Anda di halaman 1dari 14

DISEÑO DE PRESAS DE GRAVEDAD.

GRAVITY DAMS. for tension and stability. A river upstream can be


DESIGN AND ANALYSIS used mass in the spillway section under the same
conditions as for the non-maximum flow section.
4.1. Introduction. -
4.4.- Freeboard.-
A brief discussion of Guidelines for making
guidelines for making a gravity dam design is The current practice of the Bureau to allow
given in section. Modifications to improve the maximum elevation of the water surface match
design should be done by remodeling the the top of the in the non-overflow section of the
structure. The design of a gravity dam is dam, consider that the standard 3.5 feet high
achieved by making successive designs, each solid parapet acts as a freeboard .
progressively improving based on the results of a Exceptional cases may point to the need for
stress analysis. The analyzes of the tensions of the more freeboard, depending on the height than
gravity dams are divided in two: Classifications: anticipated.
- Analyzes based on action and gravity based
B.- THE VOLTAGE GRAVITY METHOD AND
on the load test method. 4-30.)
The "Gravity Analysis Method" discussed in
STABILITY ANALYSIS
considerable detail in sections 4-5. Description and use.-
4-5 to 4-l0, provides a two-dimensional solution for
Gravity "Method of analysis of tension and
straight gravity dams.
stability" Used a lot for preliminary studies of
These systems are vertical overhangs, horizontal gravity dams, depending on the design phase
beams, and twisted elements. Dynamic analyzes And the information required The equations are
are used in load stress analysis methods to given with standard shapes and illustrations
calculate stresses due to earthquake. A showing the calculation of normality and cut
discussion of foundation analysis is given in Efforts in horizontal, normal and cutting planes in
sections 4-49 through 4-52. A dam is no better the vertical planes and underlies them, both for
than its foundation, and therefore an assessment the empty tank and for the conditions of the
of the foundation's behavior is necessary to complete tank, including tail water and
ensure a system load composed of the dam and earthquake shock. Are included in the contact
the Foundation. pressure calculation calculations and are
a.- level Design.- level design for gravity dam, considered separately in the calculation of
evaluation, feasibility or purpose differs only by stability.
the level of investigation used to determine The formulas shown for calculating tensions are
design data. based on the assumption of a trapezoidal system.
Vertical stress distribution and a parabolic
A.DISEÑO
distribution of horizontal shear stress in horizontal
4 -2. Maximum no-flow section .- planes.
The shape of the maximum non-flow section is 4-6. Assumptions. -
determined by the prescribed loading conditions, Design criteria are given in Chapter III. However,
the shear strength of the rock, and the height of these assumptions peculiar to the analysis of
the maximum section. The water flow of a gravity gravity are listed below:
dam is vertical to concentrate the weight of the (1) The concrete dam is Homogeneous,
concrete on the upstream face where it acts to isotropically and uniformly elastic material.
overcome the effects of the water loading of the (2) No differential movements occurring in the
reservoir. Pending will be suitable to meet the dam due to loads of water in the tank walls and
tension and stability requirements at the highest floors.
elevations, to large aperture is included in the (3) All loads are carried by gravity action parallel
dam. When an additional ridge thickness is used, vertical overhangs that do not receive support
from the adjacent part elements on each side.
the downstream side must be vertical from
(4) Unit vertical or normal Strains in horizontal
downstream of the ridge to an intersection with
the downwardly sloping downward side. The planes pressures vary A straight line from the
upstream face to the downstream face line.
dam must be analyzed for any other change of
(5) horizontally Shear stresses have a parabolic
slope on each side.
variation across horizontal planes from the
4-3. The slope vertedero.- section linking these
upstream face to the downstream face of the
curves must be tangent to each curve and,
dam.
where practicable, parallel to the slope
4-7. Notations for Normal Reservoir of loads. -
downstream in the flow section no -
maximum. The landfill section should be checked

1
DISEÑO DE PRESAS DE GRAVEDAD.

This load includes the full tank load and the usual in the section The upstream face.All Normal
tail water loaded into the dam, as shown in Figure positive stresses are compressive.
4-1.
U = total lifting force in horizontal section. Positive
Properties and dimensions. horizontal forces act upstream.
O = origin of coordinates, in downstream edge Tensions:
section.
θz = Normal stress in the horizontal plane. You
Φ = angle between the face and the vertical
element. θy = normal tension in the vertical plane.

T = Horizontal distance from the top edge to Tzy = Tyz = Shear Stress in horizontal plane. A
downstream edge of the section. positive shear stress Drawing in the upper left of
Figure 4- 1.
C = Horizontal distance from center of gravity of
section upstream and downstream edge equal Θp1 = First primary voltage.
to T / 2.
Θp2 = Second mains voltage.
A = cross sectional area equal to T.
Φp1 = Angle between above 1 and the vertical. It
I = moment of inertia of the section about the is positive in a clockwise direction.
center of gravity, Equal to T3 / 12.
4-8. Notations for horizontal earthquakes.-
ώc = Unit weight of concrete masonry.
The hydrodynamic pressures due to the horizontal
ώ = unit weight of water. rock movements of earthquakes are calculated
using the method Section 4-3 1. The notation is as
ho h '= vertical distance from the reservoir or the follows:
water surface glue, respectively, section.
Ps = normal pressure face.
P o p'= water reservoir or stickwater pressure,
respectively, in section. It is equal to wh or wh '.
Z = depth of the reservoir section being studied.
Forces and Moments:
H = vertical distance from the tank surface
WC = weight of dead load on the base section
elevation in question.
concerned.
Cm = a dimensionless pressure coefficient
MC = W moment about the center of gravity of
obtained from Figure 4- 18.
the section.
Wwe or W'we = change in the vertical
Ww or W'W = vertical component of the tank or
component of the load water reservoir or water
cargo stickwater respectively in the face of the
load in the face - up tail due to horizontal seismic
section.
loads.
Or M'w Mw = moment of W or Wh on center of
MWe or M'we = time Wwe or W'we on the center
gravity of the section.
of gravity section.
V or V'= horizontal component of the tank O
charge of glue water, respectively, on the face Ve = horizontal force inertia weight concrete
on the section. This equals: section above.

