Anda di halaman 1dari 1

SN Description Unit

1 Sand Gravel Piling m3


Construction of Sand Gravel Piling and conducting suitable tests all complete for 25
numbers 1m diameter of piles including supply of suitable material and required
excavation, extended from foundation base level to firm ground (2 m - 2.5 m depth) as
shown in drawing or as instructed by the engineer . The Sand and gravel shall be mixed in
ratio of 30 % sand and 70 % gravel and shall be compacted to 98 % MDD. The compaction
shall be confirmed by field density test. And the safe bearing capacity of firm ground shall
be 120 KN/m2, which shall be confirmed by Plate load test at minimum three locations.

Anda mungkin juga menyukai