KITACON SDN. BHD. & PEMBINAAN KITACON SDN. BHD. FORM NO.

HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINING CONTROL REV.


Rev. No.:________
Project / Location: Name of Job: Prepared By: Reviewed By:
R4 / BBR111, Bandar Bukit Raja 2, 16. Electrical Works
Klang, Selangor. Date: Date:

16. Electrical Works


HAZARD IDENTIFICATION RISK ASSESSMENT
Current Control Measures /
Responsibility
No Job Sequence Hazard Potential Risk Probability Severity Risk Recommendation

Mechanical (4) To control lorries speeding at site. (max.15km/h)


-Minor injury
Struck by moving part of 2 3 6 (5) Workers stay away from moving vehicle / lorry.
-Damage to property (6) To provide appropriate PPE.
vehicle. Project Manager
Delivery of Material
1 Loading and Physical (5) Crane must operate by competent operator. Site Manager
unloading material - Workers stay away from lifting area.
Struck / hit by moving part of Site Agent
-Minor injury 2 3 6 - Designated person to supervise hoisting and lifting
material during shifting activity operation.
( manual handling ) Site Engineer
(6) To provide appropriate PPE.
Site Supervisor
Physical (5) Crane must operate by competent operator. SHO / SSS
-Serious injury / Fatality
2 Heavy lifting Falling object during lifting of 2 5 10 - Machine / hoist inspection before work commences.
-Damage to property (6) To provide appropriate PPE. EO
heavy equipment.
Scaffolder
(5) Supervised by designated person during stacking of
material. Work Leader
Physical
Stacking / Storing - To ensure material not obstructing any access way. Machinery opr/
3 Workers slip to poor material -Minor injury 2 3 6
material - Material to install in proper platform.
arrangement - High of material to monitor. Driver
(6) To provide appropriate PPE. Signalman
(5) Manual handling / lifting should be carry out with Banksman
Physical (Ergonomic)
correct method. Rigger
Improper method of handling -Negligible injury 2 3 6 - Scaffolding erecting by experience workers.
Erection of working activity. (6) To provide appropriate PPE. Welder
4
platform Workers
(4) Proper working platform for workers.
Physical
-Serious injury 2 4 8 (5) Scaffolding erecting by experience workers.
Workers slip and fall. (6) To provide appropriate PPE.

Legend:
(1) Eliminate ; (2) Substitution; (3) Isolate; (4) Engineering Control; (5) Administrative Control; (6) Personal Protective Equipment (PPE)
KITACON SDN. BHD. & PEMBINAAN KITACON SDN. BHD.
HAZARD IDENTIFICATION, RISK ASSESSMENT & DETERMINING CONTROL

Electrical Works (Cont’d)


HAZARD IDENTIFICATION RISK ASSESSMENT
Current Control Measures /
Responsibility
No Job Sequence Hazard Potential Risk Probability Severity Risk Recommendation

Insert electrical (4) Proper working platform for workers / use double
Physical leaf of steel ladder.
5 wiring into conceal -Serious injury 2 4 8 Project Manager
Workers slip and fall (5) Scaffolding erecting by experience workers.
piping (ceiling) (6) To provide appropriate PPE. Site Manager
Site Agent
(4) To provide safe working platform / use a steel ladder. Site Engineer
Physical
-Serious injury 2 4 8 (5) Scaffolding erecting by experience workers. Site Supervisor
Workers slip and fall (6) To provide appropriate PPE.
SHO / SSS
EO
Hacking a recess line -Serious injury
Physical (4) To ensure working platform are properly erected. Scaffolder
to brick wall & end (long term can impair to 2 4 8
6 Dust Exposure (6) To provide appropriate PPE.
point of conceal lung)
Work Leader
piping Machinery opr/
(4) Electrical wire shall hang-up and not obstruct Driver
Mechanical walkway. Signalman
Electrical shock-due to bad -Serious injury 2 4 8 (5) To ensure power tool in good condition before used.
condition of power tools. - Power tool to be test before used. Banksman
(6) To provide appropriate PPE. Rigger
-Serious injury Welder
Patch up with cement Chemical (long term can impair Workers
7 2 4 8 (6) To provide appropriate PPE.
mortar Contact with wet cement worker skin dermatitis)
-Skin burn

Legend:
(1) Eliminate ; (2) Substitution; (3) Isolate; (4) Engineering Control; (5) Administrative Control; (6) Personal Protective Equipment (PPE)