Mp or M'p = time V or V 'around the center of ME = V moment about the center of gravity
gravity of section equal to: section.

ΣW = resulting vertical force on the section, as VPE O V'pE = Change in horizontal component of
water + W, + Wk. the water reservoir or load queue in face - up due
to horizontal seismic loads.
ΣV = horizontal force resulting top section, equal
to V + V’. MPE or MPE = Moment M'pE or M'pE about center
of gravity section.
ΣM = Resultant forces section on the center of
gravity. It is equal to Mc + Mw + M'w + Mp + Σ W = vertical force resulting top section, equal to
M'p; The positive moment produces compression + Ww Wc + W'W (+/-) WWE (+/-) W'wE will.

2
DISEÑO DE PRESAS DE GRAVEDAD.

Σ V = resultant horizontal force previous section, equal dam by two systems of elements, one of Arches
to I / + v'f v, F VPE fv; E. and the other of cantilevers, one could replace it
for three each of which occupies the entire
CM = Resultant forces above the horizontal section on volume of the dam. This assumption is based on
the center of gravity. It is equal to + Mw + Mc + Mp + the theory that the contraction joints, by action
M'w M'p (+/-) ME (+/-) MWe (+/-) M'wE (+/-) MPE (+/-) can transfer the load horizontally to the pillars by
M'pE . means of horizontal shearing of the elements and
Algebraic signs of the terms in the equations subscript twisting in the vertical element, but can not at the
E earthquake for W Σ, Σ Σ M VY depend on the moment of twisting Transfer horizontally to the
assumed direction for the horizontal earthquake abutment. For untied joints, it is obvious that
acceleration foundation.There is no notation for the contraction can not be assumed that joints
earthquake vertical shock. provide flexural strength in vertical or horizontal
A vertical earthquake shock is assumed to produce an planes.
acceleration of the mass of the dam and water in In the "Twist method of load analysis", it is assumed
direct proportion to the Y value. This is equivalent to that the dam is divided Vertical and horizontal
increasing or decreasing the density of concrete and The vertical elements of which it is usually
water, depending on the direction of the shock. considered is 1 foot wide and horizontal elements
1 foot high. The cantilevered structure consists of
4-9. Element Forces and Moments Acting overhang. -
a series of cantilevered vertical elements as
Forces of hydrodynamic inertia and concrete on the described above, which rest on the base and
cantilever element for horizontal seismic shock add to transfer of the dead load and a portion of the
the forces shown in Figure 4-1. total external loads only by gravity. Also included
The forces are negative for an acceleration of the in the total The deformation of the twisted
foundation acting upwardly and positively for a base structure with the movement of the pillar due to
acceleration acting in a downstream direction. forces overturned by the overhang that joins the
Forces and moments for static charges are easily foundation at a common point with the horizontal
calculated for each section by determining the element, and the shear deflection in the
momentary areas and arms of the triangular pressure horizontal due to the loads On the twisted
diagrams and the area and eccentricity of vertical structure.
sections.
Notes.-
C.- METHODS OF LOAD ANALYSIS. X, y, z = coordinates along the X axis, Y axis; The Z
axis, respectively.
1.- Twist method of load analysis; Joints not Mz = bending moment parallel XZ plane, foot
grouped: pounds.
Mxy = bending moment parallel XY plane, foot-
4-11. Introduction.-
pounds.
A gravity dam may be considered to consist of a V = Torque horizontal XY plane, foot pounds.
series of cantilevered abutment elements. This Mzy = Torque ZY vertical foot pounds.
interaction between adjacent overhangs causes V = Horizontal Load thrust water, Pounds
elements of torsion, or turns, to materially affect Vc = Shearing cantilever due to the horizontal
the way the water load is distributed between the component load carried by water overhangs
elements of the overhang in the dam. This pounds.
changes the stress distribution from that found by Vt = Shearing on the horizontal element twisted
the ordinary gravity analysis in which the torsional structure due to horizontal component of the
effects, as well as the deformation of the Roca water load carried by the twisted structure,
foundation, are neglected. However, the pounds.
important effects in the support regions where the The subscript A as in aMx and aVc Indicates the
length of the overhangs changes rapidly. value of the abutment for Torque in the XY plane
This torsion action tends to twist the overhangs and shear in the base of the cantilever,
from their seats in the inclined walls of the barrel, respectively.
tending to develop cracks in the dam in these T = thickness of the dam in elevation feet.
regions. Ec = Modulus of elasticity of concrete in tension or
compression, pounds per square foot.
12. 4- Theory.- Er = Modulus of elasticity of material compression
The use of a Structural twist for the analysis of the stress in tension, psf.
prey was review of the experimental load analysis G = Modulus of elasticity in shear Crete, psf.
method done for the recovery office in 1930. It μ = Poisson coefficient.
was proposed that instead of replacing the arch

3
DISEÑO DE PRESAS DE GRAVEDAD.

θz = angular rotation in the horizontal plane, 𝑘1


𝛼′ = (1)
radians. 𝐸𝑟 𝑇 2
Az = normal to the axis of Presa, Deflection feet. 𝑘5
Z = vertical distance from the base of the 𝛼 ′′ = (2)
𝐸𝑟 𝑇
cantilever feet. 𝑘2
I = Moment of inertia for a vertical cantilever unit ϒ′ = 𝐸𝑟
(3)
or a horizontal beam width of the height of the
𝑘4
unit cross section, pies4. 𝛿′ = (4)
𝐸𝑟 𝑇 2
J = factor used in calculating angular rotations
cantilevers Because torsions Disengaged-joints. The contact surface between the dam and the
A = area of cross - sec tion of a beam, or foundation is developed and plotted as shown in
cantilever square feet. For a wide unit or height, Figure 4-1. In computation the deformations of a
A = T. particular element, the width of a 'becomes
equal to T, the thickness of the Prey in the element
L = length of a horizontal beam, feet. considered, make T / b '= a / b, ob' = (b / a) T.
External pressure ρ = depth hours, pounds per Below are the final equations for the movements
square foot. of the foundation of a horizontal element of the
unit in each stirrup of the dam.
P = Unit ordered load, psf
Next, we show the final equations for the
K = A constant which depends on the ratio movements of the foundation of a horizontal
of the actual distribution of cutting a element of the unit in each stirrup of the
uniformly distributed shear. In these dam. They are the algebraic signs for the left
analyzes K / G / E 3 and K = 1,25. stirrup and the asterisk (*) indicates that the signs
are to be reversed for the movements in the right
Ψ = angle between the canyon wall on stirrup.
the base and the vertical degrees.

