DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
March 2018
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Table of Contents
1 Introduction ..................................................................................................................................... 3
2 Site and Surrounds ........................................................................................................................ 3
2.1.1 Location ............................................................................................................................... 3
Title Information ....................................................................................................................... 7
Natural Values ........................................................................................................................... 7
Natural Hazards ........................................................................................................................ 7
Heritage ....................................................................................................................................... 8
Surrounding Area ..................................................................................................................... 8
Infrastructure Services ............................................................................................................ 8
2.7.1 Transport Network ........................................................................................................... 8
2.7.2 Reticulated Services ......................................................................................................... 8
Site Contamination .................................................................................................................. 8
3 Development Application ........................................................................................................... 9
Applicant ..................................................................................................................................... 9
Proposed Use and Development ....................................................................................... 9
HOURS OF CONSTRUCTION .......................................................................................................... 10
4 Planning Assessment .................................................................................................................. 10
Zoning ........................................................................................................................................ 10
Use Categorisation ................................................................................................................ 11
4.2.1 ‘Residential’ use class .................................................................................................... 11
4.2.2 Approval Status ............................................................................................................... 11
Urban Mixed Use Zone Provisions................................................................................... 11
4.3.1 Zone Purpose ................................................................................................................... 11
4.3.2 Use Standards .................................................................................................................. 12
4.3.3 Development Standards .............................................................................................. 13
Codes.......................................................................................................................................... 24
4.4.1 Bushfire Prone Areas Code E1.0 ................................................................................ 24
4.4.2 Potentially Contaminated Land E2.0 ....................................................................... 24
4.4.3 Landslide Code E3.0 ...................................................................................................... 27
Page |1
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Page |2
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
1 Introduction
This report has been prepared in support of a Development Application being lodged
by Commercial Project Delivery on behalf of York House Development for use and
development of land at 23-25 York Street, Launceston for the purposes of conversion
of an upper level floor of an existing building for apartments (residential – multiple
dwellings).
The report provides an assessment against the relevant provisions of the Launceston
Interim Planning Scheme 2015 (‘The Planning Scheme’).
The subject site comprises an area of 1492.2m2 and constitutes a single title which has
its access via a right of carriageway (6.10 metres wide) across the adjacent title
(CT37426/1). The site is located on the southern side of York Street, immediately to
the west of the Balmoral on York hotel and to the east of a car park. The site rises from
York Street to the south-west. The site is fully developed to all boundaries with an
Page |3
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
existing building that is three storeys high at the front, reducing to a single storey at
the rear on account of the topography of the site. The application is concerned with
the upper level of the existing building with the lower and middle levels to remain as
commercial office tenancies.
Page |4
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Photo 2: View along western side of building along the right of way access
Page |5
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Page |6
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Title Information
The proposed development application relates to the following titles:
Land Area
Address Owner(s) Title Reference
Natural Values
The subject site is a fully developed urban lot. It therefore does not contain any
significant natural values.
Natural Hazards
The subject site is not shown on the Planning Scheme maps as being subject to a
potential flooding and landslip hazard. It is not located within or near bushfire prone
land.
Page |7
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Heritage
The subject site is not heritage listed either at Local or at State level.
Surrounding Area
The site is situated on the fringe of the Central Business District. It is located within a
strip of York Street that is characterised by a mix of uses but where offices
predominate. It is sited immediately adjacent to the Balmoral on York Hotel, dwellings
to the rear and a car park to the west. Immediately opposite the site is the City Mill
office building. There are a number of former dwellings along the street which have
been converted to offices or medical practices.
The site is located centrally between three of the city’s major parks, those being City
Park, Princess Square and the Windmill Hill reserve. It is a 330m walk from the site to
City Park, 180 metres to the Windmill Hill reserve and 420 metres to Princess Square.
Infrastructure Services
Site Contamination
The site is listed on Council’s list of potentially contaminated sites, however the
application is accompanied by an environmental site assessment which has concluded
that there are grounds to suggest that historical contamination has not occurred and
the assessment of risk has determined no increase associated with the development.
Geotechnical risk will be removed as the first step of the development permit with the
UPS tank being grouted. A management plan is recommended as a precautionary
measure to prevent dermal contact with potential undocumented underground
material.
Page |8
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
3 Development Application
Applicant
The applicant is Commercial Project Delivery obo York House Development. The
appropriate contact is:
M: 0408397393
E: chloe@cpdelivery.com.au
Fifteen of the apartments will have a mezzanine level while three will be single level
apartments. The mezzanine apartments have their bedrooms and bathrooms located
in the mezzanine. Entry to the apartments will be via the existing entrance foyer to the
building off York Street, or via one of two sets of stairwells along the western side of
the building or via a lift within the rear basement car park. Of the 18 apartments, 10
are proposed to be 2 bedroom and 8 x 1 bedroom (2 of which are studio apartments).
Apartments 1 and 2 have north facing decks providing private open space whilst the
balance of the apartments either have their open space facing in an easterly or westerly
direction depending upon which side of the building they are located.
Page |9
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
HOURS OF CONSTRUCTION
a. Demolition work is to be carried out only between the hours of 9am and
4pm Monday to Saturday; and
b. All construction works on Unit 1 and 3 must not commence before 9am;
c. Subject to subparagraph b., construction works must only be carried out
between the hours of 7am to 6pm Monday to Friday and 8am to 5pm
Saturday;
d. no construction works are to be carried out on Sunday or Public Holidays.
d. The adjoining business known as "Balmoral on York" at 19 York Street,
will be notified 24 hours prior to the commencement of removal of
asbestos from the existing building at 23-25 York Street.
4 Planning Assessment
Zoning
The subject site is zoned Urban Mixed Use under the Launceston Interim Planning
Scheme 2015 as identified in Figure 2 below. It is situated within the CBD Car Parking
exemption area but otherwise is not subject to any overlays.
P a g e | 10
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Use Categorisation
‘use of land for self contained or shared living accommodation. Examples include
an ancillary dwelling, boarding house, communal residence, home-based
business, hostel, residential aged care home, residential college, respite centre,
retirement village and single or multiple dwellings.’
The sub-classification is ‘multiple dwellings’ which as per Clause 4.1 is defined as:
P a g e | 11
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
15.2.1.4 To create:
(a) activity at pedestrian levels, with active road frontages offering
interest and engagement to shoppers; and
(b) appropriate provision for car parking, pedestrian access and traffic
circulation.
15.2.1.1 Consistent. The proposal to convert the upper level of an existing office
building to residential apartments is an integration of a range of services within
the one site.
15.2.1.2 Consistent. The addition of new inner city apartments within close
proximity to the CBD will increase the intensity of development and residential
densities within the City. The adaptive reuse of an existing building allowing
commercial tenancies to continue on the ground floor whilst increasing
residential offerings in the City is entirely in accordance with the zone purpose
statement.
15.2.1.3 Consistent. The proposed use and development of the site for residential
purposes will assist in furthering this objective.
15.2.1.4. Consistent. The proposed works will not alter the façade and level of
activity at street level and will maintain commercial tenancies on the ground floor.
P a g e | 12
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Complies with A1
The overall height of the building height will increase by 580mm to allow ceiling
heights of 2.4m in the upper bedrooms. The maximum overall height will
therefore increase from 13.1m to 13.6m. Whilst this is greater than the A1 (a), the
height of the immediately adjacent Balmoral on York is close to 7 metres taller
than York House, meaning the minor increase in overall height is still significantly
lower than a building on the immediately adjoining property. Further, the minor
increase in height will not be apparent when viewed from the street and adjoining
heights due to the fact that the gable roof will be pulled back from York Street
and the new roof wont extend to the site boundaries.
P a g e | 13
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 14
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 15
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Objective
To ensure that the building façade promote and maintain high levels of
pedestrian interaction and amenity.
Acceptable Solution Performance Criteria
A1 New buildings with non residential P1 New buildings must be designed
uses on ground floors must: to maximise interaction between the
use of the building and pedestrians,
(a)have clear glazing, display having regard to:
windows or glass doorways for a
minimum of 80% of all ground (a)an adequate level of glazing,
floor facades to, roads, malls, openness and transparency on the
laneways or arcades; ground floor facades to roads,
(b)not have security grilles or screens malls, laneways or arcades;
that obscure the ground floor (b)the potential for security grills or
facades to roads, malls, laneways screens to reduce the amenity of
or arcades; the building or reduce levels of
(c) not have mechanical plant or interaction with the public;
equipment, such as air (c) screening or obscuring all
conditioning units or heat pumps mechanical plant or equipment
located on the facade; and such as air conditioning units or
(d)not have blank walls, signage heat pumps so they are not
panels or blocked out windows, recognisable or visible from ground
wider than 2m on ground floor level public view points; and
facades to roads, malls, laneways (d)minimising the area of all blank
or arcades. walls, signage panels or blocked
out windows on ground floor
facades to roads, malls, laneways
or arcades
A2 P2
Alterations to ground floor facades Alterations to ground floor facades of
of non residential buildings must nonresidential buildings must be
not: designed to maximise interaction
between the use of the building and
(a)reduce the level of glazing on
pedestrians, having regard to:
a facade to a road, mall,
laneway or arcade that is (a)the level of glazing, openness and
present prior to alterations;
P a g e | 16
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 17
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Complies with P1
The pedestrian access from York Street to the residential apartments and the
commercial tenancies is via the same existing access point as the ground floor
tenancies therefore the application relies on the performance criteria in respect
of A1.1. The pedestrian access fronting York street is not greater than 4m wide
(approx. 3 metres) and therefore compliance with A1.2 is achieved.
