Anda di halaman 1dari 2

PLANILLA DE METRADOS

PROYECTO
MEJORAMIENTO Y REEMPLAZO DE LA RED COLECTORA Y AMPLIACION DE LA RED DE AGUA POTABLE DEL TRAMO JR. HUASCAR Y CARRETERA CENTRAL, EN EL DISTRITO
DE JAUJA -PROVINCIA DE JAUJA -REGION JUNIN

PRESUPUESTOSISTEMA DE ALCANTARILLADO
SUBPRESUPUESTO :
CLIENTE MUNICIPALIDAD PROVINCIAL DE JAUJA
Ele
m. Nº de
ITEM DESCRIPCIÓN Und LARGO ANCHO ALTO PARCIAL TOTAL
Simi Veces
l.
01. RED DE COLECTORA DE ALCANTARILLADO
01.01. OBRAS PROVISIONALES
01.01.01 CARTEL DE INFORMACION DE 3.60 x 4.20 und 1.00 1.00 1.00 1.00
01.01.02 OFICINA, CASETA Y ALMACEN mes 1.00 1.00 1.00 1.00
01.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS, MATERIALES Y HER glb 1.00 1.00 1.00 1.00

01.02 OBRAS PRELIMINARES


01.02.01 TRAZO, NIVELACION Y REPLANTEO m 1.00 1,011.25 1.00 1,011.25 1,011.25
01.02.02 LIMPIEZA DE TERRENO MANUAL m 1.00 1,011.25 1.00 1,011.25 1,011.25
01.02.03 CORTE EN PAVIMENTO FLEXIBLE m 1.00 1,011.25 1.00 1,011.25 1,011.25
01.02.04 REPLANTEO FINAL DE LA OBRA PARA LINEAS REDES m 1.00 1,011.25 1.00 1,011.25 1,011.25
01.02.05 CERCO DE MALLA HDP DE 1M. ALTURA PARA LIMITE SEGURIDAD OBRA m 1.00 1,011.25 2.00 2,022.50 2,022.50

01.03 MOVIMIENTO DE TIERRAS


01.03.01 EXCAVACION DE ZANJA EN TERRENO NORMAL C/MAQ. M3 1,371.39
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 01 H= 1.20 A BZ. 02 H=1.8 m 1.00 50.00 0.80 1.53 61.20
P/TUB.T NORMAL DN 200 TRAMO DE BZ.02 15 H=1.86 A BZ.03 16 H m 1.00 40.88 0.80 1.99 65.08
P/TUB.T NORMAL DN 200 TRAMO DE BZ.03 H=2.12 A BZ.04 H=2.20 m 1.00 12.32 0.80 2.16 21.29
P/TUB.T NORMAL DN 200 TRAMO DE BZ.04 H=2.20 A BZ.05 H=2.57 m 1.00 29.53 0.80 2.38 56.23
P/TUB.T NORMAL DN 200 TRAMO DE BZ.05 H=2.57 A BZ.06 H=3.16 m 1.00 29.50 0.80 2.86 67.50
P/TUB.T NORMAL DN 200 TRAMO DE BZ.06 H=3.16A BZ.07 H=2.85 m 1.00 40.33 0.80 3.00 96.79
P/TUB.T NORMAL DN 200 TRAMO DE BZ.07 H=2.85 A BZ.08 H=1.5 m 1.00 40.38 0.80 2.17 70.10
P/TUB.T NORMAL DN 200 TRAMO DE BZ.08 H=21.5 A BZ.13 H=1.5 m 1.00 198.64 0.80 1.50 238.37
P/TUB.T NORMAL DN 200 TRAMO DE BZ.12 H=1.54 A BZ.EX 27 H=1 m 1.00 76.56 0.80 1.54 94.32
P/TUB.T NORMAL DN 200 TRAMO DE BZ.14 H=1.50 A BZ.17 H=1.50 m 1.00 198.64 0.80 1.50 238.37
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 17 H=1.55 A BZ.EX 18 m 1.00 53.78 0.80 1.50 64.54
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 18 H=1.50 A BZ.EX 19 m 1.00 58.65 0.80 1.62 76.01
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 19 H=1.64 A BZ. 20 H=1 m 1.00 59.66 0.80 1.62 77.32
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 20 H=1.50 A BZ. 21 H=1.50 m 1.00 58.19 0.80 1.50 69.83
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 21 H=1.64 A BZ. 22 H=1.41 m 1.00 58.19 0.80 1.45 67.50
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 22 H=1.41 A BZ EX. 22 H=1 m 1.00 6.00 0.80 1.45 6.96