𝜶 = Angular movement of the stirrup ∗ 𝜃2 = 𝑀𝛼2 +V𝛼2 (5)


For what:
in the vertical plane due to the bending
moment unit, radians ∆𝑦 = 𝑉ϒ +𝑀𝑧 𝛼2 (6)

Υ = Pilar normal movement to the axis of 𝛼 = 𝛼 ′ 𝑐𝑜𝑠 3 𝛹 + 𝛿′𝑠𝑒𝑛2𝛹 cos 𝛹 (7)


the dam due to shear force unit in the
stirrup foot. 𝑎2 = 𝑎" 𝑐𝑜𝑠 2 𝛹 (8)

ϒ = ϒ′ cos ϒ (9)
𝒂𝟐 = Angular movement of Pillar in vertical
plane due to the horizontal shear force of
unit in the stirrup, radians It is customary to require 6 'for a differential area
unit on one side of the dam an average value for
𝒂𝟐 = Movement is normally ribo to the axis of the equivalent zone on that side of the dam. If the
the dam because of the unit bending damsite is approximately symmetrical about the
moment of unity, feet. maximum section, they are dimensions of the
equivalent zone for one or both sides of the dam
δ = angular movement in horizontal plane
a and b / 2. For this reason, ratios @ y;substituted
by Pilar radians unit torque, radians.
by the ratio b / a in some cases to obtain values
The Sign Convention to be used is shown in Figure of the curves in Figures 4-7 through 4-10. These
4-6. substitutions are indicated below:

4-14. Foundation constants.- And Υ use for radius b;

Rotation and deformations of the surface Δ use for radio.


Foundation moments and forces unit, per unit
Below are the final equations for the movements
length, are given by the following formulas, in
of a vertical element of the unit in each stirrup of
which k is a function of μ b / a, and T is equal
the dam. As before, it is the algebraic signs for the
to a '(see Figs 4-7 to 4-10).
left stirrup and the asterisk (*> indicates which
signals must be reversed for movements in the
right stirrup

4
DISEÑO DE PRESAS DE GRAVEDAD.

Particular attention should not be paid to the


underlined part of the equation when used for
𝜃2 = 𝑀𝑥 𝛼 + V𝛼2 (10) analysis with ungrouted joints, but will be referred
to in the explanation for analysis with grout joints.
∗ 𝜃2 = 𝑀𝑥𝑦 δ (11)
4-18. Unit rotations of vertical elements of twisted
∆𝑦 = 𝑉ϒ +𝑀𝑧 𝛼2 (12) structure due to the torque unit. -

Unit rotations of vertical twisted elements due to


triangular unit torque loads are illustrated in Figure
for what: 4-1. 3. Unit rotations of a vertical element on the
left side of the dam are calculated by replacing
the moments Of torsion in the following equation,
𝛼 = 𝛼 ′ 𝑠𝑒𝑛3 𝛹 + 𝛿′𝑠𝑒𝑛𝛹 𝑐𝑜𝑠 2 𝛹 (13) where the symbols have the meaning given in
section 4-13
𝛼2 = 𝛼 ′′ 𝑠𝑒𝑛2𝛹 (14)
𝑀𝑥𝑦
θ𝑧 = ∑ ∆Z+𝐴 𝑀𝑥𝑦 𝛿 (18)
′ 3
𝛿 = 𝛿 𝑠𝑒𝑛 𝛹 + 𝛼′𝑠𝑒𝑛𝛹 𝑐𝑜𝑠 𝛹 2
(15) 𝐺𝐽

ϒ = ϒ ′ sin 𝛹 (16)
In the foregoing, J is a factor for determining
torsion in an axis of uniform cross section. The
values of J are computed [3] from the equation,
4-15. Selection of Elements.-
J = βb𝑐 3 (19)
If the dam is symmetrical, only half of the dam
needs to be analyzed. If it is not symmetrical, the Where:
dam is divided into a convenient plane near the
center where the floor of the barrel is relatively b = length of the horizontal section of the side
flat, or where it is expected that little spinning element. (In this case the element is the block
action is likely to exist. For the analysis of half a between two ungrouted contraction joints).
symmetrical dam, generally five to seven c = lower side of the horizontal section of the
horizontal elements and four to seven vertical
element.
elements are selected to represent the structure.
The following table gives the values of β for
4-16. Loads, forces and moments. -
different ratios of b / c
Forces and moments by dead load, waterload,
earthquake shock, and other charges and
annotations are determined as indicated in
sections 4-7, 4-8 and 4-9. Concrete weight is
assigned to overhangs, since it is assumed that
deviations due to weight occur gradually during
the construction of the prey prior to the grouting
of the shrinkage joints.
To facilitate the determination of the values of J
4 - 17. Initial and deviations from the unit by the different elevations of each vertical
voladizos.- element, the data in the above table have been
Before starting an adjustment, it is necessary to plotted and a curve drawn as shown in Figure 4-
determine the cantilever properties and 14. To determine J for an element 1 foot wide, the
calculate initial deflections and cantilever units computed values are divided by the distance
due to the initial load and normal load of the unit, between the contraction joints.
respectively. The values of J determined by the above method
The calculation of the unit of forces and moments will be carried out for any element of the unit
due to normal unit loads is illustrated in the figure. within this block or similar blocks with the same
distance between the contraction joints and the
same thickness at each elevation

4-19. Structure Deviations of Horizontal Elements


of Twisted Unit.-

Deviations of the unit of horizontal elements due


to shear stress are used in the calculation of
deflections for each adjustment. Unit loads are

5
DISEÑO DE PRESAS DE GRAVEDAD.

applied to the horizontal elements by means of numerically equal to the shear stress in the
triangular loads having a P-value per square foot horizontal member.
in the stirrup and varying as a straight line to zero Since the load pairs are in thousands of feet-
at the intersections of each respective vertical pounds per square foot, the shear forces must be
element with the horizontal element. expressed in units of thousands of pounds.

