INSPECTION AND TEST PLAN

Project name: ICA2 x 12 MW coal-fired power station project Supplier/Manufacture: Equipment/System::


Yantai Jereh Electric Power Co., Ltd. Black Start Diesel Generator
Set

Contract Name / Contract No: Address : No.7, Aucma Street, Laishan DOC No.:
District,Yantai City, Shan Dong Province

No Description of inspection/test Reference Document No. Quantum of Check Surveillance by Remarks

Manufacture Agent Manufacture Contractor Owner


AKSA JEREH AKSA Jie neng
1 Mitsubishi Engine Test According to the test report of 100% 100% R R R
Mitsubishi
2 Engga Alternator Test According to the test report of 100% 100% R R R
Engga ,
3、 Warnings/Shutdowns tested, which Tests performed :ISO8528。 100% 100% H H H
include Emergency-stop, overcrank,
locked rotor, overvoltage, low oil
pressure-LOP, high engine
temperature-HET, low coolant
level-LCL, low water temperature-LWT
4 ½ hour @ full load Tests performed :ISO8528。 100% 100% H H H

5 Phase Sequence (Rotation) Tests performed :ISO8528。 100% 100% H H H

地址(ADD):中国山东省烟台市莱山区澳柯玛大街 7 号 邮编(P.C.):264003
NO.7 AUCMA STREET, LAISHAN DISTRICT, YANTAI, CHINA
电话(TEL):0086-535-6723205
传真(FAX):0086-535-6728122
http://www.jereh.com
6 Phase Balance (Voltage) Tests performed :ISO8528。 100% 100% H H H

7 Frequency Range Adjust Tests performed :ISO8528。 100% 100% H H H

8 Voltage Modulation Tests performed :ISO8528。 100% 100% H H H

9 Regulation Stability & Transient Tests performed :ISO8528。 100% 100% H H H


Response

10 Voltage & Frequency Regulation Tests performed :ISO8528。 100% 100% H H H

11 Voltage Dip & Rise @ Rated Load Tests performed :ISO8528。 100% 100% H H H

12 Maximum Power Tests performed :ISO8528。 100% 100% H H H

compiled by: checked by: approved by:

Legend :R — Review of record


W — Witness
H — Customer Hold Point to be witnessed and work shall not proceed till it is witnessed and cleared
The manufacturer should notice the Agent, EPC and Owner at least two weeks ago to attend the test. If the Agent, EPC and Owner could not attend the test on
time, the manufacturer should arrange other time to do the test. Each arrangement time should over one week to make sure an adequate negotiation. If the Agent, EPC
and Owner could not make an agreement on test time, the manufacturer has the right to do the test alone. And the Agent, EPC and Owner should approve the
manufacturer’s test result.
The factory delivery inspection report is taken as final, if the supervision & test report has conflicts with factory delivery inspection report.