CALCULATION SHEET

LOCATION : MOJOMANIS BRIDGE


NAME OF STRUCTURE : Pavement (4,1/30, 4.1/31, 4.1/32, 4.1/33)

No.BOQ Calculation Unit Sket Drawing

PLAN RIGHT SIDE

PLAN LEFT SIDE

Page 1 of 5
No.BOQ Calculation Unit Sket Drawing
SECTION

Page 2 of 5
No.BOQ Calculation Unit Sket Drawing
4.1/30 Sod Facing
- Left Side
A = p x l x n
= 168.800 x 0.500 x 2.000
= 168.800

- Right Side
A = p x l x n
= 155.250 x 0.500 x 2.000
= 155.250

A total = 324.050 m2

4.1/31 Subbase Course, t = 300 mm (Compacted)


- Left Side
V = A x t
= 396.822 x 0.300
= 119.047
- Right Side
V = A x t
= 339.742 x 0.300
= 101.923

V total = 220.969 m3

4.1/32 Base Course, t = 150 mm (Compacted)


- Left Side
V = A x t
= 396.822 x 0.150
= 59.523
- Right Side
V = A x t
= 339.742 x 0.150
= 50.961

V total = 110.485 m3

4.1/33 Surface Course, t = 50 mm (Compacted)


- Left Side
A = 396.822

- Right Side
= 339.742

- Bridge
= p x b

= 126.200 x 4.200

Page 3 of 5
No.BOQ Calculation Unit Sket Drawing
= 530.040

V total = 1,266.604 m2

Summary
4.1/30 Sod Facing 324.050 m2
4.1/31 Subbase Course, t = 300 mm (Compacted) 220.969 m3
4.1/32 Base Course, t = 150 mm (Compacted) 110.485 m3
4.1/33 Surface Course, t = 50 mm (Compacted) 1,266.604 m2

Engineer Consultant Contractor

( ) ( ) ( )

Page 4 of 5
Summary Pavement

No.BOQ Description Unit Q'ty

4.1/31 Subbase Course, t = 300 mm (Compacted) m3 220.969


4.1/32 Base Course, t = 150 mm (Compacted) m3 110.485
4.1/33 Surface Course, t = 50 mm (Compacted) m2 1266.604