The following assessment is made against the matters to be considered under
P1:
a) The York Street pedestrian access utilises the existing building lobby and
within the lobby it will be clearly evident which stairwell leads to the residential
apartments above. Given there is currently one pedestrian access from York
Street leading to a lobby from which various tenancies are accessed, it makes
efficient design sense to retain this arrangement.
P a g e | 18
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
b) The York Street frontage access will be one of four pedestrian accesses for
the residential apartments, with additional accesses being provided via the lift
well in the basement carpark and two additional stair accesses from the
accessway on the western side of the building. It is therefore likely that
occupants of the rear apartments will utilise the two sets of stairs and/or the lift
to access their apartments whilst the occupants of the front apartments (1-4)
will utilise the York Street access. It is submitted there are a range of safe
pedestrian access options, three of which are independent of ground floor
tenancies.
c) The existing entrance from York Street is glazed and the awning above it
clearly delineates it as a door.
d) The apartments will have direct access onto York Street via the lobby.
15.4.5Daylight to windows
Objective
To allow adequate daylight into habitable room windows
Acceptable Solution Performance Criteria
A1 P1
Where the minimum distance between: Buildings must provide for adequate
(a) a new window in a habitable room levels of daylight to habitable rooms
and an existing building; or and existing windows within adjoining
buildings, having regard to:
(b) a new building constructed directly
opposite an existing habitable (a) the level of daylight available to the
room window; habitable rooms;
Is less than 3m, a light court with an (b) any existing vegetation; and
area of no less than 3m2 and (c) the topography of the site.
dimension of no less than 1m clear to
the sky must be provided.
Complies with A1
It is only apartments 1 and 3 that are immediately adjacent to an existing
building, however the creation of the private open spaces means that there is a
minimum distance of 3m between the eastern facing windows and the existing
Balmoral Motel building.
P a g e | 19
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
A1 P1
Dwellings must have an area of private Dwellings must be provided with
open space with direct access from a sufficient private open space to meet
habitable room other than a bedroom, the reasonable needs of the residents
comprising:
having regard to:
P a g e | 20
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Relies on P1
Of the 18 apartments, three of the one bedroom apartments fall slightly short of
the 8m2 (maximum variation of 0.4m2) required. Each of these apartments are
one bedroom apartments and therefore the number of potential occupants is
limited. The decks meet the minimum requirement in terms of horizontal
distance. Assessment is made against each of the Performance Criteria:
(a)(c) The POS areas for the three apartments are located immediately adjacent
to the living/dining areas and will be easily accessible. Their square configuration
will allow a small patio table to be placed upon them to ensure it is a usable
space.
P a g e | 21
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Relies on P2
Except for apartments 1, the private open space areas for each apartment will not
receive the minimum of 4 hours of direct sunlight on the 21 June to 50% of the
designated private open space area.
Assessment is therefore made against the criteria under P2 noting that the
development is the refit of an existing building and meets many of Council’s
strategic goals in terms of increasing the number of upper level residential
dwellings in the inner-city area. The site is also situated in close proximity to a
number of public park areas which residents can utilise for outdoor recreation
and living.
(a) The topography of the site does not impact the sunlight available to private
open space.
(b)(d) The site constraints are centred around adapting an existing building for
residential use whilst maintain the ground floor for commercial use. As the site is
within an inner-city area, the surrounding built form is quite dense and the height
of the adjacent Balmoral Motel contributes to the lack of available sunlight in
winter to the private open space of the eastern side apartments.
(c) The orientation of the existing building (and the site) also make it difficult to
achieve the permitted standard with respect to sunlight to private open spaces.
It is submitted that all apartments will receive glimpses of sunlight to the upper
areas of their private open space decks in mid-June and this is significantly
improved by August. A number of layouts were considered for the apartments
prior to the final design being settled upon. The proposed design is considered
to achieve the most efficient layout whilst affording each apartment with a
satisfactory level of amenity in terms of daylight and sunlight.
P a g e | 22
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
open space must receive no less than 4 (a) the impact on the amenity of
existing dwellings;
hours of sunlight on 21 June; and
(b) sunlight penetration to the private
open space of the existing dwelling;
A1.2
(c) the time of day and the duration
that sunlight is available to the
Where less than 75% of the existing
private open space of the existing
private open space receives 4 hours of
dwelling; and
sunlight on 21 June, new buildings
must not further reduce the amount (d) the effect of a reduction in sunlight
of sunlight. on the existing use of the private
open space.
15.4.8 Storage
Objective
To provide adequate storage facilities for each dwelling
Acceptable Solution Performance Criteria
A1 P1
Each dwelling must have access to 6 Each dwelling must provide adequate
cubic metres of dedicated, secure storage for the reasonable needs of
storage space not located between the residents, having regard to:
primary frontage and the façade of a (a) the size and type of dwelling
dwelling. proposed.
(b) the location, type, and size of
storage proposed;
(c) the availability, accessibility and
convenience of the storage proposed;
(d) any common or other types of
storage on the site; and
(e) the existing streetscape.
Relies on P1 for Apartments 15 and 17 only.
P a g e | 23
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
With the exception of apartments 15 and 17, all apartments have the required
6m3 storage area. Apartments 15 and 17 only have 4.2m3 storage provided within
the laundry.
Given the smaller size of these apartments which are studio apartments, it is
appropriate that the storage requirement is less than for larger apartments. The
storage for these apartments is located in a single location within the laundry
cubicle and is easily accessible and convenient for the occupants of the
apartment. The provision of storage will not impact on the streetscape.
15.4.9Common Property
Objective
To ensure common areas are easily identified.
Acceptable Solution Performance Criteria
A1 P1
Site drawings must clearly delineate No performance criteria
private and common areas including:
(a) driveways;
(b) parking spaces, including visitor
parking spaces;
(c) landscaping and gardens;
(d) mailboxes;
(e) storage for waste and recycling bins
Complies with A1
The site plan clearly shows the access driveway, parking spaces, mailboxes and
storage for waste and recycling bins. No landscaping is proposed as the building
is built to all property boundaries.
Codes
P a g e | 24
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
A copy of the Environmental Site Assessment undertaken for the site is included as
Appendix C.
Overall, the ESA accompanying the application has found that there is no evidence
that the land is contaminated and that its use and development for residential
purposes will not adversely impact on human health or the environment.
Use Standards
P a g e | 25
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Complies with A1
The ESA accompanying the application has concluded that there is no risk from
the 4 UPS tanks on the site and that there is no remaining contamination on the
site associated with these tanks. The ESA concludes that by stating that in relation
to Clause 2.5 that the ESA demonstrates that there is no evidence the land is
contaminated.
Development Standards
E2.6.2 Excavation
Objective
To ensure that works involving excavation of potentially contaminated land does
not adversely impact on human health or the environment.
Acceptable Solution Performance Criteria
A1 P1
No acceptable solution Excavation does not adversely impact
on health and the environment, having
regard to:
P a g e | 26
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Complies with P1
The ESA accompanying the application has concluded that there is no risk from
the 4 UPS tanks on the site and that there is no remaining contamination on the
site associated with these tanks. The ESA concludes that by stating that in relation
to Clause 2.5 that the ESA demonstrates that there is no evidence the land is
contaminated.
Code Purpose
E4.1 a) protect the safety and efficiency of the road and railway networks;
and
b) reduce conflicts between sensitive uses and major roads and the
rail networks.
Use Standards
P a g e | 27
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 28
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 29
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Code Purpose
P a g e | 30
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Use Standards
E6.5.1 Car Parking Numbers
Objective
To ensure that an appropriate level of car parking is provided to meet the needs
of the use.
Acceptable Solution Performance Criteria
A1 The number of car parking P1.1 The number of car parking
spaces must; spaces for other than residential
a) not be less than 90% of the uses, must be provided to meet
requirements of Table E6.1; the reasonable needs of the use,
(except for dwellings in the having regard to:
General Residential Zone) or
b) not be less than 100% of the
a) the availability of off-road
requirements of Table E6.1 public car parking spaces within
for dwellings in the General reasonable walking distance;
Residential Zone; or b) the ability of multiple users to
c) not exceed the requirements
share spaces because of:
of Table E6.1 by more than 2 (i) variations in car parking
spaces or 5% whichever is demand over time; or
the greater, except for (ii) efficiencies gained by
dwellings in the General consolidation of car parking
Residential Zone; or spaces;
d) be in accordance with an
c) the availability and frequency
acceptable solution of public transport within
contained within a parking reasonable walking distance of
precinct plan. the site;
d) any site constraints such as
existing buildings, slope,
drainage, vegetation and
landscaping;
e) the availability, accessibility
and safety of on-road parking,
having regard to the nature of
P a g e | 31
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P1.2
P1.3
A2
The number of accessible car parking P2
spaces for use by persons with a
No performance criteria
disability for uses that require 6 or
more parking spaces must be in
accordance with Part D3 of the
National Construction Code 2014, as
amended from time to time.
P a g e | 32
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
A1 and A2 Not applicable – the site is located in the CBD car park exempt
area.
