Pelat Lantai Tipe S2 AB

Data Perencanaan:
F'c = 24 Mpa
Fy = 400 Mpa
Fu = 546 Mpa
�_1 = 0.85
Lx = 2000 mm
= 2 mm
Ly = 4700 mm
= 4.7 m
h = 135 mm
= 0.135 m

Pembebanan pelat
a. Beban Mati (DL)
- Berat sendiri pelat t = 13 cm = 0.135 * 2400 = 324 kg/m2
- Berat spesi t = 2 cm = 2 * 21 = 42 kg/m2
- Berak keramik t = 1 cm = 1 * 24 = 24 kg/m2
- Berat rangka plafond = 1 * 7 = 7 kg/m2
- Berat plafond = 1 * 11 = 11 kg/m2
= 408 kg/m2

b. Beban Hidup (LL)


- Gedung Perkantoran
Koridor di atas lantai pertama = 3.83 kN/m2 = 383 kg/m2

c. BebanUltimate
- q pelat = 1.2 DL + 1.6 LL
= 1.2 408 + 1.6 383
= 1102.4 kg/m2
= 11.024 kN/m2
Menghitung ρ minimum dan ρ maksimum
a. ρ minimum = 1.4/ Fy
= 0.0035
b. ρ maksimum = 75% *ρ beton

�_𝑏𝑒𝑡𝑜𝑛 = (0.85.β_1. 〖𝑓′〗 _𝑐)/𝑓_𝑦 ∗600/(600+𝑓_𝑦 )

= 0.072
ρ maksimum = 75% *ρ beton
= 0.054

Perhitungan Momen
a. Tipe pelat (asumsi perletakan jepit penuh pada keempat sisi)
Ly 4700
= = 2.350 > 2 Pelat 1 arah
Lx 2000

b. Momen yang terjadi (M. Perlu)

Mlx = 1/14∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
= 3.150 kN.m = 3149714.29 N.mm

Mtx = 1/12∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
= 3.675 kN.m = 3674666.67 N.mm

c. Momen nominal (M. Perlu)


Mnlx = Mlx/0.8
= 3.937 kN.m = 3937143 N.mm
Mntx = Mntx/0.8
= 4.593 kN.m = 4593333 N.mm

Perhitungan penulangan
Perhitungan tulangan lapangan dan tumpuan :

Diasumsikan menggunakan tulangan D10 = 10 mm


Selimut beton diasumsikan dengan tebal s = 20 mm
dx = Tebal plat - Selimut beton - (0,5 x diameter tulangan)
= 135 - 20 - 0.5 x 10
= 110 mm
dy = Tebal plat - Selimut beton - diameter tulangan - (0,5 x diameter tulangan)
= 135 - 20 - 10 - 0.5 x 10
= 100 mm

Tulangan lapangan arah X :


Mnlx = 3937143 N.mm
Rn = Mnlx 3937143 3937143
= = = 0.325
b x dx2 1000 x 110 2 12100000
m = fy 400
= = 19.61
0.85 x fc' 0.85 x 24

� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.325 x 19.61
1 - 1 -
19.61 400
= 0.00082
Cek rasio penulangan :

�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.00082 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.
Menentukan tulangan yang terpakai :
As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Menggunakan tulangan D 10

As D10 = 1/4 𝜋𝑑^2 = 78.57 mm2

n = As perlu 385.00
= = 5 buah
As D10 78.57
Jarak = 1000
= 200 mm
5
Jarak maks = 3.h = 405.00 mm

Kontrol

𝐽𝑎𝑟𝑎𝑘
200 ≤ < 𝐽𝑎𝑟𝑎𝑘405
𝑚𝑎𝑘� OK
As pakai = As D10*n = 392.86 mm2

Kontrol

〖��〗
385.00_𝑝𝑒𝑟𝑙𝑢< ≤ 392.86
〖 � OK
�〗 _𝑝𝑎𝑘𝑎𝑖
Jadi digunakan tulangan D10 - 400

Tulangan tumpuan arah X :


Mntx = 4593333 N.mm
Mn 4593333 4593333
Rn = = = = 0.380
b x dx2 1000 x 110 2 12100000
fy 400
m = = = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.380 x 19.61
1 - 1 -
19.61 400
= 0.0010
Cek rasio penulangan :

�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.0010 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Diterima dari tulangan lapangan D10 - 400
= As pakai / 2
= 196.43 mm2
As sisa = As perlu - Diterima dari tulangan lapangan
= 188.57 mm2

Menggunakan tulangan D 10

As D10 = 1/4 𝜋𝑑^2 = 78.57 mm2

n = As sisa 188.57
= = 3 buah
As D10 78.57
Jarak = 1000
= 333 mm
3
Jarak maks = 3.h = 405.00 mm

Kontrol

𝐽𝑎𝑟𝑎𝑘
333 ≤ < 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
405.00 OK
As pakai = As D10*n = 235.71 mm

