America, South
America, Turkey, China and Africa.
• Develop a site specific design that • Monitor the operational kinetics against
Terry Mandziak: tmandziak@srk.com
accounts for such conditions as those used in the design process,
(Denver)
metallurgy, topography, climate, update with metallurgical testing
geotechnics, environmental and performed during operations, and
closure conditions; • Perform a risk assessment at numerous GRANT CARLSON
• Develop a rigorous program stages of the design process.
for sampling and metallurgical In addition to these technical Grant is a
characterisation that assesses the recommendations, SRK suggests that senior consultant
variability of the ore; the design process should: specialising in mining
• Select the appropriate heap leach with SRK Canada’s
• Benchmark with other projects; Mining division. Prior
pad (HLP) type, containment, and ore
loading system; • Implement a peer review program; to joining SRK, Grant
worked at a number
• Consider adjacent facilities and • Follow a staged design process that
of mining operations
anticipate potential facility changes covers the entire HLP Life cycle;
across Canada
in the heap leach life cycle, including • Allow for construction and operational in design, planning and supervision
closure conditions; flexibility in the design; roles. His primary experience is mining
• Select the system for solution • Exceed minimum requirements and feasibility studies and due diligence
management (including irrigation, define battery limits early on; and reviews with expertise in using mining
solution collection and water balance speciific solfware including MineSight
system), that considers upsets, such • Document the process to provide 3D, Vulcan, GEMS & Whittle. Grant
as extremely wet or dry conditions; transparency and allow for regular is currently the Chair of the CIM
reviews of key decisions. Vancouver Branch.
Terry Mandziak: tmandziak@srk.com
Grant Carlson: gcarlson@srk.com
(Vancouver)

15
Successful metallurgical program for
the Montagne d’Or gold project

ERIC OLIN
On site at Montagne d’Or gold project
Eric has over 30
years’ experience in
the minerals industry.
He specialises in
D uring 2016, SRK undertook a • Holding a kick-off meeting with all
feasibility-level development program stakeholders and disciplines to ensure
consulting for plant
to describe the metallurgical process that the scope of the program and
operations, process
for Nordgold’s Montagne d’Or gold expected outcomes are fully defined.
development, and
project located in French Guiana. The • Involving experienced project
project management
objective was to develop a practical geologists and mining engineers in
and has extensive
process flowsheet and define the the selection of drill core intervals
research & development experience
process operating parameters and from which both master composites
with base metals, precious metals,
metal recoveries in sufficient detail and and variability composites could
ferrous metals and industrial minerals.
to the required level of accuracy. This be developed for the metallurgical
Eric has been involved with numerous
included developing a process design program. For the Montagne d’Or
third-party due-diligence audits, and
criteria, equipment requirements, project, three master composites were
with preparing project conceptual, pre-
process capital costs and operating selected to represent three major
feasibility and full-feasibility studies. He
costs. This program involved numerous ore zones. In addition, twenty-two
has also held both general management
stakeholders, professionals and variability composites were developed
and plant superintendent positions for
organisations that all contributed to to represent different ore lithologies,
several gold and base metal mining
a successful outcome. The following grade ranges and mining phases. Also,
operations.
points were instrumental in the comminution composites representing
Eric Olin: eolin@srk.com program’s success: each of the ore and waste lithologies
(Denver) were developed from core.

16
• Involving the metallurgical staff from The metallurgical program conducted
the selected process engineering firm for the Montagne d’Or project served as
throughout the metallurgical program. the basis for defining the process design
This is essential at a feasibility level criteria for a flowsheet that includes:
of study to ensure that the program primary crushing, SAG mill grinding, gravity
fully captures all of the processing concentration, carbon-in-leach cyanidation
parameters required to define the with O2 injection, tails thickening and
process design criteria and selected cyanide detoxification based on the SO2/
process flowsheet. Air process. An average overall gold
• Coordinating with geochemists and recovery of about 94% is projected and
geotechnical engineers to ensure includes allowance for losses due to
that process products were obtained inherent plant inefficiencies. It is worth
during the metallurgical program noting that leach enhancement with O2
for specific geochem and geotech injection resulted in reducing the required
evaluations. leach time from 48 hours (with air injection)
to less than 30 hours.

Eric Olin: eolin@srk.com

• Selecting qualified and experienced


metallurgical laboratories to
undertake the defined scope of
work according to the defined
schedule requirements. Several
different commercial metallurgical
laboratories specialising in
comminution, cyanidation,
gravity concentration, solid liquid
separation, carbon adsorption
circuit modelling and cyanide
detoxification were used for the
project.
• Employing close management and
supervision of the metallurgical
program conducted at each of
the laboratories with timely data
review and feedback to allow the
program to move forward without
delay.
Core from fresh, unaltered bedrock at Montagne d’Or

17
Poor gold reconciliation: acknowledge
the nature of the ore
Gold reconciliation audits are often Clearly, one should assess the metal
motivated by the following question: accounting systems and procedures but,
in certain instances, one should also
Did the measured gold ever exist?
acknowledge the nature of the ore.
• If yes, locate the gold if it is still within
For example, in a large South African
the circuit, or identify the likely route
gold mine, two shafts enjoyed the luxury
by which it left.
of dedicated plants. Declining tonnages
• If not, establish reasons for the resulted in the decision to process ore
erroneous estimation and propose from both shafts through the larger,
remedial measures to rectify. more modern plant. Recovered gold was
In essence, gold discrepancies can allocated between the shafts in proportion
be reduced to one of sampling/ to the respective head content, with gold
measurement deficiencies or physical grade being based on coarse run-of-mine
losses/accumulations, or a combination of samples taken by automated cross-
both. While gold theft is a real risk, this is belt samplers. Sample size, frequency
generally not our focus. and size reduction/splitting procedures
were considered to be good. Almost
immediately, however, the indicated gold
recovery of the smaller, lower-grade shaft
VIC HILLS dropped, bringing its viability in doubt.