Objective
To ensure that an appropriate level of bicycle parking spaces are provided to
meet the needs of the use.
Complies with A1
Table E6.1 of the Planning Scheme, does not set a requirement for the provision
of bicycle parking for the Residential Use Class. Nonetheless given the
apartments are inner-city, provision has been made in the basement for an area
for bicycle parking.
Objective
To ensure that taxis can adequately access developments.
P a g e | 33
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Objective
To ensure that motorbikes are adequately provided for in parking considerations.
P a g e | 34
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Objective
To ensure adequate access for goods delivery and collection, and to prevent loss
of amenity and adverse impacts on traffic flows.
Not applicable
Development Standards
P a g e | 35
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Complies with A1
All parking, accessways, manoeuvring and circulation spaces meet the
requirements of A1.
P a g e | 36
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
A1.2
A1.3
A1.4
P a g e | 37
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Objective
To ensure pedestrian access is provided in a safe and convenient manner
P a g e | 38
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
A1.2
In parking areas containing
accessible car parking spaces for
use by persons with a disability, a
footpath having a minimum
width of 1.5m and a gradient not
exceeding 1 in 14 is required from
those spaces to the main entry
point to the building.
Objective
To ensure adequate access for goods delivery and collection and to prevent loss
of amenity and adverse impacts of traffic flows.
A1 P1
The area and dimensions of loading Loading bays must have area and
bays and access way areas must be dimensions suitable for the use, having
designed in accordance with AS2890.2 regard to:
– 2002, Parking Facilities, Part 2:
Parking facilities - Off-street
commercial vehicle facilities, for the (a) the types of vehicles likely to use
type of vehicles likely to use the site. the site;
(b) the nature of the use;
(c) the frequency of loading and
unloading;
(d) the area and dimensions of the
site; and
(e) the location of the site and nature
of traffic.
A1.2 P2
It must be demonstrated that the type Access for vehicles commercial vehicles
of vehicles likely to use the site can to and from the site must be safe,
enter, park and exit the site in a having regard to:
forward direction, without impact or
conflicting with areas set aside for
P a g e | 39
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 40
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 41
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Not applicable.
Objective
To limit on-site car parking within the Launceston Central Business District
Parking Exemption Area.
A1 P1
On-site car parking is: On-site car parking must demonstrate:
(a) not provided; or (a) that it is necessary for the operation
of the use; and
(b) not increased above existing
parking numbers.
P a g e | 42
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Complies with A1
The existing rear basement level car park will revert from being associated with
commercial tenancies to the residential tenancies. The number of compliant car
parking spaces will not be altered.
P a g e | 43
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 44
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
5 Conclusion
Approval is sought for the conversion of the upper floor of the existing York House
building to 18 residential apartments whilst maintaining the ground floor commercial
P a g e | 45
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
tenancies. The proposed adaptive reuse of the existing building furthers many of
Council’s strategic directions around promoting inner city living, particularly above
ground floor. The site is very centrally located and will afford future residents ready
access to the many facilities and services the city offers including three public parks
within 400 metres of the site.
The appropriateness of the proposed Residential use for the site is evidenced by its
status as permitted above ground level in the Urban Mixed Use zone. The key
discretion arises in relation to sunlight to private open space areas on 21 June. The
orientation of the site and existing building makes it difficult to achieve compliance
with the permitted status however the open spaces will receive glimpses of sunlight,
particularly to the upper areas and the inside living areas will all receive adequate
daylight to compensate.
On the basis of this submission and supporting reports, the application is considered
to include sufficient information to enable Council to consider the proposed use and
development and make a determination in accordance with Clause 8.10 of the Interim
Planning Scheme.
P a g e | 46
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 47
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
RESULT OF SEARCH
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
RECORDER OF TITLES
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
DESCRIPTION OF LAND
City of LAUNCESTON
Lot 1 on Plan 199230
Derivation : The allotment in (Section V.v.) Gtd. to E.
Jackson.
Prior CT 2874/91
SCHEDULE 1
B348335 TRANSFER to COANNON PTY. LTD. AND KIMBOOLA HOLDINGS
PTY. LTD.
SCHEDULE 2
Reservations and conditions in the Crown Grant if any
A185653 BENEFITING EASEMENT: Right of Carriageway in common
with others as therein mentioned over Roadway shown
on Plan No. 199230
B348336 MORTGAGE to Commonwealth Bank of Australia
Registered 01-May-1990 at 12.03 PM
B699445 LEASE to Hazard Systems Pty. Ltd. of a leasehold
estate for the term of 5 years from 1-Jun-1993
Registered 28-Oct-1994 at noon
B699447 LEASE to York Accounting Services Pty. Ltd. of a
leasehold estate for the term of 5 years from
1-Mar-1993 Registered 28-Oct-1994 at 12.01 PM
Page 1 of 1
Department of Primary Industries, Parks, Water and Environment www.thelist.tas.gov.au
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
FOLIO PLAN
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
RECORDER OF TITLES
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
Search Date: 14 Sep 2017 Search Time: 04:27 PM Volume Number: 199230 Revision Number: 01 Page 1 of 1
Department of Primary Industries, Parks, Water and Environment www.thelist.tas.gov.au
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
FOLIO PLAN
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
RECORDER OF TITLES
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
Search Date: 26 Sep 2017 Search Time: 02:16 PM Volume Number: 37624 Revision Number: 01 Page 1 of 1
Department of Primary Industries, Parks, Water and Environment www.thelist.tas.gov.au
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
RESULT OF SEARCH
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
RECORDER OF TITLES
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
DESCRIPTION OF LAND
City of LAUNCESTON
Lot 1 on Diagram 37624
Derivation : Whole of OA-2R-2Ps (Sec. V.v.) Granted to W. Milne
Prior CT 2874/92
SCHEDULE 1
M519250 TRANSFER to P & M LEES SUPER PTY LTD Registered
16-Jul-2015 at noon
SCHEDULE 2
Reservations and conditions in the Crown Grant if any
B226675 BURDENING EASEMENT: Right of Carriageway [appurtenant
to Lot 1 on Diagram No. 61/35N.S. and the lands
comrpised in Certificate of Title Volume 359 Folio
179 and Volume 362 Folio 80] over the Roadway shown
on Diagram No. 37624
BURDENING EASEMENT: Right of Carriageway in perpetuity
(appurtenant to the land comprised in Certificate of
Title Volume 1102 Folio 88) over the said Roadway in
common with the right of Daisy Fawcett to use the
said Roadway and also in common with the right of
other persons who now have the right to use the said
Roadway or who might hereafter be granted such a
right by Daisy Fawcett
Page 1 of 1
Department of Primary Industries, Parks, Water and Environment www.thelist.tas.gov.au
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 48
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
PROPOSED DEVELOPMENT
18 new apartments in existing S T REET
building 25 York St Launceston YO RK
roof below
fall 5º nom.
Balmoral On York
roof below
up
robe 3.5m3
fall 5º nom.
bed 2
carpet
robe 3m3
fall 5º nom.
carpet
roof below
bed 1
tiles
ens.
bath
tiles
roof below
tiles
bath
ens.
tiles
bed 1
vehicle access to
carpet
fall 5º nom.
bed 1
existing car park
tiles
bath
ens.
roof below
tiles
carpet
Tamar Street
bed 2
below
carpet
robe 3m3
robe 3m3
Brisbane Street up
carpet
robe 3.5m3
bed 2
up
robe 3m3
up
bed 2
carpet
robe 3.5m3
up
robe 3m3
carpet
bed 2
carpet
bed 1
tiles
bath
ens.
George Street
tiles
robe 3m3
t
roof below
e
carpet
Private Right Of Way
e
roof below
tr
bed 1
tiles
ens.
bath
tiles
rl S
fall 5º nom.
bed 1
carpet
tiles
bath
ens.
tiles
fall 5º nom.
Ea tr eet
S
robe
robe 3m3
ork
bath
Y
tiles
carpet
bed 1
fall 5º nom.
roof below
carpet
robe 3m3
bed 2
fall 9º nom. fall 9º nom.
up
up
25 private
robe 3m3
up
car park
bed 2
carpet
fall 5º nom.
robe 4.5m3
roof below
6890
Balmoral
bath
tiles
carpet
bed 1
robe 3m3
car park
roof below
6690
property boundary
carpet
tiles
ens.
bath
bed 1
tiles
carpet
bed 2
fall 5º nom.
robe 2.5m3
up
res
up
vehicle access to
fall 5º nom.
roof below
existing car park
carpet
bed 1
robe 2.5m3
bath
tiles
bath
tiles
below
robe 2.5m3
carpet
bed 1
fall 5º nom.
roof below
property boundary
up
robe 2.5m3
fall 5º nom.
up
roof below
bath
tiles
carpet
bed 1
6060
Proposed Development
fall 5º nom.
roof below
carpet
bath
tiles
bed 1
robe 2.5m3
up
Elizabeth Street 5965
robe 2.5m3
bath
tiles
carpet
bed 1
fall 5º nom.
roof below
roof below
up
bath
fall 5º nom.
tiles
Street
carpet
bed 1
robe 3.5m3
carpet
bed 2
an
robe 3.5m3
roof below
up
fall 5º nom.
