Anda di halaman 1dari 6

IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 17, NO.

2, MAY 2002 445

Controlling Grid Integrity After


Power System Emergencies
W. R. Lachs, Fellow, IEEE

Abstract—An emergency strategy for dealing with multiple con- against predicted disturbances. The paper develops a strategy
tingencies that can lead to system voltage instability has been in- that would allow timely, automatic responses able to adapt to
corporated into a program for studying post-disturbance power unexpected multiple contingencies that can occur anywhere on
system dynamic events. Pattern recognition allows simple logic for
a practical and reliable means of safeguarding the grid and of- an interconnected grid. The process of developing the strategy
fering a means for preventing the multimillion dollar collapses that meant uncovering deficient assumptions, questioning present
befall worldwide interconnected systems. The proposed automatic approaches, and properly defining the task. A general strategy
arrangement only needs low cost measures and is able adapt to for most power system emergencies is outlined, but the specific
multiple contingencies. The timely responses to emergencies would objective has been to control system voltage stability, the most
allow higher power flows on lines constrained for system voltage
stability as well as raising security levels by taking advantage of prevalent cause of disruption on interconnection power systems.
the initial system resilience without need for its costly augmenta-
tion.
II. AUTOMATIC EMERGENCY CONTROL
Index Terms—Automatic emergency control, multiple contin-
gencies, system collapse, system voltage instability. Considerable research effort continues to be devoted to power
system breakdown and collapse without as yet gaining its prac-
I. INTRODUCTION tical resolution. The approach taken has been to divide the task
into separate compartments in an effort at simplification but this

P OWER systems are replete with automatic controls and


protections to ensure fast, timely responses to multitudes
of shocks that constantly strike power systems. But for more
approach fails to gain a perspective on the overall power system
issues. Also assumptions embedded as “accepted wisdom” have
impeded efforts to resolve the task. Instead it has been assessed
severe unexpected disturbances, no automatic supports are pro- as a total system problem with all assumptions being critically
vided leaving slow manual responses of operators to deal with
questioned. Just as important is the clear formulation of the ob-
fast post-disturbance phenomena, mostly without success. The
jectives, to resolve the following issues.
Electricity Supply Industry devotes effort and capital to ensure
that the power system is sufficiently robust to survive a range of — Planning criteria only assess predictable disturbances.
severe disturbances at periods of highest demand. Nonetheless, — Extensive blackouts have followed multiple contingen-
interconnected power systems throughout the world are being cies more severe than those considered by planning cri-
subjected to widespread and lengthy blackouts, such as those to teria.
the North American Western Interconnection on July 2, 1996 — Multiple contingencies can occur anywhere on the
and August 10, 1996, which interrupted millions of consumers grid.
costing the community one billion dollars [1]. The most costly — Disturbance identification is only possible after the
interruptions have occurred after the EHV transmission line net- event.
work has been disrupted and this has invariably followed mul- — After its identification, timely and appropriate re-
tiple contingencies, more severe than any considered in planning sponses must be triggered if grid integrity is to be
the power system. sustained.
This has highlighted a deficiency of existing protections that — The control arrangement must be reliable insofar that
safeguard individual system elements but not the integrity of it functions correctly when it is needed.
the transmission grid. By default, system operators form the last
line of defense against such unpredictable multiple contingen- A. Engineering Solution
cies but their inability to initiate timely responses, not unexpect- Underlying the efforts is the need to find a satisfactory engi-
edly, has culminated in the demise of power systems [2]–[4]. It is neering solution within the following guidelines.
clearly unsatisfactory that operators do not have automatic sup-
— Engineering is the art of finding practical and cost-
port for disturbances more severe than those against which au-
effective solutions.
tomatic controls and protections are provided. The deficiency is
— The first step is to correctly understand the problem
as a consequence of existing measures only having been devised
that is being addressed.
— The path to a solution needs an intimate understanding
Manuscript received October 17, 2000; revised August 9, 2001. of problem phenomena.
The author is with the School of Electrical Engineering, University of New
South Wales, Sydney, Australia (e-mail: w.lachs@ieee.org). — The best engineering solutions are simple, reliable, and
Publisher Item Identifier S 0885-8950(02)03817-8. of minimal cost.
0885-8950/02$17.00 © 2002 IEEE
446 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 17, NO. 2, MAY 2002