Interrogating the systems and procedures


Vic is a Mineral could not answer the question. Importantly,
Processing Consultant it was known that the reef geology and
B Eng Chem, with over gold deportment of the two ore sources
37 years’ experience differed (see below).
in the precious
metals industry. His Video footage showed that the cross-belt
career has included sampler over-sampled finer material, which
nine years in middle would tend to bias the grade of Shaft 1
and senior plant Reef upwards.
management, seven years as consulting
The aperture of the sample cutter did not
metallurgist for South African gold,
respect the basic rule of three times the
uranium and platinum mining companies,
maximum fragment size. This resulted
A diagnostic leach test can be very
before embarking on an independent useful to qualitatively assess how gold
in rejecting low-grade coarse particles,
consulting career. In addition to base occurs within the ore and the extent
which further biased the value of Shaft 1
metals, precious metals and uranium, to which it may be refractory. Several
Reef upwards.
project exposure has included chrome, different permutations of diagnostic
iron ore, manganese, industrial minerals Ultimately, it was concluded that the gold leach tests depend on specific
and rare earth elements. had existed but as a consequence of the objectives, but they generally involve
nature of the reef as well as the sampling the sequential leaching of a gold ore
Vic Hills: vhills@srk.co.za
methodology, recovered gold had been sample with progressively stronger
(Johannesburg)
incorrectly allocated to the detriment reagents, producing a qualitative
of Shaft 2. assessment of the gold deportment
within the sample. A typical 5-Stage
Vic Hills: vhills@srk.co.za
diagnostic leach procedure includes:
Nature of ore at a South African gold mine
Stage 1: Gravity concentration to
Shaft 1 Reef Shaft 2 Reef remove the gravity recoverable
gold from the sample, followed by
Narrow mineralised channel Wide mineralised channel
cyanidation of the tailing to determine
Higher gold concentration on basal surface Even distribution of gold throughout reef the cyanide leachable gold. Typically, a
sample is ground and then subjected to
Gold commonly associated with carbon Low carbon content with no gold association
gravity concentration with a centrifugal
Higher gold concentration in the finer fractions Even gold distribution throughout size fractions gravity concentrator, followed by hand-

18
Diagnostic leaching for refractory
gold ores

Left to right: Gold from Ten Mile Mine, Nevada; Gold, Ashanti, Ghana; Gold, Empire Mine, California

panning, or on a Mozley-type table. The and liberate any gold that might be After the 5-Stage test is completed,
concentrate is fire assayed for gold. The locked within these minerals. The sulfuric a metallurgical balance is calculated
gravity tailing is subjected to cyanidation acid leach residue is then subjected to to determine the distribution of gold
and the residue is assayed for gold. Gold cyanidation and a sample of the residue is recovered during each stage of the
recovered during Stage 1 is not considered assayed for gold. test. Gold recovered during Stage 1
refractory. A portion of the cyanidation would be considered non-refractory and
Stage 4: Leach residue from Stage 3 is
leach residue is advanced to Stage 2. could be recovered by standard gravity
reacted in a hot nitric acid leach to dissolve
concentration. Gold extracted during
Stage 2: Leach residue is reacted with more resistant sulfide minerals, such
the next four stages indicates minerals
hydrochloric acid to dissolve labile sulfide as pyrite and arsenopyrite, and liberate
that the gold occurs with and suggests
minerals such as pyrrhotite and liberate any gold that might be locked in these
process options, such as pressure
any gold that may be associated with minerals. The residue is then subjected to
oxidation, biooxidation or roasting that
them. The residue is then subjected to cyanidation and a sample of the residue is
could lead to improved recovery of the
cyanidation and a sample of the residue assayed for gold.
refractory gold values. Gold remaining in
is assayed for gold. A portion of the leach
Stage 5: Leach residue from Stage 4 is the Stage 5 leach residue is most likely
residue is advanced to Stage 3.
subjected to a high temperature roast locked or encapsulated and probably not
Stage 3: Leach residue is reacted in a hot to remove any carbonaceous material recoverable unless adequate liberation can
sulfuric acid leach to dissolve acid soluble and then subjected to cyanidation and be achieved by finer grinding.
minerals not dissolved by hydrochloric the residue is assayed for gold. Any gold
Eric Olin: eolin@srk.com
acid, such as sphalerite and reactive pyrite remaining is assumed to be locked in
and other labile copper sulfide minerals, silicates or associated with fine sulfides.

19
SRK project countries SRK offices

Specialist advice for mining projects in all


global environments.

To learn more about SRK and how we can help


you with your next challenge, visit our website:

srk .com

© SRK Consulting 2016

Anda mungkin juga menyukai