Develop the cost estimate of the driven precast reinforced concrete pile 150mm x 150mm x
6.00m based on the following data:
2. Tutorial-Cutting of Pile
Develop the cost estimate for cut off top of piles to the required levels with the following
parameter given as below :
Labour cost
(1 General Worker) = RM 75.00
Total cost for demolishing pile head = RM 120.00
Labour cost
1 skill worker/day = RM 120.00
Labour cost
2 General worker = 2 x RM 75.00 = RM 150.00
Total cost for loading/day = RM 550.00
Labour cost
2 Nos of General workers = 2 x RM75.00 = RM150.00
Total cost/ day = RM 600.00
Cost/Nos. = 23.13