Kontrol

〖��〗 _𝑝𝑒𝑟𝑙𝑢 <


188.57 235.71 OK
≤ 〖 ��〗 _𝑝𝑎𝑘𝑎𝑖
Jadi digunakan tulangan extra D10 - 333

Tulangan susut :
As susut = ρ.b.h = 0.002 * 1000 * 135
= 270 mm 2

Menggunakan tulangan D 10

As D10 = 1/4 𝜋𝑑^2 = 78.57 mm2

n = As susut 270.00
= = 4 buah
As D10 78.57
Jarak = 1000
= 250 mm
4
Jarak maks = 5.h = 675.00 mm (SNI 2847:2013 Ps. 7.12.2.1)

Kontrol

𝐽𝑎𝑟𝑎𝑘
250 ≤ < 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
675.00 OK
As pakai = As D10*n = 314.29 mm

Kontrol

〖��〗270
_𝑝𝑒𝑟𝑙𝑢 < 314.286 OK
≤ 〖 ��〗 _𝑝𝑎𝑘𝑎𝑖
Jadi digunakan tulangan D10 - 250

Rekapitulasi penulangan plat lantai :


Tulangan lapangan arah X = D10 - 400
Tulangan tumpuan arah X = D10 - 333
Tulangan susut = D10 - 250
Pelat Lantai Tipe S2 C
Data Perencanaan:
F'c = 24 Mpa
Fy = 400 Mpa
Fu = 546 Mpa
�_1 = 0.85
Lx = 1500 mm
= 1.5 mm
Ly = 4700 mm
= 4.7 m
h = 135 mm
= 0.135 m

Pembebanan pelat
a. Beban Mati (DL)
- Berat sendiri pelat t = 13 cm = 0.135 * 2400 = 324 kg/m2
- Berat spesi t = 2 cm = 2 * 21 = 42 kg/m2
- Berak keramik t = 1 cm = 1 * 24 = 24 kg/m2
- Berat rangka plafond = 1 * 7 = 7 kg/m2
- Berat plafond = 1 * 11 = 11 kg/m2
= 408 kg/m2

b. Beban Hidup (LL)


- Gedung Perkantoran
Kantilever = 4.79 kN/m2 = 479 kg/m2

c. BebanUltimate
- q pelat = 1.2 DL + 1.6 LL
= 1.2 408 + 1.6 479
= 1256 kg/m2
= 12.56 kN/m2
Menghitung ρ minimum dan ρ maksimum
a. ρ minimum = 1.4/ Fy
= 0.0035
b. ρ maksimum = 75% *ρ beton
�_𝑏𝑒𝑡𝑜𝑛 = (0.85.β_1. 〖𝑓′〗 _𝑐)/𝑓_𝑦 ∗600/(600+𝑓_𝑦 )

= 0.072
ρ maksimum = 75% *ρ beton
= 0.054

Perhitungan Momen
a. Tipe pelat (asumsi perletakan jepit penuh pada keempat sisi)
Ly 4700
= = 3.133 > 2 Pelat 1 arah
Lx 1500

b. Momen yang terjadi (M. Perlu)


1/14∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mlx =

= 2.019 kN.m = 2018571.43 N.mm


1/12∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mtx =

= 2.355 kN.m = 2355000 N.mm

c. Momen nominal (M. Perlu)


Mnlx = Mlx/0.8
= 2.523 kN.m = 2523214 N.mm
Mntx = Mntx/0.8
= 2.944 kN.m = 2943750 N.mm

Perhitungan penulangan
Perhitungan tulangan lapangan dan tumpuan :

Diasumsikan menggunakan tulangan D10 = 10 mm


Selimut beton diasumsikan dengan tebal s = 20 mm
dx = Tebal plat - Selimut beton - (0,5 x diameter tulangan)
= 135 - 20 - 0.5 x 10
= 110 mm
dy = Tebal plat - Selimut beton - diameter tulangan - (0,5 x diameter tulangan)
= 135 - 20 - 10 - 0.5 x 10
= 100 mm

Tulangan lapangan arah X :


Mnlx = 2523214 N.mm
Rn = Mnlx 2523214 2523214
= = = 0.209
b x dx2 1000 x 110 2 12100000
m = fy 400
= = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.209 x 19.61
1 - 1 -
19.61 400
= 0.00052
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.00052 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As perlu 385.00
= = 5 buah
As D10 78.57
Jarak = 1000
= 200 mm
5
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
200 < 405 OK
As pakai = As D10*n = 392.86 mm2

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢 ≤ 〖 �
�〗 _𝑝𝑎𝑘𝑎𝑖 <
385.00 392.86 OK
Jadi digunakan tulangan D10 - 400

Tulangan tumpuan arah X :


Mntx = 2943750 N.mm
Mn 2943750 2943750
Rn = = = = 0.243
b x dx2 1000 x 110 2 12100000
fy 400
m = = = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.243 x 19.61
1 - 1 -
19.61 400
= 0.0006
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.0006 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Diterima dari tulangan lapangan D10 - 400
= As pakai / 2
= 196.43 mm2
As sisa = As perlu - Diterima dari tulangan lapangan
= 188.57 mm2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As sisa 188.57
= = 3 buah
As D10 78.57
Jarak = 1000
= 333 mm
3
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
333 < 405.00 OK
As pakai = As D10*n = 235.71 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖188.57
��〗 _𝑝𝑎𝑘𝑎𝑖
< 235.71 OK
Jadi digunakan tulangan extra D10 - 333

