Anda di halaman 1dari 2

NO URAIAN PEKERJAAN

I PEKERJAAN PERSIAPAN
II PEKERJAAN GALIAN DAN URUGAN TANAH
III PEKERJAAN PONDASI
IV PEKERJAAN DINDING DAN PLESTERAN.
V PEK. BETON
VI PEKERJAAN PINTU DAN KUSEN
VII PEKERJAAN PASANGAN KERAMIK
VIII PEKERJAAN PENGECATAN
IX PEKERJAAN MEKANIKAL
X PEKERJAAN FINISING
JUMLAH
PEMBULATAN
JUMLAH
(Rp)
937,685.00
179,950.00
1,017,750.00
2,994,531.30
8,662,376.69
800,000.00
1,309,727.70
2,224,060.00
300,000.00
45,000.00
18,471,080.69
18,471,000.00