PCP INTERNATIONAL LTD.

ETC OF 1X660 MW ESP AND ITS AUXILIARIES UNIT # 01 AT LALITPUR SITE


L3 - SCHEDULE OF ESP ERECTION

PASS - C

Design WT IN Compleation
S.NO. ITEM PGMA EXP.STARTING DATE Start Date Finish Date
MT Period Days

1 FOUNDATIONS CHECKING 0 4 27.04.2012 30.04.2012


STEEL STRUCTURE

2 79-881 COLUMNS & TOP BRACINGS EREC.& ALIGN. 158 15 16.05.2012 30.05.2012

3 79-801 BEARINGS EREC. & ALIGNMENT 7.25 3 28.05.2012 30.05.2012

CASING COLUMNS AND BRACINGS, STOOL 04.06.2012 18.06.2012


4 79-848 79-843 160.25 15
PEDESTAL &HOPPER BEAM EREC. & ALIGN.

CASING WALLS PANEL AND LADDERS OF 20.06.2012 16.07.2012


5 79-849 79-610 180.25 31
BOTH SIDES EREC. AND ALIGNMENT
CENTRE L R/T R BEAMS EREC., ALIGNMENT 20.07.2012 06.08.2012
6 79-828 77.5 17
OFS, CASING WALLS , COLLECTING & EMITTING SYSTEM

AND WELDING
ERECTION OF INSUL. SUPP. PANNEL AND 05.08.2012 04.09.2013
7 79-846 79-806 52.25 30
PORCELAIN INSULATORS ALIGNMENT
ALL PLATFORMS AND LADDERS WITH 05.09.2012 04.10.2012
8 79-865 89-610 82 30
HANDRAILS
COLLECTING ELECTRODE SUSPENSION 17.09.2012 30.09.2012
9 79-819 49.75 12
ERECTION & ALINGMENT
EMITTING SYSTEM i.e. (UPPER, MIDDLE
79-821 79-822 16.09.2012 15.10.2012
10 ,LOWER LEVELS) MINOR FRAMES EREC. AND 188.75 30
79-832
ALIGNMENT
11 79-820 COLLECTING ELECTRODE ERECTION 235 22 16.10.2012 06.11.2012

12 79-824 ERECTION OF SHOCKBAR ANGLE 38.75 15 21.11.2012 05.12.2012

HUCK BOLTING & COLLECTING ELECTRODE 26.11.2012 25.12.2012


13 0 30
ALINGMENT

MIDDLE & LOWER HOPPERS PRE- 25.12.2012 24.01.2013


14 79-845 147.75 30
ASSEMBLY.,EREC. AND ALIGNMENT
PENTHOUSE ISTALLATION HOPPERS, INNER ROOFS, CASING
Design WT IN Compleation
S.NO. ITEM PGMA EXP.STARTING DATE Start Date Finish Date
MT Period Days

15 79-808 79-811 GAS DISTRIBUTON SYSTEM / GAS SCREEN 39.75 20 25.12.2012 13.01.2013

INLET & OUTLET FUNNEL OF GAS 16.01.2013 15.03.2013


16 79-850 59.5 60
DISTRIBUTION SCREEN (FAB. &EREC.)

COLLECTING RAPPING SYSTEM WITH 26.02.1013 25.03.2013


17 79-825 79-826 37.25 30
HAMMERS AND DRIVES OF ALL 9 FIELDS

EMITTING RAPPING SYSTEM WITH HAMMERS 25.03.2013 24.04.2013


18 79-816 79-817 23 30
AND DRIVES OF ALL 9 FIELDS

G.D.RAPPING SYSTEM WITH HAMMERS / 18.05.2013 22.05.2013


19 79-809 79-810 5 5
DRIVEST

20 79-823 ACCESS DOORS OF CASING WALLPANELS . 3.75 3 24.05.2013 26.05.2013

21 79-844 UPPER HOPPERS EREC,ALIGN AND WELDING 115 30 05.06.2013 04.07.2013

INNER ROOF PANEL EREC. AND ROOF 17.03.2013 27.03.2013


22 79-847 56 10
HYDROTEST

OUTER ROOF EREC. ALONG WITH ITS 26.04.2013 05.05.2013


23 79-842 94 10
BOTTOM SUPPORTING FRAME
79-
59,60,61,62,63, 26.05.2013 25.07.2013
24 ERECTION OF ELETRICALS WORK 148.04 60
74,77,78,90,92,
93,94,95