∆𝑦 = ∫
𝐾𝑉𝑡
𝑑𝑥+𝐴 𝑉𝑇 𝛿 (20) 4-22. Deflections of twisted structure. -
𝐺𝐴

The deviations of the twisted structure due to


angular rotations of vertical elements are
In which the symbols have the meanings given in obtained by integrating the angular rotations
section 4-13. Using K = 1.25 and G = E / 2 (1 P), the along the horizontal elements from the abutment
general equation reduces to the following, where to the dividing plane of the dam. However, for
L is the length of the middle element, L 'is the comparison with the cantilevered deflections as
length of the loading part, measured from the to matching at conjugated points, the stop
crown, and x Is the distance from the stirrup to the motion of the particular vertical element of the
point where the deviation is desired. For a cantilevered structure (here referred to as the
triangular unit load, conjugate vertical element) should be added to
the twisted structure deflections having a
𝑃
∆y = − [3(𝐿´)2 𝑥 − 3𝐿´𝑥 2 + 𝑥 3 ] +𝑉𝐴 ϒ (21) Common stop with The horizontal element of the
2𝐸𝐴𝐿´
twisted structure
For uniform loading,
4-23. Deflections of the Cantilever Structure. -
3𝑃
∆y = − [2𝐿𝑥 − 𝑥 2 ] + 𝑉𝐴 ϒ (22)
2𝐸𝐴
The cantilever deflections are calculated by
summing the respective products of these loads
and the cantilever deflections due to normal
For a unit of charge concentrate, loads (see Sec. To these deflections are added
3𝑃𝑥 algebraically the deflections due to the initial
∆y = − + 𝑉𝐴 ϒ (23) loads and, for comparison with the total
𝐸𝐴
deflections of the structure The movement at the
base of the overhang due to the shear at the top
of the conjugate horizontal element of the
The shear forces are equal to the area under the
twisted structure is also added.
load diagram of the unit from the dividing plane
of the dam to the overhang points under 4-24. Tensions and Stability Factors. -
consideration and are negative in the sample.
After a satisfactory continuity of the structure, or
Values of unit deviations due to shear stress on agreement of deflections at the conjugate
horizontal elements are tabulated for convenient points, has been obtained by test, the total shear
use in settings. and moments at several points in the overhangs
4-20. Loads of test. - can be calculated from the established test loads

2. Experimental method of twisting the test


After the calculation of unit load deflections and
charge, clustered joints.
rotations of horizontal and vertical elements, the
next step in the analysis is the horizontal load test 4-25. Description of the method. -
division between the cantilevered structure and
the twisted structure. Near the pillars, however, The grout of the contraction joints welds the
the twisted structure usually carries the highest vertical blocks of the dam into a monolithic
proportion of load, depending on the size of the structure. For this analysis, then, we have the
dam, the shape of the barrel and the elastic cantilevered structure, the twisted structure and
properties of concrete and rock. the beam structure, or three structures instead of
two, the twisted structure being composed of
4-21. Angular rotation of vertical crooked both vertical and horizontal elements as
elements due to test loads on horizontal described above.
elements. - If the dam acts as a monolith, as is assumed, the
deviations of the overhangs, horizontal beams
The shear force due to normal test loads on a
and twisted structure-due to the test divisions of
horizontal element at the location of any vertical
the water load between the three systems-must
element is equal to the area under the load
be agreed in all parts of the dam. However, a
diagram from the divisor plane to the considered
vertical element. Since the width of the vertical general slope adjustment is not necessary since
the adjustment of the deflections in the horizontal
member is unitary, the torque in the overhang is

6
DISEÑO DE PRESAS DE GRAVEDAD.

elements of the twisted structure results in cantilever does not require a strong twist on the
agreement of the longitudinal slopes of the beam member.
horizontal elements with the transverse slopes of
the cantilevers. 4-26. Assumptions. -
The setting is more complicated than for grout From the above considerations, the structural
joints. The calculations in Figure 4-17 show that, if action of the elements of the dam can be
these rotations are integrated along their assumed as follows:
respective planes from the beam stop and the
cantilevered foundation to the point of (1) Cantilever elements resist shears in horizontal
application of the load, the resulting deflections planes and are folded in vertical planes.
at the latter point are Equals [4], from which it can
(2) Horizontal beam members resist shears in
be concluded that equal amounts of load are
vertical planes and flex in horizontal planes.
transferred vertically and horizontally by the
twisted structure. It should be noted that although (3) The twisted structure resists twisting moments
the assumption of an equal load distribution is and scissors in horizontal and vertical planes.
correct for a section of uniform thickness, it is only
approximately true for a section of variable 4-2 7. Elements horizontal beam. -
thickness.
The unitary slopes of the beams at the abutment
By hypothesis, the beam and cantilevered are used to obtain the effect of the beam
structures can withstand only bending and abutment forces on the rotation of the base of
shearing, while the twisted structure can the conjugate vertical twisted element and the
withstand only torsion and shear. The total unitary slopes in the crown are used to establish a
clockwise moment acting on the element is P slope arrangement in the Plane dividing between
multiplied by the 10-foot Arm, plus a pair beams in the left half and beams in the right half
consisting of the shear P multiplied by a 1-foot of the dam.
arm, which is balanced by a moment of
Resistance anti-clockwise from P multiplied by 11 3. Analysis of dams of curved gravity.
feet
4-30. Analysis method. -
Vertical cross sections in planes normal to the
If a gravity dam is curved in the plane only for
paper plane are of uniform thickness of the unit
convenience in locating the structure in the
from the top to the base of the dam. Suppose
existing topography and the contraction joints do
that half of the Twisted structure is carried
not fill, the analyzes should be done as described
horizontally to the pillars and the half is for straight gravity dams.
transported vertically to The foundation, by
twisting action. D. DYNAMIC ANALYSIS.