A primary step is to assess the reasons why present power A knee-jerk reaction has been to consider the low probability
system planning methods are unable to deal with multiple con- of such dangerous multiple contingencies. Probability methods
tingencies and find a better approach. A practical control of have estimated such blackouts can occur once in 50 years yet
system voltage stability must incorporate a means of timely the two 1996 North American Western Interconnection black-
identification as well as devising measures to deal with post-dis- outs occurred within six weeks. If anything it demonstrates the
turbance phenomena. To achieve these objectives there must be incorrect assumptions incorporated into probability evaluations.
a full understanding of the post-disturbance phenomena by sim- Regrettably the situation will become progressively worse if the
ulating the events leading to collapse. There is also need to re- problem is not tackled, with the greater vulnerability of grids to
assess present methods of hierarchical control to find a simpler such disturbances as line power flows increase. This will be in-
and more reliable approach. evitable with a continual growth of electricity demand coupled
with the almost impossible task of gaining additional transmis-
sion lines to reinforce the EHV grid. An approach is described
III. DANGER OF MULTIPLE CONTINGENCIES which can deal with the unpredictable multiple disturbances that
pose the prevailing threat to power systems and for this three
With the importance of reliable electricity supplies to the guidelines have been followed.
community, considerable effort and expense is devoted to pro- 1) to question areas of “accepted wisdom” and assumptions;
tecting and reinforcing the power system. Planning criteria have 2) to gain better understanding of post-disturbance phe-
been developed to define a wide range of disturbances that must nomena;
be successfully withstood. Power systems are most vulnerable 3) to devise simple and practical solutions.
on the day of annual peak so planning criteria consider a number
of single contingencies at the heaviest demand. To allow for A. Clue From the July 2, 1996 Incident
its continuing evolution the power system is reviewed annually,
Identical multiple contingencies on July 2 and 3, 1996, offer
using the forecast peak demand for the studies. If the system is
a vital clue for dealing with system voltage instability. Shortly
found vulnerable to any of the examined disturbances, it is re-
after 2 p.m. on both days, a flashover tripped a 345 kV between
inforced or specific measures are devised to overcome such a
Wyoming (Jim Bridger Power Station) and Idaho when a pro-
weakness. The next question is why planning criteria that have
tection malfunction at the power station tripped another, leaving
previously proven satisfactory can no longer avoid blackouts.
only one 345 kV line to Idaho. On July 2, this led to system
Planning criteria were devised in an era when many utilities
voltage instability, disrupting the North American Western In-
were self-sufficient in generating resources and power stations
terconnection; 11 power stations shut down and 2 million con-
were operating in cities, near the main load concentrations. The
sumers were lost [2]. On July 3, with no automatic support and
