Cable Anchoring is the process of securing the tension cables of Cable Stayed Bridges and / or Suspension
bridges into large strong Rock Beds or Concrete Beds in the ground , that the tension in th cables is
withstood and the bridge is held in place.
These are End Ground Suports at both ends of the bridge. Tension cables are anchored deep into the
ground rock and grouted fully; OR the whole anchorage block is buried under concrete embedment.
1
5 What is the principle of bow String Bridge ? 2
Bow String Bridge, also called s Tied Arch Bridge, works on the principle, that the thrust developing on
the foundations are avoided by tting the bottom ends of the arch with a horizontal tie member
Thrust arches rely on horizontal restraint from the foundations, as shown right. The vertical and horizontal reactions resolve
into a force along the arch members – the horizontal component is of significant magnitude.
This will be the most satisfactory solution when the arch bears onto good foundation material such as competent rock. The
ends of the arches are normally pinned. However, rock is not always available and so a thrust arch will not be the most
economic solution at these locations, as the horizontal reactions lead to heavy uneconomic foundations.
Tied arch
The tied-arch offers a solution when it can be arranged that the deck is at such a level that it can carry the horizontal force as
a tie member, as shown below.
The tied-arch is sometimes referred to as a bowstring arch.
By taking the arch thrust through the tie member, the primary requirement for the substructure reduces to only carrying vertical
loads. It can be seen that one end will still require a longitudinal restraint to carry wind, braking, acceleration and skidding
forces, and that the other end is permitted to move longitudinally.
2
7 What is the need of strengthening of beams ? 2
Strengthening of Beams is required under the following condictions:
Beam weakened due ot corrosion of reibnforcement
Loads have exceeded the original estimates – in bridges due to traffic increase
--- in buildings due to change in use / function
---- in buildings due to removal of some intermediate columns
For various such reasons, beams have to be strengthened techniques like
--- Jacketing --- Wrapping --- Overlay --- Plate Bonding
3
11a ) Explain the step by step procedure of underwater construction of
Diaphragm Walls ( 13 )
Diaphragm wall-Application
Commonly used in congested areas.
Can be Installed in close proximity to existing structure.
Practically suited for deep basements.
Used in conjunction with “Top Down” construction technique.
About Diaphragmwall
Very unstable soil profiles below the water table.
Limited construction time Where deeper than normal cantilever support may be required.
Can be Installed to considerable depth.
Formation of walls with substantial thickness.
Flexible system in plan layout
Easily incorporated into Permanent works.
Designable to carry vertical loads.
Construction time of Basement can be lowered considerably.
Economic and Positive solution for large deep basement in saturated and unstable soil profiles.
Can be used for seepage control in Dams.
Noise levels limited to engine noise only.
No vibration during installation.
1. ITrenching Equipments
o Hydraulic Grab.
o Kelly-mounted or Cable-hung cam buckets.
o Mechanical Grab.
5
11 b ) Explain Large Reservoir Construction ( 13 )
The principle of all open impounding reservoirs is the same, in that they consist of a dam across a valley to impound a
natural stream of water. Typically they include overflow weirs, draw-off points and cut-off walling, or
similar constructions, to intercept stray water which may flow beneath the dam. The water quality is improved by a
treatment plant.
They tend to be constructed in an elevated position, as this reduces the pumping requirement, and means that
the structure can take a very simple form in the ground.
Open impounding reservoirs can be constructed from a range of materials, such as rock, earth, concrete or composites,
depending on the reservoir size and earth type. An earthen embankment should have a watertight concrete face or a
core of clay or concrete.
6
12. a) Explain the techniques of construction for continuous concreting
operation in tall buildings. ( 13 )
Techniques for Continuous Concreting in TALL Buildings
In Modern Construction, Tall Buildings with dozens of Floors and Storeys are constructed at a very fast – track mode.
Question refers to Continuous Concreting Operations. Thus Precast Concrete Systems are not included here.