𝑃 𝑃 4-31. Introduction. -
𝐸𝑛 𝐻𝑇𝑆 𝑀𝑌𝑍 = , − − −; 𝜃𝑌𝑍 = ∙ 𝑥 − − −
2 2
The following method for dynamic analysis of
∆𝑌 = ∫ 𝜃𝑌𝑍 𝑑𝑧 concrete dams can be described as a mass-
grouped, generalized coordinate method using
𝑃 𝑃 the principle of overlap mode.
𝐸𝑛 𝑉𝑇𝑆 𝑀𝑋𝑌 = , − − −; 𝜃𝑋𝑌 = ∙ 𝑧 − − − The application of the method is done by
2 2
computer, and matrix analysis methods are used.
∆𝑌 = ∫ 𝜃𝑋𝑌 𝑑𝑧 4-32. Natural frequencies and mode shapes. -
𝑥 The natural frequencies f1, f2, f3, etc., and
𝐹𝑜𝑟 𝐻𝑇𝑆 𝐴𝑌 𝑎𝑡 𝑡ℎ𝑒 𝑝𝑜𝑖𝑛𝑡 𝑋5 , 𝑍10 , 𝑍 =
2 corresponding mode shapes (where i indicates
5 the number assigned point mass) found for the
𝑧=5
𝑃 𝑃𝑍 2 simultaneous solution of equations for dynamic
Δ=𝑌=∫ . 2𝑧 𝑑𝑧 = [ ] = 12.5 𝑃
𝑧=0 2 2 0 equilibrium free vibration. There are standard
solutions available for the eigenvalue problem.
The input that will be required to solve the self-
value problem will be the stiffness matrix [K] and
the mass matrix [M].
Therefore, the load on the beam does not require
a torsion resistant in the cantilever element for the
balance. Similarly, the load supported by a

7
DISEÑO DE PRESAS DE GRAVEDAD.

The equation is:


7
𝑏= ∗ √ℎ𝑧 (47) 𝑥̈ 𝑖 𝑡𝑜𝑡𝑎𝑙 = ∑ 𝑥̈ 𝑖𝑛 (49)
8 𝑛

Where: The response history is analyzed during the time of


the peak acceleration value at the peak.
B = the dimension of water measured horizontally
from the upstream face, The now is the acceleration for prey. These values
can be divided by the acceleration of gravity to.
Z = depth of water in the section under study, and
After the acceleration ratios, ai, are determined
H = distance between the water surface and the for the necessary elevations in the dam, the
point in question. resulting loads on the structure is calculated as
described in the following paragraphs.
4-33. Response to an earthquake. -
4-34. Loads due to horizontal seismic
Given the natural frequencies, mode acceleration. - For dams with vertical or inclined
shapes , and an acceleration log of an faces upstream, the variation of seismic
earthquake, the following equation expresses the hydrodynamic pressure with depth is given by the
acceleration of point mode, as a function of time: following equations [10]:

𝑃𝐸 = 𝐶 𝛼 𝑤𝑧 (50)

𝐶𝑚 ℎ ℎ ℎ ℎ
𝐶= [ (2 − ) + √ (2 − )] (51)
2 𝑧 2 𝑧 𝑧

Where:

where:
1 𝑷𝑬 = Normal pressure to the face,
𝑇𝑛 = ,
𝑓, 𝑛´
𝑪 = A dimensionless pressure coefficient,
𝝀 = 𝑓𝑎𝑐𝑡𝑜𝑟 𝑑𝑒 𝑎𝑚𝑜𝑟𝑡𝑖𝑔𝑢𝑎𝑚𝑖𝑒𝑛𝑡𝑜 𝑣𝑖𝑠𝑐𝑜𝑠𝑜,
𝐻𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙 𝐴𝑐𝑐𝑒𝑙𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝐸𝑎𝑟𝑡ℎ𝑞𝑢𝑎𝑘𝑒.
𝒙𝒈̈ (𝝉)= The acceleration of the soil as a function 𝜶=
𝐴𝑐𝑐𝑒𝑙𝑒𝑟𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑔𝑟𝑎𝑣𝑖𝑡𝑦.
of the digitized time for the numerical evaluation
of the integral. 𝒘 = 𝑈𝑛𝑖𝑡 𝑤𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑤𝑎𝑡𝑒𝑟.

𝝓 = 𝑁𝑜𝑑𝑎𝑙 𝑑𝑖𝑠𝑝𝑙𝑎𝑐𝑒𝑚𝑒𝑛𝑡 𝒛 = 𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝑟𝑒𝑠𝑒𝑟𝑣𝑜𝑖𝑟 𝑖𝑛 𝑠𝑒𝑐𝑡𝑖𝑜𝑛


𝒉 = 𝑉𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝑑𝑖𝑠𝑡𝑎𝑛𝑐𝑒 𝑓𝑟𝑜𝑚 𝑡ℎ𝑒 𝑡𝑎𝑛𝑘 𝑠𝑢𝑟𝑓𝑎𝑐𝑒
𝑴 = 𝑑𝑜𝑢𝑔ℎ,
𝑪𝒎 = 𝑇ℎ𝑒 𝑚𝑎𝑥𝑖𝑚𝑢𝑚 𝑣𝑎𝑙𝑢𝑒 𝑜𝑓 𝐶 𝑓𝑜𝑟 𝑎 𝑠𝑙𝑜𝑝𝑒
𝝉 = 𝑇𝑖𝑚𝑒, 𝑎𝑛𝑑