01.03.02 REFINE Y NIVELACION DE ZANJA NORMAL M 1,011.25


P/TUB.T NORMAL DN 200 TRAMO DE BZ. 01 H= 1.20 A BZ. 02 H=1.8 m 1.00 50.00 50.00
P/TUB.T NORMAL DN 200 TRAMO DE BZ.02 15 H=1.86 A BZ.03 16 H m 1.00 40.88 40.88
P/TUB.T NORMAL DN 200 TRAMO DE BZ.03 H=2.12 A BZ.04 H=2.20 m 1.00 12.32 12.32
P/TUB.T NORMAL DN 200 TRAMO DE BZ.04 H=2.20 A BZ.05 H=2.57 m 1.00 29.53 29.53
P/TUB.T NORMAL DN 200 TRAMO DE BZ.05 H=2.57 A BZ.06 H=3.16 m 1.00 29.50 29.50
P/TUB.T NORMAL DN 200 TRAMO DE BZ.06 H=3.16A BZ.07 H=2.85 m 1.00 40.33 40.33
P/TUB.T NORMAL DN 200 TRAMO DE BZ.07 H=2.85 A BZ.08 H=1.5 m 1.00 40.38 40.38
P/TUB.T NORMAL DN 200 TRAMO DE BZ.08 H=21.5 A BZ.13 H=1.5 m 1.00 198.64 198.64
P/TUB.T NORMAL DN 200 TRAMO DE BZ.12 H=1.54 A BZ.EX 27 H=1 m 1.00 76.56 76.56
P/TUB.T NORMAL DN 200 TRAMO DE BZ.14 H=1.50 A BZ.17 H=1.50 m 1.00 198.64 198.64
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 17 H=1.55 A BZ.EX 18 m 1.00 53.78 53.78
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 18 H=1.50 A BZ.EX 19 m 1.00 58.65 58.65
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 19 H=1.64 A BZ. 20 H=1 m 1.00 59.66 59.66
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 20 H=1.50 A BZ. 21 H=1.50 m 1.00 58.19 58.19
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 21 H=1.64 A BZ. 22 H=1.41 m 1.00 58.19 58.19
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 22 H=1.41 A BZ EX. 22 H=1 m 1.00 6.00 6.00