The required Construction Techniques and Systems for Continuous Concreting Operations in TALL
Buildings can be categorized under the following heads
Concrete Technology as a Material 5 marks
Formwork Systems for faster Cycle Time 4 marks
Reinforcement Systems 4 marks
o Other Supporting Systems ( for Walling, Cladding , Finishing, Utlities, etc. )
( NOT COVERED here, since question is only about CONCRETING Operations )
Concrete Technology as a Material
Use of Rapid Hardening Cement
Using Accelerator chemical admixture with OPC Concrete, so as to reduce formwork stripping time
Use of in-situ steam curing on for cast – in – situ concrete itself, so as to accelerate hardening
Use of Self- Compacting Concrete to reduce Site Concrete Pouring Opeations Time
Use of Self- Compacting Concrete , also eliminates all field concrete vibration / compaction works
saving time and money
Use of Self- Compacting Concrete , also helps to avoid defects like honey comb, which further
require additional patch repair works after removal of formwork, which in this case can be avoided
due ot use of SCC.
Use of Self- Compacting Concrete, also helps in avoiding any damage to formwork – escpecially
joints – which is likelyu to happen due to over-vibraration
Applying Curing Compounds all concrete elements just after formwork removal, so that operations
towards water curing may be avoided and time saved.
Reinforcement Systems
Use Mechanical Couplers or Welds for Rebar splicing to reduce reinforcement congestion and also to
reduce on-site bar –bender operations
Use Welded Wire Fabric , available im Mesh forms and Cage forms for Slabs and Beams, Columns,
respectively, so that , on-site cutting and bedning and shaping and assembling operations for bar –
benders are avoided, saving time.
Even if ordinary lap splices are used for rebars, use Mechanized Tying / Wrenching Equipment for
applying the binding wires for lap splices instead of manual hand applied binding wire for lap joints
7
12 b ( i ) Briefly explain the launching techniques of post tensioning of slab
-- 5 marks
Please Note :: Question asks “explain the launching techniques of post tensioning of slab “
Launching is involved usually in BRIDGES with PRECAST Concrete Deck Slab for MULTPLE Segments of EACH
span - Precast Segmental Bridge Construction - After launching all the segnents of a span, the multiple
segments are POST – TENSIONED to integrate all the segments into a SINGLE SPAN.
Students MIGHT HAVE WRITTEN the answer for PT SLAB for Buildings (Post - Tensioned Slab )
OR FOR
PT Slab ( not covered in this key )
THE INCREMENTAL LAUNCHING METHOD IN PRESTRESSED CONCRETE BRIDGE
CONSTRUCTION
The sequence of construction is similar to traditional concrete bridge building, i.e., build the support towers
(columns), build the temporary falsework, build the deck, perform finish work. The principal differences are as
follows:
1. The support towers may be built segmentally. Often this is accomplished using "slip-form" construction,
where the falsework moves (slips) upward following sequential concrete "pours." The falsework uses the
newly constructed concrete as the basis for moving upward.
2. After the towers are built, a superstructure is built atop the towers. This superstructure serves as the
"launching" point for building the deck. (The deck is often built in both directions away from the tower,
simultaneously.)
3. The deck is now constructed sequentially, beginning at the tower, one section at a time. This process is
usually accomplished using a self propelled bridge layer that hoists the bridge section into place.
In pre-cast bridges, the concrete segment is constructed on the ground, and then transported and
hoisted into place. As the new segment is suspended in place by the crane, workers install steel
reinforcing that attaches the new segment to preceding segments. Each segment of the bridge
designed to accept connections from both preceding and succeeding segments.
The Incremental Launch Method of bridge construction is suitable for box girder sections where the
bridge is straight or has constant horizontal or vertical curvature. The method eliminates temporary
supports and is therefore, most applicable where these are impossible because of the nature of the
crossing or the support height required. The construction sequence commences behind one
abutment where a highly mechanised casting yard is set up. After the first segment is cast, a
launching nose is attached and the segment is launched out of the cast bed and into the first span.
Typically, the launch nose is about 60% of the length of the span.
The segments are launched using hydraulic jacks to either pull the segment via a “stick” or utilising
a lift-and-push system. The next segment is then cast, stressed onto the first segment, and the
9
process repeated until the entire bridge is in position. Secondary pre-stressing is then installed and
temporary bearings are replaced with permanent ones.