ry
unda
Welm
ty b o existing shed
er
1500
prop
wa y
t of
r igh
shed
residence
in
r ma
wate
storm
0mm
existing roof
existing 100mm
water connection
existing
existing
stair
stair
existing
Apartment and
Tenancy Entry
existing existing
location of existing and propsed
proposed water meters letterboxes
new pyropanel
fire rated glazing
and door
office
up
up existing
office office
elec mains
elec mains
riser
riser
existing plant for
landing
commercial tenancies
existing columns
adjacent building
office adjacent building Balmoral on York
Balmoral on York
FHR
new pyropanel new fire rated foyer store
existing
existing commercial
tenancy no work
existing
tenancy storage
internal access
glazed partitions shown
with centre line existing existing
cl 2910 office office existing commercial tenancy
office reception
office
office
existing
office
existing vehicle access
retain for commercial tenacies
office existing
store
office
office
office office
void
existing
print / waste office
existing
hall office
office
open office board room
female wc
lunch room server / store
hall
cl 2910
existing roof
existing
workshop
store
existing
tea room fall
void
hall
store
(access from car park)
hall
existing access
/ fire stair
existing escape stair
existing
existing commercial
tenancy storage
existing roof structure to be removed
existing right of way
store
existing concrete
columns
660l rear lift
general waste
and recycling bins
existing concrete
columns
existing vehicle access
new perforated roller door
existing
workshop
existing
office
existing stair
existing stair
right of way
right of way existing
workshop
right of way
right of way
Existing Ground Floor plan Existing First Floor plan Existing Second Floor plan Existing Roof plan
1:200@A1 1:200@A1 1:200@A1 1:200@A1
adjacent building
Balmoral on York existing low pitched existing pitched roof
behind existing pilasters roof behind
existing
texture finish
existing existing
awning over York St entry existing crossover
to right of way
existing exhaust
to be removed
adjacent building
Balmoral on York
behind
existing aluminium
framed windows
existing painted
concrete block wall
existing painted
existing loading dock concrete block wall
and access roller doors
existing FL: Middle
existing painted
concrete block wall
existing vent existing car park
of way driveway access roller door
existing right existing escape door
Yor existing letterboxes
k St
foo 27-29 York St
tpa
th
existing FL: Lower
existing tenancy
EXISTING WEST ELEVATION car park access
roller door
existing water connection
and meters
adjacent building
Balmoral on York
shown greyed in front
existing exhaust
to be removed
existing unpainted
concrete block wall
existing unpainted
concrete block wall
adjacent building
Balmoral on York
shown greyed in front
open office
office
office
660l rear lift
store
(access from car park)
2600
general waste
4. and recycling bins
board room
reception
existing columns
existing concrete
columns
plumbing penetration
refer to engineers drawings
2600
2600
5.
3.
office
open office
office
2600
office
2500
2. 6.
hall
gym / store
hall
foyer wall infill
existing concrete
pedestrian zone columns
plumbing penetration
refer to engineers drawings
server / store
new fire rated fire rated glazing
2600
elec mains apartment parking 11 spaces 7.
office
office
riser LIFT
existing proposed lift to lower
apartment level
print / waste
stair
hall
store
open office
new pyropanel
and door
cl 2910
up existing
reception
landing
bicycle parking
2600
2600
lunch room
8.
4555
cl 2910
office
office
med
iu
store
m ri
gid t
existing loading dock
to be removed
new fire door in
existing opening
hall
ruck
2500
2600
1. 9.
turn
5400 existing loading dock and bay
to be removed
ing p
hall
ath
female wc
office
office
office
office
office
2600
660l rear lift
male wc
rev
ers
e
existing access new water meter enclosure existing vehicle access
/ fire stair recessed into wall refer to new perforated roller door new access &
engineers drawings / fire stair from
apartment level
o/ct f
3090
o/ct o/ct area 9.3m2 area 9.1m2 outdoor
outdoor
2640
o/ct o/ct area 17m2
area 14.5m2
f
1. 2 BED f f f
114m2 + outdoor f f
area 21.5m2
o/ct
bed 2 bed 1
kitchen
store
store
dining
3m3
3m3
3. 2 BED dining living living dining
dining dining kitchen
kitchen dining 69+48m2 + outdoor living living 5. 2 BED 7. 2 BED 9. 2 BED
area 13.8m2 68.8+48m2 + outdoor 66+48m2 + outdoor 64+48m2 + outdoor o/ct
up bed bed
area 13.2m2 area 10.9m2 area 11.4m2 11. 1 BED 13. 1 BED o/ct
35.2+23.2m2 + outdoor 34.8+23.2m2 + outdoor
area 10.2m2
store concrete
up area 9.9m2 15. 1 BED
6m3 ens. clear finish living f
accessible 37.5m2 + outdoor
f
17. 1 BED
living area 17m2 accessible 38m2 + outdoor
area 14.5m2
wm
wm
wm
wm
concrete concrete
clear finish clear finish
fw
fw
dining ldry/store ldry/store ldry/store ldry/store access wc access wc
bath powder 3m3 3m3 powder powder 3m3 3m3 powder entry entry
entry ldry entry entry entry entry entry entry tiles tiles
up
up
up
up
tiles tiles tiles tiles tiles ldry ldry
store store store store ldry / ldry / store store
4m3 4m3 4m3 store store
wm
HWC
store
1500
19496
6.4m3
existing
stair ldry / ldry / ldry / ldry /
store store store store/ store store/ store/ store/
up
4m3 tiles tiles 4m3 3.2m3 tiles wc 2.8m3 tiles 3.2m3 2.8m3 2.8m3 2.8m3
entry entry entry entry
up
up
up
up
ldry/store powder entry entry
powder ldry/store ldry/store powder powder ldry/store
3m3 3m3 3m3 entry 2.8m3 entry entry
concrete concrete concrete concrete
clear finish clear finish clear finish clear finish
wm
wm
wm
wm
18. 2 BED
76+47m2 + outdoor f o/ct
area 9.8m2
living living living living
kitchen
4. 2 BED 6. 2 BED 8. 1 BED 10. 2 BED 12. 1 BED 14. 1 BED 16. 1 BED
32.9+22m2 + outdoor
2. 2 BED dining 65.2+48m2 + outdoor 64.4+48m2 + outdoor up dining 63+46m2 + outdoor 32.6+22m2 + outdoor up up 32.6+22m2 + outdoor 32.3+22m2 + outdoor up
3.2m3
dining area 8.2m2 area 7.8m2 area 7.6m2 dining
store
75+47.6m2 + outdoor area 10m2 area 9.8m2 f area 9m2 area 7.7m2
3.2m3
3.2m3
3.2m3
living living living
store
store
store
area 17.5m2
dining living dining dining dining
f dining
f concrete
f f f f
clear finish
f
outdoor
area 17.5m2 o/ct living
o/ct o/ct o/ct
2885
wall / screen
wall / screen
new
2400
3130
o/ct o/ct o/ct o/ct outdoor outdoor outdoor fire stair
1800 high
1800 high
wall / screen
3890
fall 5º nom.
fall 5º nom.
fall 5º nom.
roof below roof below fall 5º nom.
roof below
roof below roof below
3310
fall 5º nom.
robe 3m3
robe 3m3
robe 3m3
robe 3m3
bed 1 bed 1 bed 1 bed 1
bed 2 bed 2
carpet bed 2 bed 2 carpet carpet carpet
roof below carpet carpet
carpet carpet
bed 1 bed 1
fall 5º nom.
up carpet carpet up
6890
7235
5965
roof below
ens. ens. ens. ens.
fall 5º nom.
robe 3m3 robe 3m3 robe 3m3 robe 3m3
bath bath
bath bath bath bath
up
up
up
up
tiles tiles
tiles tiles tiles tiles
1500
fall 5º nom.
up
roof below tiles tiles tiles
tiles tiles tiles tiles tiles
up
up
up
up
bath bath bath tiles
bath bath bath bath bath
bath
6425
robe 3.5m3 robe 3.5m3 robe 3.5m3 robe 4.5m3 robe 2.5m3
6060
ens. ens. ens.
6690
7235
carpet carpet
carpet up carpet up up carpet up bed 1
carpet bed 2
carpet carpet bed 1 carpet carpet bed 1 bed 1 bed 1
robe 3.5m3
bed 2 bed 1 bed 1 bed 2 bed 2 bed 1 bed 1 bed 2
carpet
robe 3m3 robe 3m3 robe 3m3
fall 5º nom.
2975
fall 5º nom.
fall 5º nom.
fall 5º nom.
roof below roof below roof below roof below
2930
roof below
roof below roof below roof below
roof below
fall 5º nom.
fall 5º nom.
fall 5º nom.
roof below roof below fall 5º nom.
roof below
roof below roof below
fall 5º nom.
robe 3m3
robe 3m3
robe 3m3
robe 3m3
bed 1 bed 1 bed 1 bed 1
bed 2 bed 2
carpet bed 2 bed 2 carpet carpet carpet
roof below carpet carpet
carpet carpet
bed 1 bed 1
fall 5º nom.
up carpet carpet up
fall 9º nom.
6890
tiles tiles tiles tiles
5965
roof below
ens. ens. ens. ens.
fall 5º nom.
robe 3m3 robe 3m3 robe 3m3 robe 3m3
bath bath
bath bath bath bath
up
up
up
up
tiles tiles
tiles tiles tiles tiles
1500
fall 5º nom.
up
fall 9º nom.
roof below tiles tiles tiles
tiles tiles tiles tiles tiles
up
up
up
up
bath bath bath tiles
bath bath bath bath bath
bath
6060
ens. ens. ens.