Tulangan susut :
As susut = ρ.b.h = 0.002 * 1000 * 135
= 270 mm 2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As susut 270.00
= = 4 buah
As D10 78.57
Jarak = 1000
= 250 mm
4
Jarak maks = 5.h = 675.00 mm (SNI 2847:2013 Ps. 7.12.2.1)

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
250 < 675.00 OK
As pakai = As D10*n = 314.29 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖 270��〗 _𝑝𝑎𝑘𝑎𝑖
< 314.286 OK
Jadi digunakan tulangan D10 - 250

Rekapitulasi penulangan plat lantai :


Tulangan lapangan arah X = D10 - 400
Tulangan tumpuan arah X = D10 - 333
Tulangan susut = D10 - 250
Pelat Lantai Tipe S2 AA
Data Perencanaan:
F'c = 24 Mpa
Fy = 400 Mpa
Fu = 546 Mpa
�_1 = 0.85
Lx = 2000 mm
= 2 mm
Ly = 4700 mm
= 4.7 m
h = 135 mm
= 0.135 m

Pembebanan pelat
a. Beban Mati (DL)
- Berat sendiri pelat t = 13 cm = 0.135 * 2400 = 324 kg/m2
- Berat spesi t = 2 cm = 2 * 21 = 42 kg/m2
- Berak keramik t = 1 cm = 1 * 24 = 24 kg/m2
- Berat rangka plafond = 1 * 7 = 7 kg/m2
- Berat plafond = 1 * 11 = 11 kg/m2
= 408 kg/m2

b. Beban Hidup (LL)


- Gedung Perkantoran
Ruang Kerja/Toilet = 2.40 kN/m2 = 240 kg/m2

c. BebanUltimate
- q pelat = 1.2 DL + 1.6 LL
= 1.2 408 + 1.6 240
= 873.6 kg/m2
= 8.736 kN/m2
Menghitung ρ minimum dan ρ maksimum
a. ρ minimum = 1.4/ Fy
= 0.0035
b. ρ maksimum = 75% *ρ beton
�_𝑏𝑒𝑡𝑜𝑛 = (0.85.β_1. 〖𝑓′〗 _𝑐)/𝑓_𝑦 ∗600/(600+𝑓_𝑦 )

= 0.072
ρ maksimum = 75% *ρ beton
= 0.054

Perhitungan Momen
a. Tipe pelat (asumsi perletakan jepit penuh pada keempat sisi)
Ly 4700
= = 2.350 > 2 Pelat 1 arah
Lx 2000

b. Momen yang terjadi (M. Perlu)


1/14∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mlx =

= 2.496 kN.m = 2496000 N.mm


1/12∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mtx =

= 2.912 kN.m = 2912000 N.mm

c. Momen nominal (M. Perlu)


Mnlx = Mlx/0.8
= 3.120 kN.m = 3120000 N.mm
Mntx = Mntx/0.8
= 3.640 kN.m = 3640000 N.mm

Perhitungan penulangan
Perhitungan tulangan lapangan dan tumpuan :

Diasumsikan menggunakan tulangan D10 = 10 mm


Selimut beton diasumsikan dengan tebal s = 20 mm
dx = Tebal plat - Selimut beton - (0,5 x diameter tulangan)
= 135 - 20 - 0.5 x 10
= 110 mm
dy = Tebal plat - Selimut beton - diameter tulangan - (0,5 x diameter tulangan)
= 135 - 20 - 10 - 0.5 x 10
= 100 mm

Tulangan lapangan arah X :


Mnlx = 3120000 N.mm
Rn = Mnlx 3120000 3120000
= = = 0.258
b x dx2 1000 x 110 2 12100000
m = fy 400
= = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.258 x 19.61
1 - 1 -
19.61 400
= 0.00065
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.00065 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As perlu 385.00
= = 5 buah
As D10 78.57
Jarak = 1000
= 200 mm
5
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
200 < 405 OK
As pakai = As D10*n = 392.86 mm2

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢 ≤ 〖 �
�〗 _𝑝𝑎𝑘𝑎𝑖 <
385.00 392.86 OK
Jadi digunakan tulangan D10 - 400

Tulangan tumpuan arah X :


Mntx = 3640000 N.mm
Mn 3640000 3640000
Rn = = = = 0.301
b x dx2 1000 x 110 2 12100000
fy 400
m = = = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.301 x 19.61
1 - 1 -
19.61 400
= 0.0008
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.0008 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Diterima dari tulangan lapangan D10 - 400
= As pakai / 2
= 196.43 mm2
As sisa = As perlu - Diterima dari tulangan lapangan
= 188.57 mm2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As sisa 188.57
= = 3 buah
As D10 78.57
Jarak = 1000
= 333 mm
3
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
333 < 405.00 OK
As pakai = As D10*n = 235.71 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖188.57
��〗 _𝑝𝑎𝑘𝑎𝑖
< 235.71 OK
Jadi digunakan tulangan extra D10 - 333

Tulangan susut :
As susut = ρ.b.h = 0.002 * 1000 * 135
= 270 mm 2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As susut 270.00
= = 4 buah
As D10 78.57
Jarak = 1000
= 250 mm
4
Jarak maks = 5.h = 675.00 mm (SNI 2847:2013 Ps. 7.12.2.1)