power stations were in service at peak periods and could sup-
only guided by increase of excitation and reduction of voltage,
port city loads whenever there were disturbances. As the power
operators shed 700 MW at Boise, so holding the interconnec-
system could handle single contingencies at annual peak de-
tion. If operators have responded, the same indicators can also
mand, it was assumed capable of handling more severe distur-
be used to drive an arrangement that can automatically safe-
bances at lesser load periods. The character of power systems
guard system voltage stability.
has been altered with the steadily increasing importance of the
EHV transmission network. In the immediate post-World War
II era, EHV interconnections mainly served to share generator IV. UNDERSTANDING THE PHYSICAL PHENOMENA
reserves and were usually not heavily loaded except under rare The first need has been to understand the post-disturbance
emergencies. The 1973 to 1974 oil crisis led to reducing oper- phenomena that culminate in loss of system voltage stability
ation of costly oil fired power stations and in turn led to much and collapse. Predominantly, efforts have concentrated on the
higher loading on the EHV grid. Subsequently, community en- use of a complex mathematical model of the power system, in-
vironmental concerns have led to the permanent retirement of corporating assumptions to more readily gain a computer solu-
city power stations so that the interconnected EHV has become tion. Assumptions create a divergence from real situations and
the critical link between electricity consumers and the now dis- undermine the understanding of post-disturbance events. Inci-
tant power stations. With the present power system evolution, dents culminating in collapse have reported an initial stable pe-
keeping interconnected grid integrity is essential, yet multiple riod lasting up to several minutes with a normal level of fre-
contingencies continue to disrupt grids and so cause extensive, quency until the final seconds of collapse [3], [4]. The suc-
long duration blackouts. ceeding disruptive phase has described sudden widespread ef-
System planning criteria that assess single and double con- fects throughout the interconnected network that caused its dis-
tingencies are proving inadequate and this becomes clear by ruption. Consequently, the total network must be considered, as
considering a small 30 element grid. Although small, this has a simplified model could not properly assess the overall reac-
2 or over one billion connection modes with only one not tive power changes in the post-disturbance period. Therefore,
an outage. This network can have 30 single contingencies and a load flow approach has been adopted as it allows the en-
30 29 double contingencies, or a total of 900 that could be tire network to be modeled without simplifications or assump-
examined by planning criteria. This leaves one billion multiple tions. Each load flow study evaluates and records the current and
contingencies not examined and until this deficiency is tackled, voltage on every system element, so providing a computer ana-
all power systems remain at risk of disruption. logue of the power system. All incidents of system voltage insta-
LACHS: CONTROLLING GRID INTEGRITY AFTER POWER SYSTEM EMERGENCIES 447