6690
tiles tiles tiles
carpet carpet
carpet up carpet up up carpet up bed 1
carpet bed 2
carpet carpet bed 1 carpet carpet bed 1 bed 1 bed 1
robe 3.5m3
bed 2 bed 1 bed 1 bed 2 bed 2 bed 1 bed 1 bed 2
carpet
robe 3m3 robe 3m3 robe 3m3
fall 5º nom.
fall 5º nom.
fall 5º nom.
fall 5º nom.
roof below roof below roof below roof below
roof below
roof below roof below roof below
roof below
replace and extend glazing replace and extend glazing replace and extend glazing replace and extend glazing new low roof replace existing glazing with apartment balcony /deck
to 1000mm sill height with to 1000mm sill height with to 1000mm sill height with to 1000mm sill height with over apartment 1 new double glazed units remove existing windows
new double glazed units new double glazed units new double glazed units new double glazed units and existing stairwell
adjacent building
Balmoral on York
behind
11600
25
YORK
adjacent building
Balmoral on York
behind
aluminium frame new upper level roof existing concrete upper level 1800 privacy screen vertical sunshading remove existing roof and asbestos
windows and doors beam and columns bedrooms behind between apartments screen new roof structure and sheeting new flashing to existing
new low roof powdercoated aluminium existing concrete new guttering and downpipes new lightweight cladding new lightweight cladding parapet matching
colorbond, grey tones framed windows to living areas columns and beam connect to existing stormwater window system installed easylap or similar paint finish new roof line
from inside quantum or similar
lower apartment floor level: existing floor lower apartment floor level:
existing floor
new subwall
existing windows and existing building remove existing concrete block cladding new fire escape
openings no work lower level no work to rebate below existing floor level
adjacent building
Balmoral on York
shown greyed in front
new lightweight cladding new lower roof remove asbestos powder coated new lightweight cladding new openings in upper level existing concrete new guttering and downpipes new lightweight cladding
to upper level walls fc sheet roof sheeting aluminium frame to upper level walls fc sheet existing wall bedroom columns and beam connect to existing stormwater to upper level walls fc sheet
or similar paint finish windows and doors or similar paint finish or similar paint finish new bedroom windows
open to courtyard new lower roof over
retain existing fire wall single level apartment
new light coloured finish
570
230
line of existing ridge
4780 proposed height from ground
proposed upper
apartment floor level
adjacent building
Balmoral on York
shown greyed in front
proposed upper
apartment floor level
SOUTH ELEVATION
21 June
21 August
1pm 21 August 2pm 21 August 3pm 21 August 4pm 21 August PRELIMINARY NOT FOR CONSTRUCTION
REVISION DA2 DATE 22-03-18 DESCRIPTION Issued for Development Application
ADDRESS do not scale off plans ISSUE
25 York St all dimensions in millimetres
confirm all dimensions on site
all work to relevant NCC and AS
DA2
CLIENT DWG #
Bush
architecture DWG
SCALE @ A1
DRAWN
as shown
GF
DA-11
Shadow Diagrams CHKD SH PROJECT# J002880
development
S. Group © Copyright 2018 1/10-14 Paterson Street Launceston, Tasmania
strategic design PO Box 1271 Launceston TAS 7250 Australia T: 03 63 111 403 E: info@sgroup.com.au W: www.sgroup.com.au
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
P a g e | 49
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Environmental
Site
Assessment
Document Control
Prepared & Published by: ES&D
Version: Final V3
File: 5961v2
Contact: Rod Cooper
Phone No: (03) 6431 2999
Prepared For: Launceston City Council
Version: Date:
DRAFT 1 S Smith ES&D 13/10/2017
Final V2 R Cooper ES&D 31/10/2017
Final V3 R Cooper ES&D 18/3/2018
This report has been prepared, based on information generated by Environmental Service and Design Pty Ltd from
a wide range of sources. If you believe that Environmental Service and Design Pty Ltd has misrepresented or
overlooked any relevant information, it is your responsibility to bring this to the attention of Environmental Service
and Design Pty Ltd before implementing any of the report’s recommendations. In preparing this report, we have
relied on information supplied to Environmental Service and Design Pty Ltd, which, where reasonable,
Environmental Service and Design Pty Ltd has assumed to be correct. Whilst all reasonable efforts have been made
to substantiate such information, no responsibility will be accepted if the information is incorrect or inaccurate.
This report is prepared solely for the use of the client to whom it is addressed and Environmental Service and Design
Pty Ltd will not accept any responsibility for third parties. In the event that any advice or other services rendered by
Environmental Service and Design Pty Ltd constitute a supply of services to a consumer under the Competition and
Consumer Act 2010 (as amended), then Environmental Service and Design Pty Ltd.’s liability for any breach of any
conditions or warranties implied under the Act shall not be excluded but will be limited to the cost of having the
advice or services supplied again. Nothing in this Disclaimer affects any rights or remedies to which you may be
entitled under the Competition and Consumer Act 2010 (as amended). Each paragraph of this disclaimer shall be
deemed to be separate and severable from each other. If any paragraph is found to be illegal, prohibited or
unenforceable, then this shall not invalidate any other paragraphs.
List of Figures
Figure 1 – Site Plan........................................................................................................................................ 9
Figure 2 – Zoning – Community Purpose .................................................................................................... 10
Figure 3 – Topographical map with inferred groundwater flow ................................................................ 12
Figure 4 – Picture of two fuel tanks within “Goods Receipt” bay.............................................................. 15
Figure 5 – Picture of four underground storage tanks within “Goods Receipt” bay .................................. 15
Figure 6 – Soil sampling plan....................................................................................................................... 22
Executive Summary
Environmental Service and Design (ES&D) were commissioned by S. Group Architects, on behalf
of their client, to conduct an Environmental Site Assessment (ESA) for the proposed residential
development at 23-25 York Street Launceston (the “Site”). Risk and concern was raised by
Launceston City Council relating to the presence of fuel tanks associated with the previous
operation of a wholesale chemist. The assessment was conducted by Samuel Smith of
Environmental Service and Design and reviewed by Site Contamination Practitioners Australia
(SCPA) certified practitioner Mr. Rod Cooper of Environmental Service and Design (SCPA
certification no. 15020).
• Collate site historical information to establish whether activities have occurred on site
which may have resulted in contamination of the land;
• Assess the previous land uses and subsurface conditions to determine the potential for
soil and groundwater contamination at the Site;
• Provide an assessment of the suitability of the Site for the proposed development; and
The assessment was conducted according to the principles and methodology contained within
the National Environmental Protection (Assessment of Site Contamination) Measure, 1999 (as
amended 2013). The purpose of this environmental site investigation was to identify the
potential for contamination at the site based on a desktop review of available historical
information, conversations with relevant personnel and geology. Of note, the development will
include a move to a more sensitive use, being residential. All previous operation was to a
commercial / industrial standard.
A review of the site history, dangerous goods licensing from WorkSafe Tasmania and EPA register
was conducted. Based on the dangerous goods file for the subject site, all relevant contaminants
of concern were traced to the UPS tanks on the site. A detailed assessment was required to
eliminate risk from the onsite UPS Tanks for the DA to proceed.
5
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
A site visit completed by ES&D representatives located four underground storage tanks within
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
the loading bay area, two of which contain water /fuel. The preliminary design drawings provided
by S. Group Architects indicate disturbance will occur in this area as part of the development,
thus increasing risk to construction and sub surface workers. Additionally, as part of the
development footings will be placed in this area, which will likely result in severe geotechnical
issues (i.e. footings in fill material or above tanks).
A detailed site assessment was required to satisfy LCC Planning requirement E2.5 and E2.6.2 that
potentially contaminating activities have not resulted in contamination on the site (i.e. area
where the DA is implemented).
ES&D would recommend the following occur as part of the contaminated site investigation:
• Determine if there is any risk to the development from the 4 UPS tanks located on the
site.
• All underground storage tanks be filled with grout to prevent geotechnical issues before
development occurs.
This plan being in place confirms that we satisfy LCC Planning requirement of both E2.5 and
E2.6.2.
6
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
1 Introduction
Environmental Service and Design (ES&D) were commissioned by S. Group Architects, on behalf
of their client, to undertake an Environmental Site Assessment on the proposed residential
development at 23-25 York Street Launceston. The aim of the ESA to establish whether activities
have occurred on the site which may result in contamination of the land and if so, whether the
level of risk will increase with the proposed development. The ESA will also outline potential
environmental issues associated with the development associated with the change of use.
The proponents are lodging a DA for York House, converting the upper floor into apartments,
there will be 9x2 bed units and 9x 1 bed units. The car park will remain unchanged.
The Launceston Interim Planning Scheme 2015 specifies that environmental site assessments in
relation to potentially contaminating activities must be prepared by a suitably qualified person.
Council indicated that suitably qualified persons include Site Contamination Practitioners
Australia (SCPA) certified practitioners. Consequently, Mr Rod Cooper of Environmental Service
and Design (SCPA certification no. 15020) was engaged to perform the assessment.