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
250 < 675.00 OK
As pakai = As D10*n = 314.29 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖 270��〗 _𝑝𝑎𝑘𝑎𝑖
< 314.286 OK
Jadi digunakan tulangan D10 - 250

Rekapitulasi penulangan plat lantai :


Tulangan lapangan arah X = D10 - 400
Tulangan tumpuan arah X = D10 - 333
Tulangan susut = D10 - 250
Pelat Lantai Tipe S2 DB
Data Perencanaan:
F'c = 24 Mpa
Fy = 400 Mpa
Fu = 546 Mpa
�_1 = 0.85
Lx = 2000 mm
= 2 mm
Ly = 4700 mm
= 4.7 m
h = 135 mm
= 0.135 m

Pembebanan pelat
a. Beban Mati (DL)
- Berat sendiri pelat t = 13 cm = 0.135 * 2400 = 324 kg/m2
- Berat spesi t = 2 cm = 2 * 21 = 42 kg/m2
- Berak keramik t = 1 cm = 1 * 24 = 24 kg/m2
- Berat rangka plafond = 1 * 7 = 7 kg/m2
- Berat plafond = 1 * 11 = 11 kg/m2
= 408 kg/m2

b. Beban Hidup (LL)


- Gedung Perkantoran
Hall = 4.79 kN/m2 = 479 kg/m2

c. BebanUltimate
- q pelat = 1.2 DL + 1.6 LL
= 1.2 408 + 1.6 479
= 1256 kg/m2
= 12.56 kN/m2
Menghitung ρ minimum dan ρ maksimum
a. ρ minimum = 1.4/ Fy
= 0.0035
b. ρ maksimum = 75% *ρ beton
�_𝑏𝑒𝑡𝑜𝑛 = (0.85.β_1. 〖𝑓′〗 _𝑐)/𝑓_𝑦 ∗600/(600+𝑓_𝑦 )

= 0.072
ρ maksimum = 75% *ρ beton
= 0.054

Perhitungan Momen
a. Tipe pelat (asumsi perletakan jepit penuh pada keempat sisi)
Ly 4700
= = 2.350 > 2 Pelat 1 arah
Lx 2000

b. Momen yang terjadi (M. Perlu)


1/14∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mlx =

= 3.589 kN.m = 3588571.43 N.mm


1/12∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mtx =

= 4.187 kN.m = 4186666.67 N.mm

c. Momen nominal (M. Perlu)


Mnlx = Mlx/0.8
= 4.486 kN.m = 4485714 N.mm
Mntx = Mntx/0.8
= 5.233 kN.m = 5233333 N.mm

Perhitungan penulangan
Perhitungan tulangan lapangan dan tumpuan :

Diasumsikan menggunakan tulangan D10 = 10 mm


Selimut beton diasumsikan dengan tebal s = 20 mm
dx = Tebal plat - Selimut beton - (0,5 x diameter tulangan)
= 135 - 20 - 0.5 x 10
= 110 mm
dy = Tebal plat - Selimut beton - diameter tulangan - (0,5 x diameter tulangan)
= 135 - 20 - 10 - 0.5 x 10
= 100 mm

Tulangan lapangan arah X :


Mnlx = 4485714 N.mm
Rn = Mnlx 4485714 4485714
= = = 0.371
b x dx2 1000 x 110 2 12100000
m = fy 400
= = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.371 x 19.61
1 - 1 -
19.61 400
= 0.00094
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.00094 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As perlu 385.00
= = 5 buah
As D10 78.57
Jarak = 1000
= 200 mm
5
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
200 < 405 OK
As pakai = As D10*n = 392.86 mm2

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢 ≤ 〖 �
�〗 _𝑝𝑎𝑘𝑎𝑖 <
385.00 392.86 OK
Jadi digunakan tulangan D10 - 400

Tulangan tumpuan arah X :


Mntx = 5233333 N.mm
Mn 5233333 5233333
Rn = = = = 0.433
b x dx2 1000 x 110 2 12100000
fy 400
m = = = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.433 x 19.61
1 - 1 -
19.61 400
= 0.0011
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.0011 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Diterima dari tulangan lapangan D10 - 400
= As pakai / 2
= 196.43 mm2
As sisa = As perlu - Diterima dari tulangan lapangan
= 188.57 mm2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As sisa 188.57
= = 3 buah
As D10 78.57
Jarak = 1000
= 333 mm
3
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
333 < 405.00 OK
As pakai = As D10*n = 235.71 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖188.57
��〗 _𝑝𝑎𝑘𝑎𝑖
< 235.71 OK
Jadi digunakan tulangan extra D10 - 333

Tulangan susut :
As susut = ρ.b.h = 0.002 * 1000 * 135
= 270 mm 2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As susut 270.00
= = 4 buah
As D10 78.57
Jarak = 1000
= 250 mm
4
Jarak maks = 5.h = 675.00 mm (SNI 2847:2013 Ps. 7.12.2.1)

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
250 < 675.00 OK
As pakai = As D10*n = 314.29 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖 270��〗 _𝑝𝑎𝑘𝑎𝑖
< 314.286 OK
Jadi digunakan tulangan D10 - 250

Rekapitulasi penulangan plat lantai :