bility have described a similar chain of stochastic changes and makes it clear that system breakdown can only be prevented
these have been used as blueprint for a series of a power system by effectively diminishing the post-disturbance phenomena. For
load flows that have replicated both the first slow and the second this, timely measures must be automatically triggered to prevent
disruptive phases. To reach this point required a careful assess- their dangerous uncoordinated responses.
ment of the responses to post-disturbance events of individual
elements, such as generators and transformer tap changers. Post-
disturbance phenomena leading to system voltage instability are VI. HIERARCHICAL CONTROL
simulated as a series of discontinuous events. To ensure accurate
The control of power systems currently uses a hierarchical
reactive outputs on all rotating units, all generator transformers
communications structure, called the Energy Management
were included so that excessive overexcitation on just one unit
System (EMS), whose intelligence is centralized at the main
could be identified [5], [6].
control centre. The EMS requires information from the entire
The output of each of the load flows culminating in break-
power system and even for operational control under nondis-
down was minutely scrutinized to determine the locations and
turbed conditions, sophisticated programming of the central
the system elements where significant changes had occurred.
computer is required. A severe disturbance that threatens power
During the first slow phase, the high reactive power output of
system integrity creates an avalanche of extra information that
rotating units in the vicinity of the affected region effectively
cannot be corrected by state estimation programs because of the
shielded the remainder of the network from the disturbance ef-
need for timely responses. Nonetheless, the complex control
fects, making it initially a local problem. With the onset of
software must still resolve the following six issues.
the second disruptive phase, when one rotating unit’s reactive
output was abruptly curtailed and then additional units were re- 1) The type of emergency must be identified.
stricted, the voltage reductions drew increasing amounts of re- 2) The severity of the disturbance must be assessed.
active power from ever widening areas of the network, making it 3) Measures to deal with this severity must be selected.
a system problem. Such detail, which has been essential for de- 4) The locations where they must act must be pinpointed.
vising a solution, has been inaccessible when complex software 5) Delays in sending signals over the communications net-
is used to model the collapse process so demonstrating a pitfall work must be corrected.
with such methods in gaining a practical engineering solution. 6) All this must be completed in time to give effective re-
The simulation has been essential for testing different measures sponses.
and then devising a control strategy. With lack of accuracy and the large volume of information,
it is an overwhelming task to develop software that can deal
with all these issues by means of a central computer. Added to
V. POWER SYSTEM BREAKDOWN achieving timely actions is the basic need for high reliability
As well as correctly identifying the problem it is just as im- in responding to severe, unforeseeable disturbances. These con-
portant to ask the right questions. siderations show the insurmountable difficulties associated with
The key question is “how does the power system break- choosing the path of centralized emergency control.
down?” Why then do power systems turn the practical hierarchy up-
There are multitudes of automatic protections provided on side down with control directed from the apex?
the power system. For a direct fault on any line or piece of This control structure was used more than 50 years ago, when
equipment, its protection trips in a fraction of a second, both operators at main control centres supervised operation of the
to safeguard it from further damage as well as to safeguard the power system. There was then far less automation without most
power system itself. The power system has sufficient resilience of the current technological innovations. The current structure
to withstand a direct fault on an EHV line, when the protection of EMS is another example of how the assumptions embedded in
acts correctly. Yet when no fast protection acts, the danger of “conventional wisdom” hinder a practical solution for the emer-
power system breakdown arises. This shows that when the dis- gency control of interconnected power systems. In contrast, uti-
turbance is not dealt with promptly, uncontrolled after effects lizing distributed intelligence for power system emergency con-
will continue to flow through the network and will actuate re- trol can overcome these bottlenecks.
sponses from back-up control devices. These are widely dis-
tributed throughout the power system and include turbo-gen-
erator governors, automatic voltage regulators, boiler controls VII. DEALING WITH SYSTEM VOLTAGE STABILITY
with coal-fired power stations and automatic transformer tap Any medical practitioner will testify that an ailment cannot
changing. During uncontrolled post-disturbance events, the de- be cured by only treating symptoms—a cure first requires the
vices have the following three intrinsic deficiencies cause to be identified. The Western Interconnection was divided
1) Each group functions at different rates, seconds to min- into five separate islands in the July and August 1996 incidents
utes by reactions to symptoms but not the cause [2]. By the time the
2) Each individually has actions that respond only to symptoms evolved, intergenerator oscillations were sundering
changes in its immediate vicinity synchronizing forces and power system disruption was well ad-
3) Not one of them acts in coordination with any other. vanced. A satisfactory approach must deal with the cause of
Their disparate actions in response to chaotic post-disturbance breakdown before conditions deteriorate to set up unsustainable
phenomena is the cause of system breakdown. This recognition oscillations between separate groups of generators. In tackling
448 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 17, NO. 2, MAY 2002

