T211 – RC Slab

Method Statement

for

RC Floor Slab Construction

Prepared by: Review by: Review by: Approved by:

Li Jian Jia Huang Rong Zhao Xuebing

Project Manager Project Director Director

CREC CREC

Signature Signature Signature Signature

Date Date Date Date

CONTENTS

Page 1 of 11
T211 – RC Slab

1. Scope of work

2. Resources

3. Work Sequences

Appendix 1 : Risk Assessment

Appendix 2 : Safe Work Procedure

Page 2 of 11
T211 – RC Slab

1. SCOPE Of WORK

This method statement is refer to the construction of tunnel RC floor slab of this project

2. RESOURCES

2.1 Machinery & Equipment

1) Concrete Vibrators

2) Air compressor

3) Rebar Cutting Machine

4) Rebar Bending Machine

5) Generator (by Main-con)

6) Air Breaker

7) RAMP for Forklift (by Main-con)

8) Forklift (by Main-con)

9) 0.7 m3 Concrete Bucket

2.2 Materials

1) Concrete by Main-con

2) 12m Straight Bar and/or BRC mesh by Main-con

3) Retarder for CJ (Refer to appendix 1)

4) Curing material : Curing compound

5) Plywood (2.44m x 1.22m x 18mm thk)

6) Concrete Spacer Block

7) Hy-rib mesh (construction joint)

8) E&M Cast – in –items ( by other )

9) Pre-cut wire and bar chair

Page 3 of 11
T211 – RC Slab

3. WORK SEQUENCE

3.1 Hacking Works

1) Provide necessary protection works for the existing works. (Canvas or other materials)

2) Use Air-compressor breakers to hack the existing RC slab up to 500mm thk, leave the
last 10mm thk RC slab. Use light breaker to hack till the Pre-cast segment.

3.2 Rebar installation

1) The fabricated rebar shall be hoisted down to the loading bay in beneath and transfer
to the working area by manually or by trolley.
2) The fabricated rebar shall be installed according to the shop drawing and supported
by spacer block at bottom layer to maintain the required cover and fix with Grade 20
GI wire at a randomly alternate spacing.

3) Install M&E Item if any. (by Others)

4) Using Hilti HY 150 drill for Starter Bar from existing RC wall

5) The bottom bar will be installed by steel fixers followed construction drawing. Refer to
Picture A.

6) The top reinforcement bar will only be installed after completion of bottom bar.

7) Bar chair installation if request.

8) The top bar and links will be installed by steel fixers.

9) Fix R6 bar shall be welded to top bar at c/c 1500mm, mark color tape the casting level
on the R6 bar to control the casting level.

10) Inspection shall be arranged after the completion of rebar installation.

11) Side formwork shall carry out according to the structural alignment provided by the
land surveyor after the rebar inspection.

Page 4 of 11
T211 – RC Slab

Picture A.

3.3 Level Control

1) Crec shall provide the level control at the scupper drain area and main-on for level
control wall area every 3m.

2) Installation half diameter PVC Pipe at scupper drain.

3) Fix R6 bar and R6 U bar to maintain the PVC Pipe elevation and alignment during
casting.

4) R6 bar with color tape shall be used to indicate the designated casting level where it
shall be welded to top layer of rebar.

5) The R6 bar and R6 U bar shall be removed after the curing.

6) The PVC pipe shall be removed after the curing.

Page 5 of 11
T211 – RC Slab

R6 U bar 1.5m
Level Control by MainCon spacing Level Control by MainCon
Level Control by Crec Level Control by Crec
2% slope 2% slope

Half Diameter T1 rebar


PVC Pipe
T2 rebar
R6 rebar 1.5m R6 rebar 1.5m
R6 bar welded top
spacing bar spacing
B2 rebar

Starter Bar
B1 rebar
Starter Bar

Starter Bar

Note: Using Hilti Hy 150 Drill 50mm depth for Starter Bar from Existing RC Wall

3.4 Concreting

1) The engineer in- charge / supervisor must check and ensure that latest approved
shop drawings and are used for construction purpose.

2) The engineer/supervisor in-charge must also co-ordinate closely with the Project
coordination team to retrieve the latest information on the services penetration
and openings including all cast-in element or embedded items.

3) A process of inspection will be conducted in the presence of QP(S) and contractor's


representatives.

4) We will do a temporary working platform before casting.

5) When all the above is done, the engineer/supervisor will proceed to order the
concrete and inform alt relevant parties of the estimate concrete arrival time.

Page 6 of 11
T211 – RC Slab

6) CREC site supervisor will coordinate with the batching plant to ensure an optimal
number of concrete trucks on standby, to ensure smooth continuous pumping and
with minimal waiting time.

7) CREC site supervisor, on arrival of each truck, shall check the concrete delivery
order to ensure the correct grade and type of concrete is dispatched.

8) Upon confirmation, the site supervisor on ground level will inform the supervisor
and foreman at the casting area that the concrete had arrived and will start to
pump.

3.5 Casting Sequence

1) The casting shall start from one corner and moving forwards to the Construction Joint
direction, max. 20 meters length.

Construction Joint
HY-Rib Mesh

Note: Maximum 20 meter spacing for Construction Joint


Every Construction Joint Use HY-Rib Mesh

2) HY-Rib mesh will be proposed for CJ and for the rebar protruding area to prevent
concrete grout loss/leaking. All hy-rib material shall not left inside inside slab in
permanent stage.

3) The casting process for the slab basically operated with the help of concrete pump and
stationary pump to deliver concrete materials to the casting area though the
temporary structure opening.

Page 7 of 11
T211 – RC Slab

4) If the stationary pump will not reach the casting area will use forklift and concrete
bucket to transfer the concrete material up to the casting area.

Casting Sequence

5) The concrete shall be deposited in horizontal layers not exceeding 300mm height or
any deeper than the length of the vibrator poker head.

6) The poker shall extend 100mm below the layer being compacted during placing of 2 nd
layers of concrete to knit the two layers together.

400mm 300mm
100mm

Bottom layer 300mm

Vibration for bottom and top layer of concrete.

Page 8 of 11
T211 – RC Slab

7) Placing concrete with Max.500mm per layer.

8) Foreman or supervisor shall randomly check on the fresh place concrete by using a
steel rod (soft or start harden) to avoid cold joint formation.

9) The concrete surface shall level by wooden or steel trowel to achieve a uniform
flat surface upon concrete reaches to the casting level.

10) Before curing, we use trowel to smooth the concrete surface by using aluminum
level bar to make sure the level of the concrete is correct to the design level.

Page 9 of 11
T211 – RC Slab

Appendix 1

Risk Assessment

Page 10 of 11
T211 – RC Slab

Appendix 2

Safe Work Procedure

Page 11 of 11