25 79-855 PENT HOUSE 48.25 25 10.06.2013 05.07.2013

TRANSFORMER,RECTIFIER AND BUS DUCT


26 ERECTION,POSITIONING AND CONNECTION 45 15 04.08.2013 18.08.2013
WITH FIELD INSULATORS.

27 79-815 ERECTION OF E/E 8.5 40 13.07.2013 22.08.2013

28 79-873 MONORAIL BEAMS AND HOIST EREC. 3.25 16 01.09.2013 16.09.2013

29 AIR LEAK TEST 0 7 01.10.2013 07.10.2013

30 79-867 79-868 INSULATION & CLADING OF ALL ESP 106.75 60 15.10.2013 14.12.2013

TOTAL = 18 MONTH 2170.54


Design WT IN Compleation
S.NO. ITEM PGMA EXP.STARTING DATE Start Date Finish Date
MT Period Days

PLANNED BY APPROVED BY
PLANNING ENG. GM (P) PCPIL
DATE-28/04/2012

REMARK
REMARK
REMARK

REVIEWED BY
BHEL
PCP INTERNATIONAL LTD.
ETC OF 1X660 MW ESP AND ITS AUXILIARIES UNIT # 01 AT LALITPUR SITE
L3 - SCHEDULE OF ESP ERECTION

PGMA PASS - D
ITEM

SL. Design WT Completion


DESCRIPTIION OF WORK Start Date Finish Date
NO, IN MT Period Days

1 FOUNDATIONS CHECKING 0 4 28.05.2012 31.05.2012


STEEL STRUCTURE

2 79-881 COLUMNS & TOP BRACINGS EREC.& ALIGN. 158 15 01.06.2012 15.06.2012

3 79-801 BEARINGS EREC. & ALIGNMENT 7.25 3 12.06.2012 15.06.2012

79-848 79- CASING COLUMNS AND BRACINGS, STOOL 19.06.2012 4.07.2012


4 160.25 15
843 PEDESTAL &HOPPER BEAM EREC. & ALIGN.

79-849 79- CASING WALLS PANEL AND LADDERS OF BOTH 05.07.2012 04.08.2012
5 180.25 31
610 SIDES EREC. AND ALIGNMENT
FS, CASING WALLS , COLLECTING & EMITTING SYSTEM

CENTRE L R/T R BEAMS EREC., ALIGNMENT AND 07.08.2012 23.08.2012


6 79-828 77.5 17
WELDING

79-846 79- ERECTION OF INSUL. SUPP. PANNEL AND 20.08.2012 19.09.2012


7 52.25 30
806 PORCELAIN INSULATORS ALIGNMENT

79-865 89- ALL PLATFORMS AND LADDERS WITH 20.10.2012 19.11.2012


8 82 30
610 HANDRAILS

COLLECTING ELECTRODE SUSPENSION 01.10.2012 12.10.2012


9 79-819 49.75 12
ERECTION & ALINGMENT

79-821 79- EMITTING SYSTEM i.e. (UPPER, MIDDLE ,LOWER 01.10.2012 21.10.2012
10 188.75 30
822 79-832 LEVELS) MINOR FRAMES EREC. AND ALIGNMENT

11 79-820 COLLECTING ELECTRODE ERECTION 235 22 01.11.2012 22.11.2012

12 79-824 ERECTION OF SHOCKBAR ANGLE 38.75 15 05.12.2012 20.12.2012


CASING W

PGMA
HOPPERS, INNER ROOFS,ITEM
SL. Design WT Completion
DESCRIPTIION OF WORK Start Date Finish Date
NO, IN MT Period Days

HUCK BOLTING & COLLECTING ELECTRODE 10.12.2012 09.01.2013


13 0 30
ALINGMENT

MIDDLE & LOWER HOPPERS PRE- 05.01.2013 04.02.2013


14 79-845 147.75 30
ASSEMBLY.,EREC. AND ALIGNMENT

79-808 79- 05.01.2013 20.01.2013


15 GAS DISTRIBUTON SYSTEM / GAS SCREEN 39.75 20
811

INLET & OUTLET FUNNEL OF GAS DISTRIBUTION 01.02.2013 30.03.2013


16 79-850 59.5 60
SCREEN (FAB. &EREC.)