01.03.03 CAMA DE TIERRA ZARANDEADA E=0.10M. ZANJA P/TUBO CON MATERI M3 242.70
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 01 H= 1.20 A BZ. 02 H=1.8 m 1.00 50.00 0.80 0.30 12.00
P/TUB.T NORMAL DN 200 TRAMO DE BZ.02 15 H=1.86 A BZ.03 16 H m 1.00 40.88 0.80 0.30 9.81
P/TUB.T NORMAL DN 200 TRAMO DE BZ.03 H=2.12 A BZ.04 H=2.20 m 1.00 12.32 0.80 0.30 2.96
P/TUB.T NORMAL DN 200 TRAMO DE BZ.04 H=2.20 A BZ.05 H=2.57 m 1.00 29.53 0.80 0.30 7.09
P/TUB.T NORMAL DN 200 TRAMO DE BZ.05 H=2.57 A BZ.06 H=3.16 m 1.00 29.50 0.80 0.30 7.08
P/TUB.T NORMAL DN 200 TRAMO DE BZ.06 H=3.16A BZ.07 H=2.85 m 1.00 40.33 0.80 0.30 9.68
P/TUB.T NORMAL DN 200 TRAMO DE BZ.07 H=2.85 A BZ.08 H=1.5 m 1.00 40.38 0.80 0.30 9.69
P/TUB.T NORMAL DN 200 TRAMO DE BZ.08 H=21.5 A BZ.13 H=1.5 m 1.00 198.64 0.80 0.30 47.67
P/TUB.T NORMAL DN 200 TRAMO DE BZ.12 H=1.54 A BZ.EX 27 H=1 m 1.00 76.56 0.80 0.30 18.37
P/TUB.T NORMAL DN 200 TRAMO DE BZ.14 H=1.50 A BZ.17 H=1.50 m 1.00 198.64 0.80 0.30 47.67
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 17 H=1.55 A BZ.EX 18 m 1.00 53.78 0.80 0.30 12.91
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 18 H=1.50 A BZ.EX 19 m 1.00 58.65 0.80 0.30 14.08
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 19 H=1.64 A BZ. 20 H=1 m 1.00 59.66 0.80 0.30 14.32
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 20 H=1.50 A BZ. 21 H=1.50 m 1.00 58.19 0.80 0.30 13.97
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 21 H=1.64 A BZ. 22 H=1.41 m 1.00 58.19 0.80 0.30 13.97
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 22 H=1.41 A BZ EX. 22 H=1 m 1.00 6.00 0.80 0.30 1.44

01.03.04 RELLENO COMP. ZANJA (PULSO) T-NORMAL- DN 200 M3 1,128.69


P/TUB.T NORMAL DN 200 TRAMO DE BZ. 01 H= 1.20 A BZ. 02 H=1.8 m 1.00 50.00 0.80 1.23 49.20
P/TUB.T NORMAL DN 200 TRAMO DE BZ.02 15 H=1.86 A BZ.03 16 H m 1.00 40.88 0.80 1.69 55.27
P/TUB.T NORMAL DN 200 TRAMO DE BZ.03 H=2.12 A BZ.04 H=2.20 m 1.00 12.32 0.80 1.86 18.33
P/TUB.T NORMAL DN 200 TRAMO DE BZ.04 H=2.20 A BZ.05 H=2.57 m 1.00 29.53 0.80 2.08 49.14
P/TUB.T NORMAL DN 200 TRAMO DE BZ.05 H=2.57 A BZ.06 H=3.16 m 1.00 29.50 0.80 2.56 60.42
P/TUB.T NORMAL DN 200 TRAMO DE BZ.06 H=3.16A BZ.07 H=2.85 m 1.00 40.33 0.80 2.70 87.11
P/TUB.T NORMAL DN 200 TRAMO DE BZ.07 H=2.85 A BZ.08 H=1.5 m 1.00 40.38 0.80 1.87 60.41
P/TUB.T NORMAL DN 200 TRAMO DE BZ.08 H=21.5 A BZ.13 H=1.5 m 1.00 198.64 0.80 1.20 190.69
P/TUB.T NORMAL DN 200 TRAMO DE BZ.12 H=1.54 A BZ.EX 27 H=1 m 1.00 76.56 0.80 1.24 75.95
P/TUB.T NORMAL DN 200 TRAMO DE BZ.14 H=1.50 A BZ.17 H=1.50 m 1.00 198.64 0.80 1.20 190.69
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 17 H=1.55 A BZ.EX 18 m 1.00 53.78 0.80 1.20 51.63
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 18 H=1.50 A BZ.EX 19 m 1.00 58.65 0.80 1.32 61.93
P/TUB.T NORMAL DN 200 TRAMO DE BZ.EX 19 H=1.64 A BZ. 20 H=1 m 1.00 59.66 0.80 1.32 63.00
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 20 H=1.50 A BZ. 21 H=1.50 m 1.00 58.19 0.80 1.20 55.86
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 21 H=1.64 A BZ. 22 H=1.41 m 1.00 58.19 0.80 1.15 53.53
P/TUB.T NORMAL DN 200 TRAMO DE BZ. 22 H=1.41 A BZ EX. 22 H=1 m 1.00 6.00 0.80 1.15 5.52