system voltage instability that follows multiple contingencies, C. Emergency Strategy


the following issues must be dealt with. The elements needed for the emergency strategy to safeguard
— The critical disturbance could occur anywhere on the against system voltage instability have been presented.
grid. — The identifying parameters, voltage reductions and ro-
— The disturbance cannot be predicted. tating unit excitation increases.
— Disturbance after-effects must be controlled before — They are used with a distributed intelligence.
uncoordinated responses of back-up devices are acti- — Countermeasures, including strategic load shedding,
vated. have been assessed.
— The integrity of the grid must be sustained. The method of integrating them into the emergency strategy
Hence a hierarchical control structure with a distributed intel- has been the culmination of extensive dynamic simulation
ligence would fulfil these needs. To respond effectively, iden- studies. The key findings for this purpose have been the
tifiable changes must be swiftly discerned at localities on the following.
grid that are affected by a disturbance so as to trigger timely — The magnitude of parameter changes to identify the
responses. Essentially countermeasures should be made at af- threat to system voltage instability.
fected points while the grid remains intact, as the best means — Measures are only needed at locations that have shown
of eliminating the post-disturbance phenomena that otherwise substantial parameter changes.
lead to its breakdown. Such an approach should be taken to deal — The grid is saved by preventing the second disruptive
with all causes of power system breakdown, but here the attack phase.
is only focused on dealing with system voltage stability. — The distributed intelligence continues to respond until
not one unit exceeds its rated excitation.
A. Seeking the Identifying Parameters — The voltage reduction at each affected EHV substation
The first requirement in implementing a distributed intelli- is used to quantify the amount of load (strategic) shed-
gence for controlling system emergencies has been to unearth ding.
the parameter changes that can identify the danger. Reported — Most of the selected measures precede load shedding,
incidents of system voltage instability and collapse have de- with timings based on dynamic studies.
scribed the characteristic symptoms of sustained sharp reduc- — With the disturbance severity, the power angle across
tions of transmission voltage levels in conjunction with increase the grid is unduly large, even after load shedding.
of reactive power outputs on rotating units [2]–[4]. — This requires a measure to reduce the power angle.
The successful simulation of post-disturbance events by a — Measures continue to respond until parameter changes
series of load flows have replicated the reported characteristic have been practically eliminated as this shows that
changes of voltages and rotating unit reactive power outputs, re- post-disturbance phenomena have been damped out.
ferred to in Section IV [5], [6]. Simulation studies for multiple The definition of system voltage instability was formulated and
contingencies at many parts of an interconnected EHV network, proved the key to devising the emergency strategy.
allowed the parameter changes to be calibrated for identifying System voltage stability is threatened when a disturbance
dangerous disturbances. Any direct fault on the EHV grid would increases the reactive power demand beyond the sustainable
initially provoke similar parameter changes, except they would capacity of the available reactive power resources [7].
disappear when the protection clears the fault. Consequently, a The emergency strategy hinges on pattern recognition as the
delay of longer than the slowest protection is needed to correctly driver of the distributed intelligence and its great advantage is
identify the threat to system voltage stability. the immediate identification of a disturbance with simple logic.
Parameter changes need to be calibrated to allow control logic to
B. Developing Effective, Low Cost Countermeasures make a YES/NO decision while simultaneously pinpointing lo-
The next requirement after devising pattern recognition for calities where responses are needed to control post-disturbance
identification has been to devise effective, low cost countermea- events.
sures. The simulation load flow method that could replicate the An inadvertent real-life demonstration of the emergency
dynamic sequence of post-disturbance events provided the tool strategy occurred on July 3, 1996, when operators reacted to
with which countermeasures could be assessed. the symptoms of unit excitation increases and reduction of
The most powerful measure is strategic load shedding which voltages, by shedding 700 MW at Boise and thereby regaining
minimizes the amount shed by finding the optimum locations. system voltage stability and keeping the grid intact.
Strategic load shedding could regain system voltage stability
by itself, but with the initial slow phase, there is time for other D. Testing the Emergency Strategy
measures that can reduce the amount of shedding. Low cost The simulation program that directed an existing load flow
measures that could respond quickly enough and whose action program was amended to include the emergency strategy. By in-
would not inconvenience any consumer were examined. For cluding measures the program provided a prototype of a system
the power system under investigation, the measures adopted protection for guarding system voltage stability.
included fast tap changing on EHV substation transformers, Extensive studies have been undertaken on a number of in-
raising synchronous condenser and generator terminal voltages, terconnected networks on which multiple contingencies at di-
and fast tap changing on generator transformers [6]. verse locations of each were examined. In every case the emer-
LACHS: CONTROLLING GRID INTEGRITY AFTER POWER SYSTEM EMERGENCIES 449

gency strategy prevented disruption of the interconnection from F. Planning Resource