79-825 79- COLLECTING RAPPING SYSTEM WITH HAMMERS 12.03.2013 11.04.2013


17 37.25 30
826 AND DRIVES OF ALL 9 FIELDS
PENTHOUSE ISTALLATION

79-816 79- EMITTING RAPPING SYSTEM WITH HAMMERS 08.04.2013 07.05.2013


18 23 30
817 AND DRIVES OF ALL 9 FIELDS

79-809 79- G.D.RAPPING SYSTEM WITH HAMMERS / 01.06.2013 05.06.2013


19 5 5
810 DRIVEST

20 79-823 ACCESS DOORS OF CASING WALLPANELS . 3.75 3 07.06.2013 10.06.2013

21 79-844 UPPER HOPPERS EREC,ALIGN AND WELDING 115 30 20.06.2013 19.07.2013

INNER ROOF PANEL EREC. AND ROOF 05.04.2013 15.04.2013


22 79-847 56 10
HYDROTEST

OUTER ROOF EREC. ALONG WITH ITS BOTTOM 05.05.2013 15.05.2013


23 79-842 94 10
SUPPORTING FRAME

79-
59,60,61,62,
24 63,74,77,78, ERECTION OF ELETRICALS WORK 148.04 60 10.05.2013 09.08.2013
90,92,93,94,
95

25 79-855 PENT HOUSE 48.25 25 25.05.2013 20.07.2013

TRANSFORMER,RECTIFIER AND BUS DUCT


ING SYSTEM

26 ERECTION,POSITIONING AND CONNECTION WITH 45 15 20.08.2013 05.09.2013


FIELD INSULATORS.
PGMA
RAPPING SYSTEM
ITEM
SL. Design WT Completion
DESCRIPTIION OF WORK Start Date Finish Date
NO, IN MT Period Days

27 79-815 ERECTION OF E/E 8.5 40 25.07.2013 05.09.2013

28 79-873 MONORAIL BEAMS AND HOIST EREC. 3.25 16 15.09.2013 30.09.2013

29 AIR LEAK TEST 0 7 25.10.2013 31.10.2013

79-867 79- 01.11.2013 31.12.2013


30 INSULATION & CLADING OF ALL ESP 106.75 60
868

TOTAL = 18 MONTH 2170.54

PLANNED BY APPROVED BY
PLANNING ENG. GM (P) PCPIL
ITE

DATE: 28.04.2012

REMARK
REMARK
REMARK

REVIEWED BY
BHEL
PCP INTERNATIONAL LTD.
ETC OF 1X660 MW ESP AND ITS AUXILIARIES UNIT # 01 AT LALITPUR,SITE
L3 - SCHEDULE OF ESP ERECTION FROM PASS A TO PASS D

PASS - B

Design
Completion
S.NO. ITEM PGMA DESCRIPTION OF WORK WT IN Start Date Finish Date
Days
MT

1 FOUNDATIONS CHECKING 0 4 04.04.2012 7.04.2012


STEEL STRUCTURE

2 79-881 COLUMNS & TOP BRACINGS EREC.& ALIGN. 158 15 10.04.2012 25.04.2012

3 79-801 BEARINGS EREC. & ALIGNMENT 7.25 3 26.04.2012 29.04.2012

CASING COLUMNS AND BRACINGS, STOOL 30.04.2012 14.05.2012


4 79-848 79-843 160.25 15
PEDESTAL &HOPPER BEAM EREC. & ALIGN.

CASING WALLS PANEL AND LADDERS OF BOTH 15.07.2012 16.06.2012


5 79-849 79-610 180.25 31
SIDES EREC. AND ALIGNMENT

CENTRE L R/T R BEAMS EREC., ALIGNMENT AND 17.06.2012 05.07.2012


6 79-828 77.5 17
WELDING
ING WALLS , COLLECTING & EMITTING SYSTEM

ERECTION OF INSUL. SUPP. PANNEL AND PORCELAIN 01.06.2012 30.06.2012


7 79-846 79-806 52.25 30
INSULATORS ALIGNMENT

8 79-865 89-610 ALL PLATFORMS AND LADDERS WITH HANDRAILS 82 30 01.08.2012 30.09.2013

COLLECTING ELECTRODE SUSPENSION ERECTION & 01.08.2012 12.08.2012


9 79-819 49.75 12
ALINGMENT

79-821 79-822 79- EMITTING SYSTEM i.e. (UPPER, MIDDLE ,LOWER 01.08.2012 30.08.2012
10 188.75 30
832 LEVELS) MINOR FRAMES EREC. AND ALIGNMENT

11 79-820 COLLECTING ELECTRODE ERECTION 235 22 01.09.2012 22.09.2012

12 79-824 ERECTION OF SHOCKBAR ANGLE 38.75 15 06.10.2012 20.10.2012


HOPPERS, INNER ROOFS, CASING WALLS , COL
Design
Completion
S.NO. ITEM PGMA DESCRIPTION OF WORK WT IN Start Date Finish Date
Days
MT
HUCK BOLTING & COLLECTING ELECTRODE 11.10.2012 10.11.2012
13 0 30
ALINGMENT

