REPUBLIC OF THE PHILIPPINES

DEPARTMENT OF AGRARIAN REFORM MONITORING


MinSAAD REPORT
Mindanao Sustainable Agrarian and Agriculture
Development Project

SUBPROJECT NAME INSPECTION DATE WEATHER


Construction of Cadiis PHF (Solar Dryer) March 16, 2018 Sunny
SUBPROJECT ID NO. SUBPROJECT LOCATION RESETTLEMENT AREA
15-5050104001- 001 Cadiis, Carmen, Cotabato NC SA 1
START DATE TARGET COMPLETION DATE ACCOMPLISHMENT
November 3, 2017 December 18, 2018 (For Revision) PHY (95%) FIN (N/A)
CONTRACTOR NAME IMPLEMENTING AGENCY CONTRACT COST
Alzen Engineering and Construction Supplies LGU Carmen PhP 611,219.03
DESCRIPTION OF
ITEM ISSUES / FINDINGS / OBSERVATIONS RECOMMENDATIONS
WORKS
1 Solar Dryer Finishing on the walls of canal and curbs Smoothen the finish of solar dryer
of the solar dryer are still rough and its canals as per plan
2 Project Marker / Not yet installed. Materials are already at Install the permanent signboard
Signboard the project site. beside the solar dryer. Make sure
the writings and drawings on the
signboard plate is permanent, i.e.,
painted/permanent print/not in
tarpaulin
ATTENDANCE : Engr. Bennette Jae Soledad (PPMO Infra Coordinator), Engr. Benjamin Patricio III (Engineer I, LGU Carmen)

PHOTO DOCUMENTATION

Figure 1 Solar Dryer Figure 2 Surfaces on curbs and walls of the canals are rought. Must be
finished with smooth surface.

Figure 3 Another angle of the solar dryer facing east. Figure 4 Surfaces on curbs and walls of the canals are rought. Must be
finished with smooth surface.

PREPARED BY NOTED BY

ENGR. IAN JAN N. DALISAY ENGR. ROGER B. TABAÑAG


MPMO Rural Infrastructure Specialist Rural Infra Component Manager, DAR-MinSAAD