Tulangan lapangan arah X = D10 - 400
Tulangan tumpuan arah X = D10 - 333
Tulangan susut = D10 - 250
Pelat Lantai Tipe S2 EB
Data Perencanaan:
F'c = 24 Mpa
Fy = 400 Mpa
Fu = 546 Mpa
�_1 = 0.85
Lx = 2000 mm
= 2 mm
Ly = 4700 mm
= 4.7 m
h = 135 mm
= 0.135 m

Pembebanan pelat
a. Beban Mati (DL)
- Berat sendiri pelat t = 13 cm = 0.135 * 2400 = 324 kg/m2
- Berat spesi t = 2 cm = 2 * 21 = 42 kg/m2
- Berak keramik t = 1 cm = 1 * 24 = 24 kg/m2
- Berat rangka plafond = 1 * 7 = 7 kg/m2
- Berat plafond = 1 * 11 = 11 kg/m2
= 408 kg/m2

b. Beban Hidup (LL)


- Gedung Perkantoran
Cafe = 4.79 kN/m2 = 479 kg/m2

c. BebanUltimate
- q pelat = 1.2 DL + 1.6 LL
= 1.2 408 + 1.6 479
= 1256 kg/m2
= 12.56 kN/m2
Menghitung ρ minimum dan ρ maksimum
a. ρ minimum = 1.4/ Fy
= 0.0035
b. ρ maksimum = 75% *ρ beton
�_𝑏𝑒𝑡𝑜𝑛 = (0.85.β_1. 〖𝑓′〗 _𝑐)/𝑓_𝑦 ∗600/(600+𝑓_𝑦 )

= 0.072
ρ maksimum = 75% *ρ beton
= 0.054

Perhitungan Momen
a. Tipe pelat (asumsi perletakan jepit penuh pada keempat sisi)
Ly 4700
= = 2.350 > 2 Pelat 1 arah
Lx 2000

b. Momen yang terjadi (M. Perlu)


1/14∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mlx =

= 3.589 kN.m = 3588571.43 N.mm


1/12∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mtx =

= 4.187 kN.m = 4186666.67 N.mm

c. Momen nominal (M. Perlu)


Mnlx = Mlx/0.8
= 4.486 kN.m = 4485714 N.mm
Mntx = Mntx/0.8
= 5.233 kN.m = 5233333 N.mm

Perhitungan penulangan
Perhitungan tulangan lapangan dan tumpuan :

Diasumsikan menggunakan tulangan D10 = 10 mm


Selimut beton diasumsikan dengan tebal s = 20 mm
dx = Tebal plat - Selimut beton - (0,5 x diameter tulangan)
= 135 - 20 - 0.5 x 10
= 110 mm
dy = Tebal plat - Selimut beton - diameter tulangan - (0,5 x diameter tulangan)
= 135 - 20 - 10 - 0.5 x 10
= 100 mm

Tulangan lapangan arah X :


Mnlx = 4485714 N.mm
Rn = Mnlx 4485714 4485714
= = = 0.371
b x dx2 1000 x 110 2 12100000
m = fy 400
= = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.371 x 19.61
1 - 1 -
19.61 400
= 0.00094
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.00094 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As perlu 385.00
= = 5 buah
As D10 78.57
Jarak = 1000
= 200 mm
5
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
200 < 405 OK
As pakai = As D10*n = 392.86 mm2

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢 ≤ 〖 �
�〗 _𝑝𝑎𝑘𝑎𝑖 <
385.00 392.86 OK
Jadi digunakan tulangan D10 - 400

Tulangan tumpuan arah X :


Mntx = 5233333 N.mm
Mn 5233333 5233333
Rn = = = = 0.433
b x dx2 1000 x 110 2 12100000
fy 400
m = = = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.433 x 19.61
1 - 1 -
19.61 400
= 0.0011
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.0011 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Diterima dari tulangan lapangan D10 - 400
= As pakai / 2
= 196.43 mm2
As sisa = As perlu - Diterima dari tulangan lapangan
= 188.57 mm2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As sisa 188.57
= = 3 buah
As D10 78.57
Jarak = 1000
= 333 mm
3
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
333 < 405.00 OK
As pakai = As D10*n = 235.71 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖188.57
��〗 _𝑝𝑎𝑘𝑎𝑖
< 235.71 OK
Jadi digunakan tulangan extra D10 - 333

Tulangan susut :
As susut = ρ.b.h = 0.002 * 1000 * 135
= 270 mm 2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As susut 270.00
= = 4 buah
As D10 78.57
Jarak = 1000
= 250 mm
4
Jarak maks = 5.h = 675.00 mm (SNI 2847:2013 Ps. 7.12.2.1)

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
250 < 675.00 OK
As pakai = As D10*n = 314.29 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖 270��〗 _𝑝𝑎𝑘𝑎𝑖
< 314.286 OK
Jadi digunakan tulangan D10 - 250

Rekapitulasi penulangan plat lantai :


Tulangan lapangan arah X = D10 - 400
Tulangan tumpuan arah X = D10 - 333
Tulangan susut = D10 - 250
Pelat Lantai Tipe S2 BE
Data Perencanaan:
F'c = 24 Mpa
Fy = 400 Mpa
Fu = 546 Mpa
�_1 = 0.85
Lx = 2000 mm
= 2 mm
Ly = 4700 mm
= 4.7 m
h = 135 mm
= 0.135 m