𝒕 = 𝐴 𝑝𝑎𝑟𝑡𝑖𝑐𝑢𝑙𝑎𝑟 𝑡𝑖𝑚𝑒, 𝜏 = 𝑡.
For dams with a vertical and slope combination,
if the height of the vertical portion of the
There is little data available on damping upstream face of the dam is equal to or greater
concrete dams, expressed as h in equation than half of the total height of the dam, analyze
(48). Chopra [9] indicates that a reasonable like vertically.
assumption for h in a particular gravity structure is E. THE Finite Element Method.
0.05.
04.03 6. Introduction. -
Equation (48) is evaluated in chosen time
increments. An increase of 0.01 seconds has The finite element method uses the idea that a
been used. At the end of each of these time continuous body being a set of different elements
increments, the accelerations for all node points connected at their corners. The reason for the
in all modes considered are summed up as in the immediate acceptance and the tremendous
following equation: amount of use of this method is that made
possible the approximate solution of many
problems that had been neglecting engineers on

8
DISEÑO DE PRESAS DE GRAVEDAD.

designing or coarsely approaching. 2. PH and music and variations


The inclusion complex geometric variations and property. - The program allows reading
physical properties before the adaptation of the changes m or module, density,
finite element method and the modern high temperature and accelerations after
speed digital computer was just beyond the reference é s each an to lysis.
realm of reality. The two - dimensional finite
element method can analyze most of the 3. You can be obtained a diagram
problems associated with variations in the microfilm entire grid or details
geometry of the sections of the dam. thereof. Also é n can be obtained a
plot with the identification or n n ú mere
1. Program two-dimensional Finite Element given material within each element .
4-37. Purpose. - 4. Properties of bilinear material. -The
program allows the input of an
The purpose of this software is to determine strains m or module in compression or ny in
and stresses in two-dimensional plane stress tension or n. The m or module of
structures arbitrarily. tension or n included in successive
4-38. Method. - 5. Openings. - An opening can be
The same number of equations that relate the simulated in the structure by assigning a
stiffness coefficients times unknown deflections zero to any material or element actually
existing loads (members of the right hand) have defining the structure with the opening
been generated. The value of this unknown is not included in the definition or n. The first
determined and is used in solving the above m é all permits use or ptimo Y and allows
equation that has only two unknowns. The value greater flexibility.
of this unknown is determined and is used in (6) Verification and preparation of the
solving the above equation that has only two cover. - There are several options to
unknowns. Then known deflections are used, the monitor and facilitate the preparation of
stiffness of the individual elements and the entries.
equations relating stress and strain for the
element to calculate the stress condition of the (7) Stiffness shear. - it may be included the
element . effect of shear stiffness in the third
dimension.
4-39. Entry. -
(8) Units. - output units of the program
The problem is defined by a card entry that match the input units. In general, these
describes the geometry and the boundary units are not shown in the
conditions of the structure, material properties, output. However, there is an option that
loads, control information for the layout and the allows the units occur in the output feet
use of options in the program. Mesh generation, and pounds per square inch provided
charge generating property and generation of that the input is in feet and kips.
material is incorporated into the system.
(9) Normal stress and shear stress in a
4-40. Departure. - plane. - The normal stress and shear stress
at any given plane can be
The output of this program consists primarily of a
calculated. Furthermore, since the
print data input and output displacements and
internal angle of friction and cohesion of
stresses each node within each element. Also
the plane, one can calculate the safety
available is a presentation of microfilm mesh and
factor against slipping.
lattice parts with paths efforts on the
screen. Some outputs of punched cards are also (10) Reference temperature. -
available for special purposes preparation input temperature loads with respect to a given
or output analysis. reference temperature for the whole
problem apply. If portions of the problem
4-4 1. Capacities. -
have different reference temperatures,
they can be introduced into the card
1. External forces and temperature is material properties and nullify the global
known displacements and accelerations reference and temperature for that
given as a percentage of the material only.
acceleration or n due to gravity in the X
and Y directions. (11) using pressure limits. - The program
calculates concentrated loads in the
nodes based on these pressures.

9
DISEÑO DE PRESAS DE GRAVEDAD.

(12) The coordinates input may be same ratios of displacement deformation and
prepared by digitizing a scale drawing of stress-strain used in the formulation of the stiffness
external forces problem may apply. The element.
scale can be adjusted within the program
by introducing a scaling factor on the 4-46. Capabilities and limitations. -
control board. The coordinates used by Accurate modeling flex requires the use of
the program are the coordinates input several elements (three have been shown to work
times the scale factor. If no scale factor, quite well) through the folding section. The
the coordinates are used as given. number of nodal point program capacity for
4-42. Limitations. - 65,000 computer storage elements is 900 words,
2,000 nodal points and maximum bandwidth of
(1) Nodes 999; Elements, 949; Materials, 100. 264.

(2) Bandwidth (maximum difference between 0.024[Number of nodal points] + 0.45 [Item Number]
any element nodes) = 42. Number of nodal points Bandwidtha 2
+100 ( )𝑥 3 𝑥 ( ) (52)
775 96
(3) Maximum number of rows in a detailed = 25
route section.

4-43. Approximations. -

(1) Linear distribution of deflection between For a problem that uses the full capacity of the
nodes. program, this is equal to:

(2) The curved surface has to be approximated 0.024 (2.000) + 0.45 (900) + x 3 x (
264 2
) =
by a series of straight lines. 96
6,308 𝑠𝑒𝑐𝑜𝑛𝑑s
(3) attachment points should be established
within the limits. Ability to use mesh generation, concentrated
loads, automatic or uniform application of
(4) Voltage flat two-dimensional
hydrostatic loading and material properties that
4-44. Application to gravity dams. - exist in the program. However, the non-
rectangular solids require additional time for the
The two - dimensional finite element analysis is formulation of the rigidity due to the need for
adaptable to analysis of gravity dam when greater numerical integration.
assuming planarity is used. Areas of stress cracks
and seams weak material can be included in the 4-47. Entry. -
foundation. The structure to be analyzed is approximated by
The internal hydrostatic pressure may be included a set of elements. The finer mesh (smaller
as fillers in the section analyzed. An example elements) is located in the region of maximum
illustrating the application of two - dimensional voltage change.
finite element method for analysis of a gravity
dam and its foundation is illustrated in Appendix To enable accurate modeling of
C. deformation. The division is also made such that
the minimum bandwidth possible, and the nodes
2. Three-dimensional finite element program and elements are numbered taking this into
4-45. Application. - account. The program requires the following
basic information:
This computer program developed by the`
University of California, Berkeley, used the (1) Operational data such as title, job number,
parametric element six nodal points number of elements, maximum bandwidth,
(hexahedron) of Zienkiewicz-Ironsiso to analyze number of materials, etc.
three - dimensional elastic solids. Once (2) The conditions of constraint on the edge.
established scroll functions, strains can be
formulated element shifts nodal points are (3) Material description of the elements.
related strains voltage-displacement. A set of
equations for the entire system is obtained by (4) The accuracy of integration required for each
equating the product of unknown displacements element.
times rigidity known forces at each nodal point. (5) The XYZ coordinates of each node point and
The nodal displacements are determined the eight numbers nodal point forming each
by solving this set of equations. Tensions are element (mesh generation can be used to
calculated dt nodes of each element,using the perform these functions).

