Anda di halaman 1dari 9

Costing Comparision Between Conventional & Mivan Shuttering

Conventional Mivan Option I - 3 full sets Mivan Option II - 1.7 Sets


Sr. no. Item/Description fo Work
Basis Amount Basis Amount Basis

1 Labour cost / BUA sq. feet (incl Crane) Incl. Shuttering and Crane 400.00 Including Crane Only 350.00 Including Crane Only

2 Shuttering Cost NA 0.00 As per Calculation 190.00 As per Calculation


3 Steel 7 kg. X 48 336.00 6 kg. X 48 288.00 6 kg. X 48
4 Concrete (RMC) 0.045 m Cube X 5000 per m3 225.00 0.06 m Cube X 5000 per m3 300.00 0.06 m Cube X 5000 per m3
5 Block - work (with Sand & Cement) Lumpsum 70.00 Lumpsum 35.00 Lumpsum
6 External Plaster Lumpsum 60.00 Lumpsum 0.00 Lumpsum
7 Gypsum Plaster for Internal Walls Lumpsum 45.00 Lumpsum 20.00 Lumpsum
8 Back Filling & ATT Lumpsum 5.00 Lumpsum 5.00 Lumpsum
9 G.I. Binding Wire Lumpsum 6.00 Lumpsum 6.00 Lumpsum
10 Electricity & Water Lumpsum 35.00 Lumpsum 35.00 Lumpsum
11 Labour Hutment , PF. & Insurance Lumpsum 20.00 Lumpsum 20.00 Lumpsum
Total (1 to 11) Rs. 1,202.00 1202.00 Rs. 1,249.00 1249.00 Rs. 1,169.00
12 10% Congingencies & unforseen Exp. Rs. 120.00 120.00 Rs. 125.00 125.00 Rs. 117.00
13 Excavation Lumpsum 20.00 Lumpsum 20.00 Lumpsum
Total Cost 1342.00 1394.00
Cost in Rupees per BUA
tion II - 1.7 Sets
Remarks
Amount

350.00 - RMC and Pump by Developer in both options

110.00 (Refer Mivan shuttering cost sheet)


288.00
300.00 Extra Conrete= 0.015 m cube for mivan
35.00
0.00
20.00
5.00
6.00
35.00
20.00
1169.00
117.00
20.00
1306.00
Mivan Shutering Cost
12000/m Cube

Total Shuttering Requirment


OPTION I - 3 Sets for 3 Towers
For one Tower = 4500 sq. feet / Floor (approx.)
= 418 m2
Total Shuttering Requirment = =
5times of floor area 2090 m2

No of Sets 3
therefore for 3 Building = 6270 m2
Rate per m2 = 12500
Basic Cost = 783.75 Rs Lacs

No. of Repetitions = 32
Total Area of Construction 432000

Rate per Sq ft. = Rs. 181.42 per sq. feet

Total Shuttering Requirment


OPTION II - 1.7 Sets for 3 Towers
For one Tower = 4500 sq. feet / Floor (approx.)
= 418 m2
Total Shuttering Requirment = =
5times of floor area 2090 m2

No of Sets 1.7
therefore for 3 Building = 3553 m2
Rate per m2 = 12500
Basic Cost = 444.125 Rs Lacs

No. of Repetitious = 32
Total Area of Construction 432000

Rate per Sq ft. = Rs. 102.81 per sq. feet


RMC PLANT @ SITE
1 Plant cost = Rs. 50 lac
2 Transit Mixer ( 2 nos.) = Rs. 60 lac
3 Concrete Pumps (3 nos.) = Rs. 100 lac
Total = Rs. 210 lac
Int. on RMC Plant Investment for 2 yrs@ 18%p.a. = Rs. 76 lac
Total = Rs. 286 lac

Total concrete required = 0.05 m Cube / sq. feet of BUA


= 0.05 m Cube / 600000 sq. ft.
= 30000 cum

Plant cost / Cum of concrete Rs. 952 cum


=

Assuming 40 % Resale value


Operational cost @ Rs. 225 per cum. @25% approx. = Rs. 71 lac
therefore effective Cost =65% of = Rs. 286 lac
= Rs. 114 lac
Total Plant + Operational cost = Rs. 186 lac

Therefore Actual Plant Cost / cum of Concrete = Rs. 619


M-40 Grade of concrete ( Rate Analysis)
Concrete Cost
material Qty. Unit Rate Amount
Crushed Sand 0.6 cum 1235 741
M- I & II 0.75 cum 740 555
Admixture 1.6 Ltr 70 112

Cement 8 bags 300 2400


Fly Ash - 10 % 80 Kg 2.5 200
4008
Add 5% wastage 5% 200
Add Plant cost Rs. 619
4827

Cost of RMC supply 5350


Add Pumping charges 200
5550

Saving

Total 30,000 723 21684000


2.17 CR
SCOPE OF WORK/ MATERIAL PURCHASE FOR CIVIL WORK

S. No. Material/work Types of Contracts


Conventional Form
MIVAN Form
With M+L Labour Only
Contr. GEECEE Contr. GEECEE Contr. GEECEE
cost/BUA cost/BUA cost/BUA cost/BUA cost/BUA cost/BUA

1 Cement 153 153 179


a Concrete 120 120 168
b Block work 10 10 5
c Plastering 23 23 6
2 Fly Ash ( for Concrete.) 10 10 14

3 Steel 336 336 288

3a Binding Wire 6 6 6

4 Aggregates 125 125 108


a River Sand ( for Block work) 17 17 5
b River Sand ( for plaster) 38 38 6
b Crushed sand ( concrete) 46 46 65
c Metal I & II 23 23 33
5 AAC Blocks 45 45 14

6 Gypsum Plaster ( Int.) 45 45 18


Anti termite treatment &
6 back filling 5 5 5

7 Labour cost/BUA 400 400 350

8 Conv. Form

9 MIVAN Form 190


Concrete Production & 35 23
10 Transport cost 35
a Concrete Movement Eqp.
b Transit Mixer
c Concrete Pump
12 Crane

Elect.,water , Insurance,
13 PF etc. 55 55 55

14 Excavation 20 20 20

Total 636 599 455 779 538 732


Add. 10 % contingencies
15 & Unforseen exp. 699 658 501 857 592 806

Grand Total 1358 1358 1397


Remarks

cost included in labour rate


Free supply to contr.

cost included in labour rate

Anda mungkin juga menyukai