MIDDLE & LOWER HOPPERS PRE-ASSEMBLY.,EREC. 11.11.2012 10.12.2012


14 79-845 147.75 30
AND ALIGNMENT

15 79-808 79-811 GAS DISTRIBUTON SYSTEM / GAS SCREEN 39.75 20 11.11.2012 30.11.2012

INLET & OUTLET FUNNEL OF GAS DISTRIBUTION 01.12.2012 30.01.2013


16 79-850 59.5 60
SCREEN (FAB. &EREC.)

COLLECTING RAPPING SYSTEM WITH HAMMERS AND 11.01.2013 10.02.2013


17 79-825 79-826 37.25 30
DRIVES OF ALL 9 FIELDS

EMITTING RAPPING SYSTEM WITH HAMMERS AND 10.02.1013 12.03.2013


18 79-816 79-817 23 30
DRIVES OF ALL 9 FIELDS
PENTHOUSE ISTALLATION

19 79-809 79-810 G.D.RAPPING SYSTEM WITH HAMMERS / DRIVEST 5 5 03.04.2013 08.04.2013

20 79-823 ACCESS DOORS OF CASING WALLPANELS . 3.75 3 09.04.2013 11.04.2013

21 79-844 UPPER HOPPERS EREC,ALIGN AND WELDING 115 30 20.04.2013 19.05.2013

22 79-847 INNER ROOF PANEL EREC. AND ROOF HYDROTEST 56 10 02.02.2013 12.02.2013

OUTER ROOF EREC. ALONG WITH ITS BOTTOM 11.03.2013 21.03.2013


23 79-842 94 10
SUPPORTING FRAME

79-
59,60,61,62,63,74, 01.04.2013 31.05.2013
24 ERECTION OF ELETRICALS WORK 148.04 60
77,78,90,92,93,94,
95

25 79-855 PENT HOUSE 48.25 25 02.03.2013 26.03.2013

TRANSFORMER,RECTIFIER AND BUS DUCT


26 ERECTION,POSITIONING AND CONNECTION WITH 45 15 26.03.2013 11.04.2013
FIELD INSULATORS.
Design
Completion
S.NO. ITEM PGMA DESCRIPTION OF WORK WT IN Start Date Finish Date
Days
MT

27 79-815 ERECTION OF E/E 8.5 40 28.05.2013 07.07.2013

28 79-873 MONORAIL BEAMS AND HOIST EREC. 3.25 16 28.05.2013 14.06.2013

29 AIR LEAK TEST 0 7 08.07.2013 15.07.2013

30 79-867 79-868 INSULATION & CLADING OF ALL ESP 106.75 60 16.07.2013 15.09.2013

TOTAL = 18 MONTH 2170.54

PLANNED BY APPROVED BY
PLANNING ENG. GM (P) PCPIL
PCP INTERNATIONAL LTD.
SP AND ITS AUXILIARIES UNIT # 01 AT LALITPUR,SITE
E OF ESP ERECTION FROM PASS A TO PASS D
DATE: 28.04.2012

PASS - B

REMARK
REMARK
REMARK

REVIEWED BY
BHEL
project
ETC OF 1X660 MW ESP AND ITS AUXILIARIES UNIT # 01 AT LALITPUR SITE
L3 - SCHEDULE OF ESP ERECTION
DATE: 28.04.2012

PASS - A

EXP.STARTING
S.NO. ITEM PGMA Activities Duration Start Date Finish Date
DATE

1 WBS 30.11.10 FOUNDATIONS CHECKING 4 27.04.2012 30.04.2012

2 79-881 04.12.10 COLUMNS & TOP BRACINGS EREC.& ALIGN. 15 01.5.2012 15.05.2012
STEEL STRUCTURE

3 79-801 25.12.10 BEARINGS EREC. & ALIGNMENT 3 12.05.2012 15.05.2012

79-848 79- CASING COLUMNS AND BRACINGS, STOOL 19.05.2012 03.06.2012


4 31.12.10 15
843 CASING PEDESTAL &HOPPER BEAM EREC. & ALIGN.
WALLS PANEL
AND
79-849 79- CASING WALLS PANEL AND LADDERS OF BOTH 04.06.2012 03.07.2012
5 LADDERS OF 31
610 SIDES EREC. AND ALIGNMENT
BOTH SIDES
EREC. AND
ALIGNMENT CENTRE L R/T R BEAMS EREC., ALIGNMENT
6 79-828 20.12.10 17 04.07.2012 20.07.2012
AND WELDING
SING WALLS , COLLECTING & EMITTING SYSTEM