Pembebanan pelat
a. Beban Mati (DL)
- Berat sendiri pelat t = 13 cm = 0.135 * 2400 = 324 kg/m2
- Berat spesi t = 2 cm = 2 * 21 = 42 kg/m2
- Berak keramik t = 1 cm = 1 * 24 = 24 kg/m2
- Berat rangka plafond = 1 * 7 = 7 kg/m2
- Berat plafond = 1 * 11 = 11 kg/m2
= 408 kg/m2

b. Beban Hidup (LL)


- Gedung Perkantoran
Ruang Rapat = 4.79 kN/m2 = 479 kg/m2

c. BebanUltimate
- q pelat = 1.2 DL + 1.6 LL
= 1.2 408 + 1.6 479
= 1256 kg/m2
= 12.56 kN/m2
Menghitung ρ minimum dan ρ maksimum
a. ρ minimum = 1.4/ Fy
= 0.0035
b. ρ maksimum = 75% *ρ beton
�_𝑏𝑒𝑡𝑜𝑛 = (0.85.β_1. 〖𝑓′〗 _𝑐)/𝑓_𝑦 ∗600/(600+𝑓_𝑦 )

= 0.072
ρ maksimum = 75% *ρ beton
= 0.054

Perhitungan Momen
a. Tipe pelat (asumsi perletakan jepit penuh pada keempat sisi)
Ly 4700
= = 2.350 > 2 Pelat 1 arah
Lx 2000

b. Momen yang terjadi (M. Perlu)


1/14∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mlx =

= 3.589 kN.m = 3588571.43 N.mm


1/12∗𝑞_𝑝𝑒𝑙𝑎𝑡∗𝐿_𝑥^2
Mtx =

= 4.187 kN.m = 4186666.67 N.mm

c. Momen nominal (M. Perlu)


Mnlx = Mlx/0.8
= 4.486 kN.m = 4485714 N.mm
Mntx = Mntx/0.8
= 5.233 kN.m = 5233333 N.mm

Perhitungan penulangan
Perhitungan tulangan lapangan dan tumpuan :

Diasumsikan menggunakan tulangan D10 = 10 mm


Selimut beton diasumsikan dengan tebal s = 20 mm
dx = Tebal plat - Selimut beton - (0,5 x diameter tulangan)
= 135 - 20 - 0.5 x 10
= 110 mm
dy = Tebal plat - Selimut beton - diameter tulangan - (0,5 x diameter tulangan)
= 135 - 20 - 10 - 0.5 x 10
= 100 mm

Tulangan lapangan arah X :


Mnlx = 4485714 N.mm
Rn = Mnlx 4485714 4485714
= = = 0.371
b x dx2 1000 x 110 2 12100000
m = fy 400
= = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.371 x 19.61
1 - 1 -
19.61 400
= 0.00094
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.00094 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As perlu 385.00
= = 5 buah
As D10 78.57
Jarak = 1000
= 200 mm
5
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
200 < 405 OK
As pakai = As D10*n = 392.86 mm2

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢 ≤ 〖 �
�〗 _𝑝𝑎𝑘𝑎𝑖 <
385.00 392.86 OK
Jadi digunakan tulangan D10 - 400

Tulangan tumpuan arah X :


Mntx = 5233333 N.mm
Mn 5233333 5233333
Rn = = = = 0.433
b x dx2 1000 x 110 2 12100000
fy 400
m = = = 19.61
0.85 x fc' 0.85 x 24
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))
� = 1/𝑚 𝑥(1−√(1−(2 𝑥 𝑅_𝑛 𝑥 𝑚)/𝑓_𝑦 ))

= 1 2 x 0.433 x 19.61
1 - 1 -
19.61 400
= 0.0011
Cek rasio penulangan :
�_𝑚𝑖𝑛≤�<�_𝑚𝑎𝑥
ρmin = 0.0035 > ρ = 0.0011 < ρmax = 0.054
Digunakan ρ = 0.0035 untuk menghitung kebutuhan luas penampang tulangan.

Menentukan tulangan yang terpakai :


As perlu = ρ.b.d = 0.0035 x 1000 x 110
= 385.00 mm2
Diterima dari tulangan lapangan D10 - 400
= As pakai / 2
= 196.43 mm2
As sisa = As perlu - Diterima dari tulangan lapangan
= 188.57 mm2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As sisa 188.57
= = 3 buah
As D10 78.57
Jarak = 1000
= 333 mm
3
Jarak maks = 3.h = 405.00 mm

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
333 < 405.00 OK
As pakai = As D10*n = 235.71 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖188.57
��〗 _𝑝𝑎𝑘𝑎𝑖
< 235.71 OK
Jadi digunakan tulangan extra D10 - 333

Tulangan susut :
As susut = ρ.b.h = 0.002 * 1000 * 135
= 270 mm 2

Menggunakan tulangan D 10
1/4 𝜋𝑑^2
As D10 = = 78.57 mm2

n = As susut 270.00
= = 4 buah
As D10 78.57
Jarak = 1000
= 250 mm
4
Jarak maks = 5.h = 675.00 mm (SNI 2847:2013 Ps. 7.12.2.1)