system voltage stability. Rather than trying to present results of The final step has been to integrate the guidance software
many studies, one extremely severe outage has been described into a new load flow program, devised for a Personal Computer,
to illustrate the spectacular success of the emergency strategy. capable of handling networks with as many as 15 000 busbars
This example describes the simultaneous loss of 5 EHV lines [7]. This program requires the data used for an existing load
on a 92 bus, 15 000 MW system, that would otherwise have suf- flow program, the “bread and butter” tool used by power system
fered system voltage instability. For a perspective of the emer- planners. It is also necessary to nominate measures to respond
gency strategy, a number of diagrams compare post-disturbance to the post-disturbance effects of disturbances.
changes of one selected parameter in the safeguarded and col- The program allows power systems to be assessed for
lapse mode [6], [7]. The timing of measures in safeguarding the multiple contingencies well beyond the scope of disturbances
grid, including shedding 1000 MW at affected substations as considered by present planning criteria. This would be an im-
well as dynamic post-disturbance events, are described. portant step in implementing the automatic emergency control.
The low cost to install the protection would improve operational
E. Revolutionizing Reactive Power Planning security on the EHV grid, and allow a better utilization of
the network’s capability. This contrasts to existing planning
The prevailing approach to reactive power planning of large methods that require heavy capital expenditures in reinforcing
power systems is extremely time consuming even though it is the power system to improve its load carrying capability. The
limited to annual studies of single and perhaps double con- studies would demonstrate that automatic measures, using pat-
tingencies. For each vulnerable case, means must be devised tern recognition and responding after otherwise unpredictable
against the threat to voltage stability, a task made more difficult contingencies, could sustain system voltage stability and avert
by the diversity of disturbance locations. Reinforcing the EHV collapses such as occurred on the Western Interconnection in
grid would be a good solution but now is almost impossible July and August 1996.
with the financial and environmental constraints so that one of
three following approaches is usually adopted. VIII. CONCLUSION
1) Devise a special purpose protection for each situation. This paper shows a method for establishing a system protec-
2) Constrain the power flow on an EHV transmission line. tion that can automatically safeguard grid integrity against the
3) Provide additional reactive power compensation. threat of system voltage instability. The arrangement responds
Each of these approaches has a deficiency, apart from being to multiple contingencies on the grid with an emergency strategy
only applicable to a foreseeable disturbance. that can to adapt to any unexpectedly severe disturbance.
The highest priority is given to its reliability, a vital need of
1) Each special purpose protection must be checked for co- all practical protection schemes. The intrinsincally simple ap-
ordination with other protections. proach of the proposal would facilitate its rapid establishment
2) Higher electricity costs result at heavy load periods when at a minimal cost.
line power flows are constrained. The 20-year effort toward this development was prompted
3) The provision of extra reactive resources requires capital by recognizing weaknesses in prevailing methods for tackling
expenditure yet each addition would only support a lim- the control of power system emergencies. Consider that power
ited region. An unacceptable outlay would be needed to system development allows for single and double contingencies
combat the multitude of disturbances that can occur on whereas system voltage instability has followed multiple con-
the grid. tingencies. Current emergency control efforts focus on central-
In contrast, the emergency strategy offers automatic re- ized energy management systems at the main control centres for
sponses to multiple contingencies at any point of the grid. The which elaborate software, incorporating a mathematical model
reason for the emergency strategy’s effectiveness is its ability of the power system must sift through the avalanche of data cre-
to eliminate excessive reactive power demand in the affected ated following a disturbance. This approach is not reliable nor
localities within the initial post-disturbance phase. Thereby the can it achieve timely responses to prevent the disturbance. Then
sustainable capacity of existing resources can continue to meet the uncoordinated responses of back-up devices would produce
the interconnected system’s reactive power demand even for system breakdown when post-disturbance phenomena persist.
unexpectedly severe disturbances. The important step on the path to developing the automatic
Because of its automatic responses as well as its ability to emergency control has been successful simulation of the post-
adapt to any prevailing disturbance it opens a new frontier in disturbance first slow and second fast phases, culminating in
system reactive power planning. These automatic responses in system voltage instability. With this resource the elements for a
curtailing the excessive reactive demand can allow the post-dis- system protection arrangement were uncovered, including iden-
turbance demand (after its action) to met by the available reac- tifying parameter changes, effective measures and an emergency
tive power resources. This inherent ability to adapt to any mul- strategy. Threatening situations can be identified by pre-cali-
tiple contingency would eliminate the tedious task of examining brated changes of voltage and rotating unit excitation, lending it-
a multitude of disturbances. Engineers would only need to ex- self to a distributed intelligence capable of responding to distur-
amine a sufficient number of multiple contingencies to be as- bances anywhere on the power system. The emergency strategy
sured that the emergency strategy would be effective. curtails post-disturbance after-effects by directing measures to
450 IEEE TRANSACTIONS ON POWER SYSTEMS, VOL. 17, NO. 2, MAY 2002