Under the Launceston Interim Planning Scheme 2015 the proposed development will need to
satisfy the Contaminated Land Code E2;
Whether it is considered from a use (E2.5) or development (E2.6.2) perspective (both of which
are applicable), we will show that the site meets the performance criteria,
(a) an environmental site assessment that demonstrates there is no evidence the land is
contaminated.
7
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
2 Scope of Works
o oral history;
o a search of WorkSafe Tasmania’s (WST) general records management system,
which holds information pertinent to potentially contaminating activities on
land in Tasmania, including storage of dangerous goods (fuel storage),
Environment Protection Authority (EPA) Environmentally Relevant Land Use
Register, and Council database information;
• a site visit to check for any visual evidence that may indicate contamination of the site
(addressed above), and an investigation of nearby properties.
• soil samples from around the decommissioned tanks to confirm there is no risk to the
development.
As a State Policy for the purposes of State policies and Procedures Act 1993, the National
Environmental Protection (Assessment of Site Contamination) Measure 1999 (NEPM) was the
guideline used for the assessment.
8
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
4 Site Details
Coannon Pty. Ltd. and Kimboola Holdings Pty. Ltd. are currently considering developing 23-25 York
Street Launceston (the upper floor) and lodging a DA for 9x2 bed units and 9x 1 bed units.These
will be residential (B) apartments. The car park will remain unchanged.
The investigation area covers approximately 1572 m2 at 23-25 York Street Launceston. The sites
location is shown on Figure 1.
4.2 Zoning
The site is currently zoned “Urban mixed use” (Launceston Interim Planning Scheme 2015, Figure
2) and is surrounded by “Inner Residential” to the east and south, “Urban mixed use” to the north
and West. “Central Business” zoning exists to the far west of the site.
9
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Urban
Mixed Use
Central Business
Inner Residential
5 Site Description
23-25 York Street, Launceston is currently owned by the Coannon Pty. Ltd. and Kimboola Holdings Pty.
Ltd. and is occupied by several businesses including IT and financial companies. The site is proposed for
9x2 bed units and 9x 1 bed residential apartments to be constructed within the existing multi-level
commercial building. This is a more sensitive use and so residential guidelines need to be met. The
dangerous goods file indicates licenses were issued to Drug Houses of Australia, Medical Distribution
Centre, Cados and Sigma Company for the storage of fuel, chemicals and drum/bottle (inflammable
liquids) between 1964 and 1980. Concerns have thus been raised by Launceston City Council due to the
presence of fuel and chemical tanks. This under the LCC Interim Planning Scheme 2015 is the potentially
contaminating activity being investigated.
10
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
6 Geology, Hydrology and Hydrogeology
6.1 Topography
The site slopes gently from the to the north-west. A review of Google Earth indicates elevations
range from 30m AHD at the south-east corner of the site to 22m AHD at the north-west corner
of the site. Local topography declines steeply to the west. Site visit showed that the western
boundary drops at least 7.0 meters over several meters and no seepage or groundwater is
evident. Groundwater depth is at least 7-8 below the surface.
The nearest surface water body is North Esk River located approximately 700m to the north
Review of the LIST (Land Information System Tasmania) indicates that the sites is underlain with
undifferentiated cenozoic sequences consisting of poorly consolidated clay, silt, and clayey labile
sand with rare gravel and lignite; some iron oxide-cemented layers and concretions; some leaf
fossils. Bore logs (Appendix 2) indicate reasonably good quality clay to 3.0 meters.
11
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
12
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
6.5 Acid Sulfate Soils
Review of the LIST (Land Information System Tasmania) indicates that the site has no potential
containing acid sulphate soils.
7 Site History
The following information has been reviewed to determine the historical land uses and likelihood
of contamination as a result.
A search of the EPA Tasmania’s contaminated land register (pre-2007) was conducted and
determined the site has not been regulated, had any incidents/complaints nor been listed as
potentially contaminated. From this we can assume there were no incidents in the acid storage
area.
Several wholesale chemists/processing existed on the site from at least 1964. Dangerous goods
licensing indicates the potential for petrol, kerosene, acids and ethers in underground storage
tanks at the site. Contaminants of Potential Concern (COPC) associated with the underground
storage of fuels/chemicals include:
13
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
•
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Heavy metals (predominantly lead)
• BTEX
• Phenols
• Ethers
Records did not indicate drugs were produced on the site, it is thought that drug packaging was
conducted and the records clearly indicated 4 UPS tanks and other chemicals within smaller
above ground storage area, probably in the receiving area directly behind the UPSS system.
9 Site Visit
ES&D representatives visited the sites on the 14th of September 2017. The site was occupied by
several IT and financial companies. The perimeter of the site was inspected along with the ground
floor of the building. Four underground storage tanks were identified within the “Goods Receipt”
at the south-western corner of the building (figures 4 and 5). Two of these were filled with
concrete, while the other two were filled with water and contained some fuel odour. All bowsers
have been removed from the site and there were no fill lines, however the vent lines are still on
the side of the building. Asbestos super-six sheeting was noted on the roof of the building in good
condition.
No hydrocarbon staining was evident in the loading bay or on the slab of the ground floor of the
building. No evidence of bulk chemical storage was evident on the site.
Neighboring properties upgradient consist of residential dwellings which will not result in a
potential contamination risk to the site. Additionally, based on the steep topography at the site,
contamination from the underground storage tanks is likely to move away from the building,
reducing risk of vapour intrusion. The warehouse area had solid clean floors and so apart from
the four underground tanks it is likely any other chemicals would have been stored in smaller
above ground containers.
14
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Underground tanks
containing fuel/water
Underground tanks
filled with concrete
Figure 5 – Picture of four underground storage tanks within “Goods Receipt” bay
15
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
10 Potential Receptors
A preliminary Conceptual Site Model (CSM) (Table 1) was developed after consideration of risks
to potential human and ecological receptors as outlined below.
Future residents and workers involved in the construction of the development were considered
in the preliminary CSM, along with subsurface workers and Residential B usage (minimal
opportunities for soil access).
16
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
17
ESA – 23-25 York Street Launceston
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
The NEPM 2013 defines the DQO approach as a seven-step process to define the type, quantity
and quality of data to support decisions relating to the environmental condition of a site. The
DQO approach assesses performance or acceptance criteria that data need to achieve by
reference to Measurable Data Quality Indicators (MDQI) for both field and laboratory
procedures.
To provide advice on the extent of contamination at the site and determine the potential risk
posed to human health and the environment associated with the proposed residential
development, development and use. A preliminary site investigation undertaken by ES&D
identified potentially contaminating activities have occurred based on the site history. Ie UPSS.
The goals of the assessment were to obtain sufficient information to indicate the extent and
magnitude of contamination that may exist on the site and aid decision-making.
The decisions to be made based on the results of the investigative program are:
• Does soil at the site contain concentrations of CoPC more than the adopted assessment
criteria?
• Do the findings of the investigation provide sufficient data to conclude the site is suitable
for residential development without the requirement for remediation or further
assessment.
The main inputs that were required to resolve the goals of the study were:
• Soil condition – judgmental sampling and analysis of natural soils using auger.
Note that the samples to be taken between the tanks and the building.
The study boundary was limited to the area identified in figure 1 (23-25 York Street) and
investigation limit (extent of test pits).
The potential for significant decision errors should be minimised by implementing the QA/QC
program and by completing an investigation that has an appropriate sampling and analytical
density for the purposes of the investigation and comprises representative sampling.
The results of the judgmental sampling program must meet the following:
• COPC do not exceed the human health investigation or screening criteria for residential
developments for all soil samples.
The quality of data collected by the investigation will be assessed by ensuring the field sampling
methodology is appropriate, documentation is complete, samples are tested for the COPC’s,
sampling techniques are appropriate, representative samples are collected, trained personnel
perform the tasks, and NATA laboratory testing. This will ensure any comparison against the
health investigation and screening levels is reliable.
The sampling, analysis and quality plan for the site investigation has been developed to
determine current levels of soil contamination in the areas proposed for development and
determine risks to human health using adopted assessment criteria. Use of appropriate sampling
design, sampling techniques and use of a NATA certified laboratory the data will satisfy the
objectives of the investigation.
12 Investigation Methodology
Sampling activities were prepared for the site prior to commencing field work and were produced
as the outcome of the seven-step DQO process (section 13) and were guided according standards
listed below:
• AS 4482.1 (2005) Guide to the Sampling and Investigation of Potentially Contaminated Soil
- Part 1: Non-Volatile and Semi Volatile Compounds;
• AS 5667.1 (1998) Guidance on the design of sampling programs, sampling techniques and
the preservation and handling of sampling.
Environmental Service and Design investigated potential soil contamination at 23-25 York Street
5th October 2017. Based on the likely extent of contamination associated with the historical
storage of ethers and petroleum products, two boreholes were drilled to the east of the storage
tanks already decommissioned, between them and the building. To assess contamination
associated with the storage of petroleum products, samples were collected at 3.4m and analysed
for:
• TPH/TRH
• BTEXN
A photo ionization meter was used throughout the drilling activities to identify sources of volatile
organic carbons in addition to visually inspecting the removed soil every .5m to 1m for evidence
of hydrocarbon staining.
To assess the level of contamination associated with the historical storage of petrol and diesel,
samples were collected in two locations (figure 6) and analysed for the presence of volatile
organics and petroleum hydrocarbons. It is also noted that if there had been acid contamination
within the building and it has impacted soil, PID and odour would be detected at the sampling
points.