01.03.05 ELIMINACION DE MATERIAL EXCEDENTE M3 242.70


02.02.04.01 ELIMINACION DE MATERIAL TOTAL M3 1.00 242.70 242.70

01.04 SUMINISTRO E INSTALACION DE TUBERIA PVC UF ISO 4435 1,011.25


01.04.01 TUBERIA PVC-U UF NTP ISO 4435 SERIE 25 DN 200 INC. ANILLO + 2% m 1.00 1,011.25 1.00 1,011.25

01.05 PRUEBA HODRAULICA DE TUBERIA PVC UF ISO 4435 1,011.25


01.05.01 INSTALACION DE TUBERIA DE PVC P/DESAGUE DN 200 INC. PRUEBA HI m 1.00 1,011.25 1.00 1,011.25

01.06 CONSTRUCCION DE BUZONES TIPO I


01.06.01 OBRAS DE CONCRETO SIMPLE
01.06.01.01 CONCRETO DE F'c=100 KG/CM2 PARA SOLADO DE BUZONES M2 1.00 1.77 9.00 15.93 15.93
01.06.01.02 ENCOFRADO Y DESENCOFRADO EN DADOS DE APOYO M2 1.00 0.30 0.30 9.00 0.81 0.81
01.06.01.03 CONCRETO EN DADOS DE APOYO F'c=210 Kg/Cm2 M3 1.00 0.30 0.30 45.00 4.05 4.05

01.06.02 BUZONES
01.06.02.01 BUZON TIPO I DE CONCRETO F'c = 210 Kg/ cm2 H=1.20-1.50m D=1.20m UND 1.00 15.00 15.00 15.00

01.07 CONEXIONES DOMICILIARIAS DE ALCANTARILLADO


01.07.01 EXCAVACION DE ZANJA EN TERRENO NORMAL C/MAQ. M3 1.00 6.73 0.80 1.50 80.00 646.08 646.08
01.07.02 REFINE Y NIVELACION DE ZANJA NORMAL M 1.00 6.73 80.00 538.40 538.40
01.07.03 CAMA DE TIERRA ZARANDEADA E=0.10M. ZANJA P/TUBO CON MATERIAL M3 1.00 6.73 0.80 0.10 80.00 43.07 43.07
01.07.04 RELLENO COMP. ZANJA (PULSO) T-NORMAL- DN 200 M3 1.00 6.73 0.80 1.40 80.00 603.01 603.01
01.07.05 ELIMINACION DE MATERIAL EXCEDENTE M3 1.00 43.07 43.07 43.07
01.07.06 INSTALACION DE TUBERIA PVC D= 6" PARA CONEXIONES DOMICILIAR M 1.00 6.73 80.00 538.40 538.40
01.07.07 CAJA DE REGISTRO PARA INSTA. DOMICILIARIAS DE DESAGUE C/TAPA(I UND 1.00 80.00 80.00 80.00
01.08 VARIOS
01.08.01 EMPALME DE TUBERIAS DN 200 MM A BUZON EXISTENTE EN SERVICIO und 1.00 5.00 1.00 5.00 5.00
01.08.02 PRUEBA DE COMPACTACION DE SUELOS (PROCTOR MODIF. DENSIDAD und 1.00 9.00 1.00 9.00 9.00
01.08.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) und 1.00 9.00 1.00 9.00 9.00
01.08.04 CRUCE ESPECIAL EN CANAL DE AGUA DE RIEGO P/TUBERIA DN 200MM ( und 1.00 1.00 1.00 1.00 1.00
01.08.05 LIMPIEZA FINAL DE OBRA glo 1.00 1011.25 1.00 1,011.25 1011.25