79-846 79- ERECTION OF INSUL. SUPP. PANNEL AND 21.07.2012 19.08.2012


7 25.01.11 30
806 PORCELAIN INSULATORS ALIGNMENT

79-865 89- ALL PLATFORMS AND LADDERS WITH 20.08.2012 18.09.2013


8 30
610 HANDRAILS

COLLECTING ELECTRODE SUSPENSION 02.09.2012 12.09.2012


9 79-819 12
ERECTION & ALINGMENT

EMITTING SYSTEM i.e. (UPPER, MIDDLE ,LOWER


79-821 79- 01.09.2012 30.09.2012
10 LEVELS) MINOR FRAMES EREC. AND 30
822 79-832
ALIGNMENT

11 79-820 COLLECTING ELECTRODE ERECTION 22 01.10.2012 22.10.2012


HOPPERS, INNER ROOFS, CASING WALLS , COLLE
EXP.STARTING
S.NO. ITEM PGMA Activities Duration Start Date Finish Date
DATE

12 79-824 ERECTION OF SHOCKBAR ANGLE 15 06.11.2012 20.11.2012

HUCK BOLTING & COLLECTING ELECTRODE 11.11.2012 10.12.2012


13 08.02.11 30
ALINGMENT

MIDDLE & LOWER HOPPERS PRE- 11.12.2012 10.01.2013


14 79-845 10.02.11 30
ASSEMBLY.,EREC. AND ALIGNMENT

79-808 79- 11.12.2012 31.12.2012


15 15.02.11 GAS DISTRIBUTON SYSTEM / GAS SCREEN 20
811

INLET & OUTLET FUNNEL OF GAS 01.01.2013 28.02.2013


16 79-850 01.03.11 60
DISTRIBUTION SCREEN (FAB. &EREC.)

79-825 79- COLLECTING RAPPING SYSTEM WITH 11.02.2013 20.03.2013


17 15..04.11 30
826 HAMMERS AND DRIVES OF ALL 9 FIELDS

79-816 79- EMITTING RAPPING SYSTEM WITH HAMMERS 10.03.1013 09.04.2013


18 28.05.11 30
817 AND DRIVES OF ALL 9 FIELDS

79-809 79- G.D.RAPPING SYSTEM WITH HAMMERS / x 08.05.2013


19 11.06.11 5
810 DRIVEST

20 79-823 16.06.11 ACCESS DOORS OF CASING WALLPANELS . 3 09.05.2013 11.05.2013

21 79-844 24.06.11 UPPER HOPPERS EREC,ALIGN AND WELDING 30 20.05.2013 19.06.2013

INNER ROOF PANEL EREC. AND ROOF 02.03.2013 12.03.2013


22 79-847 28.06.11 10
HYDROTEST

OUTER ROOF EREC. ALONG WITH ITS 11.04.2013 21.04.2013


23 79-842 11.06.11 10
BOTTOM SUPPORTING FRAME
PENTHOUSE ISTALLATION

79-
59,60,61,62,6 11.05.2013 10.07.2013
24 16.06.11 ERECTION OF ELETRICALS WORK 60
3,74,77,78,90
,92,93,94,95

25 79-855 28.06.11 PENT HOUSE 25 26.05.2013 11.06.2013


PENTHOUSE
EXP.STARTING
S.NO. ITEM PGMA Activities Duration Start Date Finish Date
DATE
TRANSFORMER,RECTIFIER AND BUS DUCT
26 20.04.11 ERECTION,POSITIONING AND CONNECTION 15 28.07.2013 11.08.2013
WITH FIELD INSULATORS.

27 79-815 15.06.11 ERECTION OF E/E 40 28.06.2013 14.08.2013

28 79-873 22.02.11 MONORAIL BEAMS AND HOIST EREC. 16 15.08.2013 30.08.2013

29 01.03.11 AIR LEAK TEST 7 15.09.2013 22.09.2013

79-867 79- 22.09.2013 22.11.2013


30 16.03.11 INSULATION & CLADING OF ALL ESP 60
868

12/4/2010 TOTAL = 18 MONTH

PLANNED BY
PLANNING ENG.
Complete

100%

80%

60%
Complete
Complete

REVIEWED BY