the affected region. Thereby the excessive reactive demand is These and other advantages offered by the proposal would
eliminated with the important benefit of permitting existing re- gain multimillion dollar benefits in power system operation and
active resources can maintain voltage control. control. The Electric Supply Industry would be remiss not to
An Automatic Voltage Stability program, incorporating the grasp such a practical and cost-effective opportunity.
emergency strategy, has been developed that can evaluate all
post-disturbance dynamic events that follow a multiple contin-
gency. It has been extensively tested, dealing with the simulta- REFERENCES
neous loss of 5 EHV lines on a 15 000 MW, 92 bus system by [1] J. A. Casazza, “An American’s view of the reorganization of the ESI,”
shedding 1000 MW [6]. Power Eng. J., vol. 11, no. 2, pp. 79–84, Apr. 1997.
[2] C. W. Taylor and D. C. Erickson, “Recording and analyzing the July 2
Of particular note are the events of 3rd July 1996 when op- cascading outage,” Comput. Applicat. Power Syst., vol. 10, no. 1, pp.
erators, reacting to excessive unit excitation and low voltages, 26–30, Jan. 1997.
shed 700 MW at Boise and so kept intact the North American [3] A. Cheimanoff and C. Corroyer, “The power failure of December 19,
1978,” in RGE Tome 89, April 1980, pp. 280–296.
Western Interconnection. On July 2, 1996, the identical contin- [4] Cigre Task Force TF-38-01-03, “Planning against voltage collapse,”
gency split the grid into five islands, interrupted 2 million con- Electra, no. 111, pp. 115–127, Mar. 1987.
sumers, and shut down 11 power stations [2]. The fact that op- [5] W. R. Lachs, “System reactive power limitations,” in Proc. IEEE Winter
Power Meeting, New York, NY, Feb. 1979, Paper A79 015-9.
erators were able to identify the changes and respond without [6] W. R. Lachs and D. Sutanto, “Voltage instability in interconnected power
prior training underlines the intrinsic simplicity of the emer- systems: A simulation approach,” IEEE Trans. Power Syst., vol. 7, pp.
gency strategy. This incident confirms that a straightforward ap- 753–761, May 1992.
[7] , “Protection for the transmission grid,” in Proc. Sixth Int. Conf.
proach can deal with the dynamic phenomena that otherwise Developments Power Syst. Protection, Mar. 25–27, 1997, pp. 201–205.
lead to system voltage instability.
Besides offering a low cost, reliable solution to a seemingly
insoluble problem the system protection has practical advan-
tages. The first being that SCADA networks already monitor
EHV voltages and rotating unit power outputs, the very param-
eters needed for the proposal. By contrast with complex EMS W. R. Lachs (M’78–SM’85–F’94) received the B.E. degree in mechanical and
software that takes a year to commission, its simple pattern electrical engineering and the M.Eng. degree in electrical engineering from
Sydney University, Sydney, Australia, and the Ph.D degree from the University
recognition software can be quickly tested and commissioned. of New South Wales, Sydney, Australia, in 1953, 1972, and 1992, respectively.
When operational, the proposed system protection would Since 1953, he worked in the Snowy Mountains Hydro-Electric Authority,
overcome the most intractab le problems bedeviling large Cooma, Australia, in communications, contracts, and system planning
branches. On moving to the Electricity Commission of New South Wales,
power systems: Sydney, Australia, he gained experience in substation design, power system
1) enhancing operational security without heavy capital ex- auxiliaries, system operation, system investigations, system planning, and
penditures; research and development coordination. Since 1988, he has undertaken full
time research at the University of New South Wales on the automatic control
2) allowing better use of system capabilities; of power system emergencies.
3) greatly reducing the danger of multimillion dollar system Dr. Lachs is a member of the IEEE Power System Stability Subcommittee
collapses; and of the CICGRE Task Force 38–02–24 “Defense Plans Against Extreme
Contingencies.” He has made submissions to CIGRE Task Forces 38-02-10 and
4) providing automatic operator support for system emer- 38-02-12. He is Fellow Search Chairman of the IEEE New South Wales Section
gencies (reducing the risk of operator errors). Committee.

Anda mungkin juga menyukai