10
DISEÑO DE PRESAS DE GRAVEDAD.

(6) applied forces (can use the automatic resistance, or when the final boundaries are free
generation load). faces that do not offer resistance. As shown in
Figure 4-20, the resultant of all loads on the
4-48. Departure. - section under investigation are resolved mass in a
The output of the program consists of: shearing force, V, parallel to the plane of
potential slip and normal force, N. The safety
(1) A reprint of all input information including factor or shearing friction factor is determined by
information automatically generated. dividing the tensile strength by the sliding
force.This distribution allows considerable
(2) The displacement in the X, Y and 2 for each of variance in the normal load in the determination
the nodal points. of the resistance force and cutting force along
(3) The normal stress in the X, Y and 2 and the the sliding plane potential.
shear stress in 4-52. Three - dimensional methods. -
XY, YZ and XZ in each nodal formulation, data A typical problem in dimensional stability is a
input and output is given in point. Appendix C. wedge four sides with two exposed faces of two
Examples of problems Howingmes h other faces that provide slip resistance. The
FOUNDING F. ANALYSIS wedge shown in Figure 4-21 is used in the
discussion to illustrate various methods.
4-49. Purpose. -
(A) Method of Block Rigid 1141.-
The base or parts of it must be analyzed to
determine the stability provided the rock against The following assumptions are made for this
which the thrust of the dam has such a method:
configuration that possible failure of direct shear (1) All forces may be combined into a resultant
or when a sliding failure is possible along faults , force.
shears and gaskets.
They are associated with stability problems of (2) No no deformation can occur within the mass
excess local pressure on the dam because of the of the block.
shortcomings of the foundation.
(3) sliding in a single plane can only occur if the
1. Stability Analysis shear force in the plane is directed towards an
exposed face (open or free).
4-50. Methods available. -
(4) sliding in two planes can only occur in the
Methods available for the stability analysis are: direction of the intersection of the two planes and
A) Methods dimensional. to an exposed face.

(1) Method of the rigid section. (5) No transverse shear forces are developed (ie,
no shear normal to the direction of sliding planes).
(2) Finite Element Method.
Rigid block analysis proceeds as follows:
B) Three-dimensional methods.
(1) the planes forming the block are defined.
(1) Method of rigid block.
(2) The intersections of the planes formed by the
(2) Method partition. edges of the block.
(3) Finite Element Method. (3) the areas of the faces of the block and the
block volume is calculated.
Each of these analyzes produces a shear force
and normal force. The normal force may be used (4) The hydrostatic forces, if applicable, are
to determine the shear strength as described in calculated normal to the faces.
section 3.5. The safety factor against slipping is
calculated by dividing the resistance to cutting (5) the resultant of all forces is estimated.
by the cutting force. (6) the possibility of sliding on one or two planes it
4-5 1. bidimensionales- Methods is controlled.

A problem can be considered two-dimensional if (7) The safety factor against slipping is calculated
the geological embodiments creating for all cases in which sliding is possible.
questionable stability not vary in cross section 2. Further analysis
over a considerable length so that the extreme
limits have negligible contribution to the total 4-53. Analysis of differential displacement. -

11
DISEÑO DE PRESAS DE GRAVEDAD.

The problem of differential displacement relative mainstream, and selecting the most appropriate
deflection or mass or blocks within the foundation scheme to handle the current flow during
arises due to variations in the base construction is important for economy in the cost
material. Methods that approximate or estimate of the dam.
the mass or displacement areas within the
foundation is necessary for analyzing problems of (1) Flow characteristics.
this nature. (2) Size and frequency of flood diversion.
Typical problems that may occur are as follows: (3) Regulation by the existing dam upstream.
(1) Moving a mass whose stability depends on (4) Methods of deviation.
sliding friction.
(5) requirements specifications.
(2) Moving a sliding mass in an area of low
modulus. (6) Control of turbidity and water pollution.

(3) Moving a mass with a partial continuity intact 5 - 2 Features Streamflow. -


rock.
A place where seasonal rains may occur
(4) Shift variable load areas taken by competent will require only minimal provisions of the
rock in two directions, but cut adjacent rock by deviation for the rest of the year.
weak material unable to transmit shear load. The A stream subject to storm clouds that can occur
displacements can be approximated by: at any time is the most unpredictable and likely
require the diversion scheme more elaborate,
(1) extension of the displacement data obtained since the contractor must be prepared to handle
by shear testing in situ or laboratory samples; both low flows and flood flows at all times during
(2) model test; the period building

(3) development of an analytical model which 5-3. Flood Diversion selection. -


can be solved by hand; or (4) methods of finite It is not economically feasible plan for the
elements two or three dimensions. diversion of the biggest flood ever occurred or
Although the method used depends on the may be expected to occur at the site, so you
particular problem, it should be noted that the should decide on a minor requirement.
finite element method offers considerable This, therefore, raises the question of how much
advantage over other procedures. The finite risk to the partially completed work is involved in
element method allows an accurate the diversion scheme considered.
representation of the material property, gives After an analysis of these factors is the cost of
voltage. Distribution and allows the increasing protective work Handle increasingly
representation of the treatment required for larger floods can be compared with the cost of
displacement.
damage result if such floods occurred without
4-54. Analysis of stress concentrations due to increased protection work.
bridges. -
For larger dams involving more than one building
A stress concentration can occur in the dam due station 2 years, a flood of distraction design with
to the presence of a zone of low modulus in the a probability of presence of anywhere between
foundation. The depth of required replacement is 20 and 4 percent may be established depending
determined as the depth when tensions in the on the risk of loss and the time termination for
dam and foundation are within permitted limits. individual prey.