13 Field Activities
The services locator marked out the tank positions and, where possible, lines to ensure no
damage to underground infrastructure, including UPSS occurred. Boreholes were drilled using a
4x4 vehicle mounted hollow flight auger.
Judgmental soil samples were collected directly from the drill auger and handled according to
the documented QA/QC procedures. Each soil sample was rapidly collected into ALS supplied
analyte appropriate bottles, individually labelled, placed in an eski with freezer packs and
dispatched for overnight delivery to the laboratory with an accompanying chain of custody
document. Based on the historical activities at the site, each sample was also visually inspected
for ACM.
Field duplicates to be collected and analysed at a rate of 1 in every 20 primary samples; not
withstanding this, one duplicate to be collected per matrix
Duplicated samples to be labelled so as to conceal their relationship to the primary sample from
the laboratory. No groundwater was encountered so no groundwater samples were taken.
Techniques used to prevent cross contamination of samples and ensure the integrity of samples
were as follows:
•
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
• individual soil samples were collected by hand with single use disposable nitrile gloves;
• each soil sample was rapidly collected into ALS supplied analyte appropriate bottles,
individually labelled, placed in an eski with freezer packs and despatched for overnight
delivery to the laboratory with an accompanying chain of custody document;
Health Screening Levels (HSLs), Health Investigation Levels (HILs) and Groundwater Investigation
Levels (GILs) provided in the NEPM were the designated criteria for assessing potential human
health risks posed by contamination of soil and groundwater as applicable. The screening levels
are applied according to the land use scenario, soil type and depth. Generic land uses are
described in detail in NEPM Schedule B7 Section 3. Investigation levels are applied according to
the relevant land use scenario. Risk to receptors from site contamination is considered to be
acceptable where a result does not exceed the relevant screening or investigation level.
Assessment criteria are included in the results tables in Section 15.
As per Section 10.2 ecological assessment criteria were not applied and groundwater was not
encountered.
Site soils were predominantly silts and silty clay, but tank pits are usually packed with sands.
Section 4.6 of CRC CARE TR10 suggests that when the soil type does not match any of the three
soil categories used in the derivation of HSLs the appropriate option when deciding on soil types
for assessment of key scenarios / receptors is to assume the soil is sand as the most conservative
of the HSLs and this was the strategy adopted for the assessment.
Soil screening / investigation levels adopted were for Residential B (HSL-B, HIL-B) scenario to
account for risk to on-site land users with minimal opportunities for soil access.
Table 2 – Soil Assessment Criteria, Health Screening Levels / Health Investigation Levels
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
All primary and duplicate sample results and RPD calculations are “0%” as all results were below
detection limits so it was not deemed necessary to produce a table.
The NATA certified laboratory runs an extensive complement of QC samples with submitted
samples. The MDQI for laboratory QC was that its QA/ QC results should comply with the
laboratory’s own acceptance criteria. Any results outside the MDQI to be noted and explained.
The selection of samples for analysis was based on field observations and was conducted in
accordance with the SAQP presented above.
Laboratory analysis was conducted in accordance with the requirements of NEPM and is
referenced to USEPA and APHA methods. The analytical schedule, laboratory methods,
laboratory limits of reporting (LORs) and reference methods applied for the investigation are
detailed in appended laboratory QC reports.
15 Results
TPH
TRH
C6 – C10 Fraction minus BTEX (F1) mg/kg 50 110 180 <10 <10 <10
>C16 – C34 Fraction (F3) mg/kg 100 300 <100 <100 <100
>C34 – C40 Fraction (F4) mg/kg 100 2800 <100 <100 <100
>C10 – C16 Fraction minus Naphthalene (F2) mg/kg 10 440 120 <50 <50 <50
BTEXN
The results of the preliminary and detailed site investigation, based on the site history, site
assessment and desktop assessment, indicate there is no detected site contamination.
A final CSM was not constructed as no contamination was detected under the principles and
methodology contained within the NEPM. Risk assessment found there is no risk to residents,
construction workers nor subsurface workers due to contamination from the UPSS.
Contamination was not detected. Management measures are not required as no contamination
was detected.
A site visit completed by ES&D representatives located four underground storage tanks within
the loading bay area, two of which contained some fuel / water. The preliminary design drawings
provided by S. Group Architects indicate disturbance will occur in this area as part of the
development, thus increasing risk to construction and sub surface workers. Additionally, as part
of the development footings will be placed in this area, which will likely result in severe
geotechnical issues (i.e. footings in fill material or above tanks).
Soil tests conclusively showed no risk from the 4 UPS tanks on the site. There is no remaining
contamination on the site associated with these tanks.
• Approval of the DA, the site contamination levels are acceptable for the development
proposed. 9x2 bed units and 9x 1 bed units
The Launceston Interim Planning Scheme 2015 use (E2.5) or development (E2.6.2), meets the
performance criteria,
(a) an environmental site assessment that demonstrates there is no evidence the land is
contaminated.
Rod Cooper.
17 Limitations
ES&D has prepared this report in accordance with the care and thoroughness of the consulting
profession for S. Group Architects. It was based on accepted practices and standards at the time
it was prepared. No other warranty, expressed or implied, is made as to the professional advice
included in this report. It is prepared in accordance with the scope of work and for the purpose
outlined.
This report was prepared during September and October 2017 and is based on the conditions
encountered and information reviewed at the time of preparation. ES&D disclaims the
responsibility for any changes that may have occurred after this time.
This report should be read in full. No responsibility is accepted for any use of any part of this
report in any other context or for any other purpose or by third parties. This report does not
purport to give legal advice.
Subsurface conditions can vary across a site and cannot be explicitly defined by these
investigations. It is unlikely therefore that the results and estimations expressed in this report
will represent the extreme conditions within the site.
The information in this report is accurate at the date of issue and is in accordance with conditions
at the site at the dates sampled.
This document and the information contained herein should only be regarded as validly
representing the site conditions at the time of the investigation unless otherwise explicitly stated
in a preceding section of the report.
28
PSI – 23-25 York Street Launceston 7250
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
References
Launceston City Council Interim Planning Scheme 2015
29
PSI – 23-25 York Street Launceston 7250
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Appendices
30
PSI – 23-25 York Street Launceston 7250
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
31
PSI – 23-25 York Street Launceston 7250
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
WORKSAFE TASMANIA
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Planning Administration
18/04/2018
BOREHOLE LOG
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Classification
Consistency
Penetration
Resistance
Samples
Moisture
Support
Method
Symbol
Depth
Water
CONCRETE slab
DC
N
1.5
yellow mottled red
2.5
E 3.5
Borehole terminated @ 3.5m depth
U50
PP=470kPa
4.0
4.5
5.0
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised:
Planning Administration
18/04/2018
BOREHOLE LOG
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Classification
Consistency
Penetration
Resistance
Samples
Moisture
Support
Method
Symbol
Depth
Water
CONCRETE slab
DC
N
1.0
D
1.5
grey mottled red and yellow
D 2.0
3.0
E 3.5
Borehole terminated @ 3.5m depth
U50
4.0
4.5
5.0
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised:
Planning Administration
18/04/2018
BOREHOLE LEGEND
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
DC Diamond Coring
HA Hand Auger
Support: N None
Water: Seepage
E Environmental Sample
Moisture: D Dry
M Moist
W Wet
Consistency: L Loose
MD Medium Density
D Dense
S Soft
F Firm
St Stiff
PP Pocket Penetrometer
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Environmental
CERTIFICATE OF ANALYSIS
Work Order : EM1713722 Page : 1 of 4
Client : ENVIRONMENTAL SERVICE AND DESIGN PTY LTD Laboratory : Environmental Division Melbourne
Contact : MR ROD COOPER Contact : Shirley LeCornu
Address : 14 CATTLEY ST. PO BOX 651 Address : 4 Westall Rd Springvale VIC Australia 3171
BURNIE TASMANIA, AUSTRALIA 7320
Telephone : +61 03 6431 2999 Telephone : +61-3-8549 9630
Project : 5961 Date Samples Received : 06-Oct-2017 22:25
Order number : ---- Date Analysis Commenced : 06-Oct-2017
C-O-C number : ---- Issue Date : 10-Oct-2017 13:01
Sampler : RC
Site : 25 York Street
Quote number : MEQB-167-15
No. of samples received : 3
No. of samples analysed :3
This report supersedes any previous report(s) with this reference. Results apply to the sample(s) as submitted. This document shall not be reproduced, except in full.
This Certificate of Analysis contains the following information:
l General Comments
l Analytical Results
l Surrogate Control Limits
Additional information pertinent to this report will be found in the following separate attachments: Quality Control Report, QA/QC Compliance Assessment to assist with
Quality Review and Sample Receipt Notification.
Signatories
This document has been electronically signed by the authorized signatories below. Electronic signing is carried out in compliance with procedures specified in 21 CFR Part 11.
Signatories Position Accreditation Category
:
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
General Comments
The analytical procedures used by the Environmental Division have been developed from established internationally recognized procedures such as those published by the USEPA, APHA, AS and NEPM. In house
developed procedures are employed in the absence of documented standards or by client request.
Where moisture determination has been performed, results are reported on a dry weight basis.
Where a reported less than (<) result is higher than the LOR, this may be due to primary sample extract/digestate dilution and/or insufficient sample for analysis.