Kontrol
𝐽𝑎𝑟𝑎𝑘 ≤ 𝐽𝑎𝑟𝑎𝑘 𝑚𝑎𝑘�
250 < 675.00 OK
As pakai = As D10*n = 314.29 mm

Kontrol
〖��〗 _𝑝𝑒𝑟𝑙𝑢
≤ 〖 270��〗 _𝑝𝑎𝑘𝑎𝑖
< 314.286 OK
Jadi digunakan tulangan D10 - 250

Rekapitulasi penulangan plat lantai :


Tulangan lapangan arah X = D10 - 400
Tulangan tumpuan arah X = D10 - 333
Tulangan susut = D10 - 250
LUAS PENAMPANG TULANGAN BAJA PER METER
337\
Diameter Luas Penampang (mm2)
Batang Jarak Spasi p.k.p (mm)
(mm) 50 75 100 125 150 175 200 225 250 275
6 565.7 377.1 282.9 226.3 188.6 161.6 141.4 125.7 113.1 102.9
8 1005.7 670.5 502.9 402.3 335.2 287.3 251.4 223.5 201.1 182.9
9 1272.9 848.6 636.4 509.1 424.3 363.7 318.2 282.9 254.6 231.4
10 1571.4 1047.6 785.7 628.6 523.8 448.98 392.9 349.2 314.3 285.7
12 2262.9 1508.6 1131.4 905.1 754.3 646.5 565.7 502.9 452.6 411.4
13 2655.7 1770.5 1327.9 1062.3 885.2 758.8 663.9 590.2 531.1 482.9
14 3080.0 2053.3 1540.0 1232.0 1026.7 880.0 770.0 684.4 616.0 560.0
16 4022.9 2681.9 2011.4 1609.1 1341.0 1149.4 1005.7 894.0 804.6 731.4
18 5091.4 3394.3 2545.7 2036.6 1697.1 1454.7 1272.9 1131.4 1018.3 925.7
19 5672.9 3781.9 2836.4 2269.1 1891.0 1620.8 1418.2 1260.6 1134.6 1031.4
20 6285.7 4190.5 3142.9 2514.3 2095.2 1795.9 1571.4 1396.8 1257.1 1142.9
22 5070.5 3802.9 3042.3 2535.2 2173.1 1901.4 1690.2 1521.1 1382.9
25 6547.6 4910.7 3928.6 3273.8 2806.1 2455.4 2182.5 1964.3 1785.7
28 8213.3 6160.0 4928.0 4106.7 3520.0 3080.0 2737.8 2464.0 2240.0
29 6607.9 5286.3 4405.2 3775.9 3303.9 2936.8 2643.1 2402.9
32 8045.7 6436.6 5363.8 4597.6 4022.9 3575.9 3218.3 2925.7
36 8146.3 6788.6 5818.8 5091.4 4525.7 4073.1 3702.9
40 8381.0 7183.7 6285.7 5587.3 5028.6 4571.4
50 8730.2 7857.1 7142.9

LUAS PENAMPANG TULANGAN BAJ

Diameter Luas Penampang (mm2)


Batang Jumlah Batang
(mm) 1 2 3 4 5 6 7 8 9 10
6 28.3 56.6 84.9 113.1 141.4 169.7 198.0 226.3 254.6 282.9
8 50.3 100.6 150.9 201.1 251.4 301.7 352.0 402.3 452.6 502.9
9 63.6 127.3 190.9 254.6 318.2 381.9 445.5 509.1 572.8 636.4
10 78.6 157.1 235.7 314.3 392.9 471.4 550.0 628.6 707.1 785.7
12 113.1 226.3 339.4 452.6 565.7 678.9 792.0 905.1 1018.3 1131.4
13 132.8 265.6 398.4 531.1 663.9 796.7 929.5 1062.3 1195.1 1327.9
14 154.0 308.0 462.0 616.0 770.0 924.0 1078.0 1232.0 1386.0 1540.0
16 201.1 402.3 603.4 804.6 1005.7 1206.9 1408.0 1609.1 1810.3 2011.4
18 254.6 509.1 763.7 1018.3 1272.9 1527.4 1782.0 2036.6 2291.1 2545.7
19 283.6 567.3 850.9 1134.6 1418.2 1701.9 1985.5 2269.1 2552.8 2836.4
20 314.3 628.6 942.9 1257.1 1571.4 1885.7 2200.0 2514.3 2828.6 3142.9
22 380.3 760.6 1140.9 1521.1 1901.4 2281.7 2662.0 3042.3 3422.6 3802.9
25 491.1 982.1 1473.2 1964.3 2455.4 2946.4 3437.5 3928.6 4419.6 4910.7
28 616.0 1232.0 1848.0 2464.0 3080.0 3696.0 4312.0 4928.0 5544.0 6160.0
29 660.8 1321.6 1982.4 2643.1 3303.9 3964.7 4625.5 5286.3 5947.1 6607.9
32 804.6 1609.1 2413.7 3218.3 4022.9 4827.4 5632.0 6436.6 7241.1 8045.7
36 1018.3 2036.6 3054.9 4073.1 5091.4 6109.7 7128.0 8146.3 9164.6 10182.9
40 1257.1 2514.3 3771.4 5028.6 6285.7 7542.9 8800.0 10057.1 11314.3 12571.4
50 1964.3 3928.6 5892.9 7857.1 9821.4 11785.7 13750.0 15714.3 17678.6 19642.9
ANGAN BAJA PER METER PANJANG PLAT