RIVER DIVERSION Floods can be recurrent; therefore, if the scheme


involves the temporary storage distraction final
A. REQUIREMENTS DEVIATION cloudburst type must provide such storage
5-1. General. - facilities to evacuate within a reasonable period
of time, usually a few days
The design of a dam to be built through a
channel considering diverting the current flow 5-4. Regulation by an existing dam up water.
around or through the dam during the If the dam is to be constructed in a downstream
construction period. of the existing dam or other structure control, it is
The magnitude of the problem of the deviation sometimes possible to modify characteristics of
will vary with the size and potential of the the current flow through the intended operation
current; However, a problem of deviation exist to of the existing structure.
some extent in all locations outside the

12
DISEÑO DE PRESAS DE GRAVEDAD.

5-5. Turbidity and control water pollution. influenced by the cost of a tunnel compared to
a tunnel of equal capacity; When the tunnel
One of the most important factors to be proposed landfill is a high entrance and a tunnel
considered in determining the pattern of the fun sloping down to a near horizontal tunnel portion
is how the construction work required affect near the elevation of the riverbed, a tunnel
turbidity and pollution of the stream. Therefore, all deviation can be built between the near
schemes deviation should be reviewed for the horizontal tunnel part and raising upstream
purpose of pollution and turbidity in the current channel to effect a road circulation riverbed.
during the erection and removal of work Flow regulation to meet needs downstream after
deflection, as well as the effect on current during water storage in the reservoir has begun may be
construction time it is continued between the carried out by using a slide gate on the road
cofferdam. temporary bypass to the water surface in the
reservoir reaches the level of the output jobs
B. METHODS OF DIVERSION
consumption.If the tunnel passes near and below
5-6. General. the dam, the plug should be located near the top
expensive river under the shade of grout limit or
The method or scheme divert flooding during this can fully extend below the dam, according
construction depend on the magnitude of the to the tensions of the dam and the condition of
flooding to be diverted; Diverting current during the foundation.
construction uses one or a combination of the
following provisions: driven by the stirrups, tubes or 5-9. Channels. -
ducts by the dam area, or distraction multiple
In a wide canyon, an economical method of
stage on the tops of the blocks alternate
deviation can be a conduit for conveying the
construction of the dam tunnels. On a small
flow of construction area. Large channel can be
current can prevent flow around the site for the
steel or wooden frame with a wood coating, and
installation of a temporary tube of wood or metal
smaller channels may be of metal construction,
or the pipe, or the flow may be impounded
behind the dam during its construction, pumps pipe, etc. During construction of the dam
Canyon Ferry, steel-framed, wood-lined canal
that are used if necessary to control the surface
was built along the right bank of river diversion as
of water. Since it was impracticable to provide
a first step.
the ability to tunnel distracting enough to handle
the expected major spring flood,the contractor 5.10.-Deviation in multiple stages. -
made provisions to minimize the damage that
would result from overcoming the cofferdam. Method multistage deviation on the foundation
of alternative building blocks through branch
1. Making the alternate concrete blocks at low pipes in a concrete dam requires the
prey "f 'to allow overflow with minimal damage. displacement of the cofferdam construction. In
2. Construction of an auxiliary rock and a the second stage, the cofferdam is moved and
cofferdam cell steel "g" leaf-chip to protect the the current is on low blocks or duct section
digging "h" of the power plant from being flooded constructed deviation dam while work proceeds
overlaying the cofferdam. in the part of the dam.
3. Early Construction of the permanent wall "i"
training to take advantage of the protection it 5-11. Cofferdams .
produces.
The height at which to place a cofferdam built an
5-7. Tunnels. - economic study involves up to the cofferdam
shows such tunnel was built in Dam site gorge diversion works against capacity, including
Arde, a relatively narrow barrel, allow distraction routing studies design flood diversion. In addition,
by the stirrup. the design of the cofferdam should consider
The deflection system must be designed to consider the effect that the excavation and
prevent possibly also to contain part of the design drainage of the foundation of the dam on the
flood diversion. The size of the tunnel distraction stability of the cofferdam and should anticipate
and be dependent on the magnitude of the the removal, rescue and other factors.
flood distraction height upstream cofferdam Dehydration work for structural foundations,
(higher head, smaller tunnel has to be for a given building and cofferdam and movement
download), and the size of the deposit formed operations lands adjacent to streams or streams
the cofferdam if this is appreciable. An economic must be carried out so that prevent muddy water
study cofferdam height against the size of and eroded materials entering the channel.
the tunnel may be involved to establish the Thus,cofferdams are placed in such a place that
economic relationship. the earthworks near the minimum current, to
The desirability to align forwarding tunnel will be

13
DISEÑO DE PRESAS DE GRAVEDAD.

contain both the excavation work area within the


confines of cofferdams as possible.

C. REQUIREMENTS SPECIFICATION
05.12. Contractor 's responsibilities.

This general practice of requiring the contractor


to take responsibility for diversion during
construction of the dam and adjacent
structures. Also, the specifications usually require
the contractor diversion plan is subject to
approval by the owner.
In some cases, the whole scheme of deviation
can be left to the contractor, with the
expectation that flexibility contractor operations
allowing you to choose the diversion scheme will
be reflected in low bids. For example, restricting
certain schemes deviation be specified due to
safety requirements, geology, ecology or
limitations of time and space.

5-13. responsibilities of the designer. -


For situations difficult and / or dangerous
deviation may be economical for the owner to
take responsibility for the diversion plan. If the
owner is responsible for the deviation, it is
important that the deviation is realistic in all
aspects, and compatible with the probable
capacity and plant capacity building contractor.

14

Anda mungkin juga menyukai