Where the LOR of a reported result differs from standard LOR, this may be due to high moisture content, insufficient sample (reduced weight employed) or matrix interference.
When sampling time information is not provided by the client, sampling dates are shown without a time component. In these instances, the time component has been assumed by the laboratory for processing
purposes.
Where a result is required to meet compliance limits the associated uncertainty must be considered. Refer to the ALS Contact for details.
Key : CAS Number = CAS registry number from database maintained by Chemical Abstracts Services. The Chemical Abstracts Service is a division of the American Chemical Society.
LOR = Limit of reporting
^ = This result is computed from individual analyte detections at or above the level of reporting
ø = ALS is not NATA accredited for these tests.
~ = Indicates an estimated value.
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
Page
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
: 3 of 4
Work Order EM1713722
reproduce the document in their web browser for the sole purpose of viewing the
:
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Analytical Results
Sub-Matrix: SOIL Client sample ID Duplicate North South ---- ----
(Matrix: SOIL)
Client sampling date / time 05-Oct-2017 16:00 05-Oct-2017 10:30 05-Oct-2017 11:35 ---- ----
Compound CAS Number LOR Unit EM1713722-001 EM1713722-002 EM1713722-003 -------- --------
Result Result Result ---- ----
:
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
False
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Environmental
QUALITY CONTROL REPORT
Work Order : EM1713722 Page : 1 of 5
Client : ENVIRONMENTAL SERVICE AND DESIGN PTY LTD Laboratory : Environmental Division Melbourne
Contact : MR ROD COOPER Contact : Shirley LeCornu
Address : 14 CATTLEY ST. PO BOX 651 Address : 4 Westall Rd Springvale VIC Australia 3171
BURNIE TASMANIA, AUSTRALIA 7320
Telephone : +61 03 6431 2999 Telephone : +61-3-8549 9630
Project : 5961 Date Samples Received : 06-Oct-2017
Order number : ---- Date Analysis Commenced : 06-Oct-2017
C-O-C number : ---- Issue Date : 10-Oct-2017
Sampler : RC
Site : 25 York Street
Quote number : MEQB-167-15
No. of samples received : 3
No. of samples analysed :3
This report supersedes any previous report(s) with this reference. Results apply to the sample(s) as submitted. This document shall not be reproduced, except in full.
This Quality Control Report contains the following information:
l Laboratory Duplicate (DUP) Report ; Relative Percentage Difference (RPD) and Acceptance Limits
l Method Blank (MB) and Laboratory Control Spike (LCS) Report ; Recovery and Acceptance Limits
l Matrix Spike (MS) Report ; Recovery and Acceptance Limits
Signatories
This document has been electronically signed by the authorized signatories below. Electronic signing is carried out in compliance with procedures specified in 21 CFR Part 11.
Signatories Position Accreditation Category
General Comments
The analytical procedures used by the Environmental Division have been developed from established internationally recognized procedures such as those published by the USEPA, APHA, AS and NEPM. In house
developed procedures are employed in the absence of documented standards or by client request.
Where moisture determination has been performed, results are reported on a dry weight basis.
Where a reported less than (<) result is higher than the LOR, this may be due to primary sample extract/digestate dilution and/or insufficient sample for analysis. Where the LOR of a reported result differs from standard LOR, this may be due to high moisture c
Key : Anonymous = Refers to samples which are not specifically part of this work order but formed part of the QC process lot
CAS Number = CAS registry number from database maintained by Chemical Abstracts Services. The Chemical Abstracts Service is a division of the American Chemical Society.
LOR = Limit of reporting
RPD = Relative Percentage Difference
# = Indicates failed QC
Laboratory Duplicate (DUP) Report
The quality control term Laboratory Duplicate refers to a randomly selected intralaboratory split. Laboratory duplicates provide information regarding method precision and sample heterogeneity. The permitted ranges
for the Relative Percent Deviation (RPD) of Laboratory Duplicates are specified in ALS Method QWI -EN/38 and are dependent on the magnitude of results in comparison to the level of reporting: Result < 10 times LOR:
No Limit; Result between 10 and 20 times LOR: 0% - 50%; Result > 20 times LOR: 0% - 20%.
Sub-Matrix: SOIL Laboratory Duplicate (DUP) Report
Laboratory sample ID Client sample ID Method: Compound CAS Number LOR Unit Original Result Duplicate Result RPD (%) Recovery Limits (%)
EA055: Moisture Content (Dried @ 105-110°C) (QC Lot: 1157905)
EM1713710-008 Anonymous EA055: Moisture Content ---- 1 % 6.9 6.7 2.57 No Limit
EM1713720-007 Anonymous EA055: Moisture Content ---- 1 % 11.2 10.8 3.39 0% - 50%
EP080/071: Total Petroleum Hydrocarbons (QC Lot: 1157872)
EM1713719-001 Anonymous EP080: C6 - C9 Fraction ---- 10 mg/kg <10 <10 0.00 No Limit
EM1713728-008 Anonymous EP080: C6 - C9 Fraction ---- 10 mg/kg <10 <10 0.00 No Limit
EP080/071: Total Petroleum Hydrocarbons (QC Lot: 1158156)
EM1713682-001 Anonymous EP071: C15 - C28 Fraction ---- 100 mg/kg <100 <100 0.00 No Limit
EP071: C29 - C36 Fraction ---- 100 mg/kg <100 <100 0.00 No Limit
EP071: C10 - C14 Fraction ---- 50 mg/kg <50 <50 0.00 No Limit
EP071: C10 - C36 Fraction (sum) ---- 50 mg/kg <50 <50 0.00 No Limit
EM1713719-001 Anonymous EP071: C15 - C28 Fraction ---- 100 mg/kg <100 <100 0.00 No Limit
EP071: C29 - C36 Fraction ---- 100 mg/kg 130 140 9.17 No Limit
EP071: C10 - C14 Fraction ---- 50 mg/kg <50 <50 0.00 No Limit
EP071: C10 - C36 Fraction (sum) ---- 50 mg/kg 130 140 7.41 No Limit
EP080/071: Total Recoverable Hydrocarbons - NEPM 2013 Fractions (QC Lot: 1157872)
EM1713719-001 Anonymous EP080: C6 - C10 Fraction C6_C10 10 mg/kg <10 <10 0.00 No Limit
EM1713728-008 Anonymous EP080: C6 - C10 Fraction C6_C10 10 mg/kg <10 <10 0.00 No Limit
EP080/071: Total Recoverable Hydrocarbons - NEPM 2013 Fractions (QC Lot: 1158156)
EM1713682-001 Anonymous EP071: >C16 - C34 Fraction ---- 100 mg/kg <100 <100 0.00 No Limit
EP071: >C34 - C40 Fraction ---- 100 mg/kg <100 <100 0.00 No Limit
EP071: >C10 - C16 Fraction ---- 50 mg/kg <50 <50 0.00 No Limit
EP071: >C10 - C40 Fraction (sum) ---- 50 mg/kg <50 <50 0.00 No Limit
EM1713719-001 Anonymous EP071: >C16 - C34 Fraction ---- 100 mg/kg 170 180 8.69 No Limit
EP071: >C34 - C40 Fraction ---- 100 mg/kg 110 130 15.4 No Limit
PLANNING EXHIBITED
DOCUMENTS
Ref. No: DA 0154/2018
Date
advertised: 18/04/2018
Planning Administration
Page
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
: 3 of 5
reproduce the document in their web browser for the sole purpose of viewing the
Sub-Matrix: SOIL Method Blank (MB) Laboratory Control Spike (LCS) Report
Report Spike Spike Recovery (%) Recovery Limits (%)
Method: Compound CAS Number LOR Unit Result Concentration LCS Low High
True
Planning Administration
This document is subject to copyright and is protected by law. In displaying this
document on its website the Council grants website users a non-exclusive licence to
reproduce the document in their web browser for the sole purpose of viewing the
content. The Council reserves all other rights. Documents displayed on the Council's
website are intended for public perusal only and should not be reproduced
without the consent of the copyright owner.
Environmental
QA/QC Compliance Assessment to assist with Quality Review
Work Order : EM1713722 Page : 1 of 4
Client : ENVIRONMENTAL SERVICE AND DESIGN PTY LTD Laboratory : Environmental Division Melbourne
Contact : MR ROD COOPER Telephone : +61-3-8549 9630
Project : 5961 Date Samples Received : 06-Oct-2017
Site : 25 York Street Issue Date : 10-Oct-2017
Sampler : RC No. of samples received :3
Order number : ---- No. of samples analysed :3
This report is automatically generated by the ALS LIMS through interpretation of the ALS Quality Control Report and several Quality Assurance parameters measured by ALS. This automated
reporting highlights any non-conformances, facilitates faster and more accurate data validation and is designed to assist internal expert and external Auditor review. Many components of this
report contribute to the overall DQO assessment and reporting for guideline compliance.
Brief method summaries and references are also provided to assist in traceability.
Summary of Outliers
Outliers : Quality Control Samples
This report highlights outliers flagged in the Quality Control (QC) Report.
l NO Method Blank value outliers occur.
l NO Duplicate outliers occur.
l NO Laboratory Control outliers occur.
l NO Matrix Spike outliers occur.
l For all regular sample matrices, NO surrogate recovery outliers occur.
Document Status