Luas Penampang (mm2)


Jarak Spasi p.k.p (mm)
300 325 350 375 400 425 450 475 500 525 550
94.3 87.0 80.8 75.4 70.7 66.6 62.9 59.5 56.6 53.9 51.4
167.6 154.7 143.7 134.1 125.7 118.3 111.7 105.9 100.6 95.8 91.4
212.1 195.8 181.8 169.7 159.1 149.7 141.4 134.0 127.3 121.2 115.7
261.9 241.8 224.5 209.5 196.4 184.9 174.6 165.4 157.1 149.7 142.9
377.1 348.1 323.3 301.7 282.9 266.2 251.4 238.2 226.3 215.5 205.7
442.6 408.6 379.4 354.1 332.0 312.4 295.1 279.5 265.6 252.9 241.4
513.3 473.8 440.0 410.7 385.0 362.4 342.2 324.2 308.0 293.3 280.0
670.5 618.9 574.7 536.4 502.9 473.3 447.0 423.5 402.3 383.1 365.7
848.6 783.3 727.3 678.9 636.4 599.0 565.7 535.9 509.1 484.9 462.9
945.5 872.7 810.4 756.4 709.1 667.4 630.3 597.1 567.3 540.3 515.7
1047.6 967.0 898.0 838.1 785.7 739.5 698.4 661.7 628.6 598.6 571.4
1267.6 1170.1 1086.5 1014.1 950.7 894.8 845.1 800.6 760.6 724.4 691.4
1636.9 1511.0 1403.1 1309.5 1227.7 1155.5 1091.3 1033.8 982.1 935.4 892.9
2053.3 1895.4 1760.0 1642.7 1540.0 1449.4 1368.9 1296.8 1232.0 1173.3 1120.0
2202.6 2033.2 1888.0 1762.1 1652.0 1554.8 1468.4 1391.1 1321.6 1258.6 1201.4
2681.9 2475.6 2298.8 2145.5 2011.4 1893.1 1787.9 1693.8 1609.1 1532.5 1462.9
3394.3 3133.2 2909.4 2715.4 2545.7 2396.0 2262.9 2143.8 2036.6 1939.6 1851.4
4190.5 3868.1 3591.8 3352.4 3142.9 2958.0 2793.7 2646.6 2514.3 2394.6 2285.7
6547.6 6044.0 5612.2 5238.1 4910.7 4621.8 4365.1 4135.3 3928.6 3741.5 3571.4

AMPANG TULANGAN BAJA

Luas Penampang (mm2)


Jumlah Batang
11 12 13 14 15 16 17 18 19 20 21
311.1 339.4 367.7 396.0 424.3 452.6 480.9 509.1 537.4 565.7 594.0
553.1 603.4 653.7 704.0 754.3 804.6 854.9 905.1 955.4 1005.7 1056.0
700.1 763.7 827.4 891.0 954.6 1018.3 1081.9 1145.6 1209.2 1272.9 1336.5
864.3 942.9 1021.4 1100.0 1178.6 1257.1 1335.7 1414.3 1492.9 1571.4 1650.0
1244.6 1357.7 1470.9 1584.0 1697.1 1810.3 1923.4 2036.6 2149.7 2262.9 2376.0
1460.6 1593.4 1726.2 1859.0 1991.8 2124.6 2257.4 2390.1 2522.9 2655.7 2788.5
1694.0 1848.0 2002.0 2156.0 2310.0 2464.0 2618.0 2772.0 2926.0 3080.0 3234.0
2212.6 2413.7 2614.9 2816.0 3017.1 3218.3 3419.4 3620.6 3821.7 4022.9 4224.0
2800.3 3054.9 3309.4 3564.0 3818.6 4073.1 4327.7 4582.3 4836.9 5091.4 5346.0
3120.1 3403.7 3687.4 3971.0 4254.6 4538.3 4821.9 5105.6 5389.2 5672.9 5956.5
3457.1 3771.4 4085.7 4400.0 4714.3 5028.6 5342.9 5657.1 5971.4 6285.7 6600.0
4183.1 4563.4 4943.7 5324.0 5704.3 6084.6 6464.9 6845.1 7225.4 7605.7 7986.0
5401.8 5892.9 6383.9 6875.0 7366.1 7857.1 8348.2 8839.3 9330.4 9821.4 10312.5
6776.0 7392.0 8008.0 8624.0 9240.0 9856.0 10472.0 11088.0 11704.0 12320.0 12936.0
7268.6 7929.4 8590.2 9251.0 9911.8 10572.6 11233.4 11894.1 12554.9 13215.7 13876.5
8850.3 9654.9 10459.4 11264.0 12068.6 12873.1 13677.7 14482.3 15286.9 16091.4 16896.0
11201.1 12219.4 13237.7 14256.0 15274.3 16292.6 17310.9 18329.1 19347.4 20365.7 21384.0
13828.6 15085.7 16342.9 17600.0 18857.1 20114.3 21371.4 22628.6 23885.7 25142.9 26400.0
21607.1 23571.4 25535.7 27500.0 29464.3 31428.6 33392.9 35357.1 37321.4 39285.7 41250.0