PRESTRESSING -- Post Tensioning
External PT suits this method well, as it reduces construction time and allows easy inspection of tendons.
Bar and Slab PT systems allow vertical weband transverse deck stressing.
Incrementally launched bridges. Well suited for bridges over congested areas and waterways. Centrical
prestressing during construction combines permanent and temporary PT.
10
Precast Segmental Span-by-Span Bridges Span-by-span construction involves the erection of all segments of a span on
a temporary support system with small closure joints cast at one or both ends next to the segments over the pier.
Figure shows typical phases for span-by-span construction.
External Tendons
For span-by-span construction, the use of external tendons provides for greater efficiency in the cross
section of the box for both longitudinal and transverse efficiency, by facilitating a web thicker at the top than
bottom. This raises the centroid of the whole cross section, and maximizes the eccentricity and efficiency of
the post-tensioning in the mid-span region needed for the dominant effect of longitudinal flexure of this
method. Figure shows a typical layout of span-by-span tendons for an interior span where all tendons
deviate at a common deviation saddle.
11
12 b ii) Explain vacuum dewatering of concrete flooring.
After the requirement of workability is over, this excess water will eventually
evaporate leaving capillary pores in the concrete. These pores result into high
permeability and less strength in the concrete. Therefore, workability and high
strength don’t go together as their requirements are contradictory to each
other.
12
most.
Mainly, four components are required in vacuum dewatering of concrete, which are given
below:
1. Vacuum pump
2. Water separator
3. Filtering pad
A rubber seal is also fitted around the filtering pad as shown in fig.1. Filtering
pad should have minimum dimension of 90cm x 60cm.
o The surface obtained after vacuum dewatering is plain and smooth due to reduced
13
shrinkage.
o The formwork can be removed early and surface can be put to use early.
The Vacuum Dewatered (VD) Flooring method, is a system for laying high quality concrete floors with superior cost-
effectiveness. The key to the use of this method is the dewatering of concrete by vacuum process. Surplus water from the
concrete is removed immediately after placing and vibration, reducing the water-cement ratio to an optimum level.
14
( 13
13. a) Explain the construction of jetties and break water structures. Marks )
OFFSHORE STRUCTURES
Offshore structures include Breakwaters and
Jetties. They are alike in construction and differ mainly in function.
In an offshore barrier, the breakwater interrupts the action of the waves of open water to create
an area of calm water between it and the shore.
A jetty works to direct and confine a current or tidal flow into a selected channel.
Breakwaters
A breakwater is a large pile of rocks built parallel to the shore. It is designed to block the
waves and the surf. Some breakwaters are below the water's surface (a submerged
breakwater). Breakwaters are usually built to provide calm waters for harbors and artificial
marinas. Submerged breakwaters are built to reduce beach erosion. These may also be
referred to as artificial "reefs."
A breakwater can be offshore, underwater or connected to the land. As with groins and
jetties, when the longshore current is interrupted, a breakwater will dramatically change
the profile of the beach. Over time, sand will accumulate towards a breakwater. Downdrift
sand will erode. A breakwater can cause millions of dollars in beach erosion in the
decades after it is built.
Types of Breakwaters
-Detached breakwater low crested structure
(breakwaters can completely isolated from the
shore)
Head land breakwaters High crested strucure
Nearshore breakwaters Rubble mound strucure
-Attached breakwater Composite structure
(Breakwaters can be connected to the shore line)
Using mass ( caissons ) Using arevetment slope
(e.g with rock or concrete armor units )
Emerged breakwaters
-Submerged breakwaters
-Floating breakwaters
15
Fig 3 COMPOSITE BREAKWATER / JETTY
Jetties
Jetties are large, man-made piles of boulders or concrete that are built on either side of a
coastal inlet. Whereas groins are built to change the effects of beach erosion, jetties are
built so that a channel to the ocean will stay open for navigation purposes. They are also
built to prevent rivermouths and streams from meandering naturally.
Jetties completely interrupt or redirect the longshore current. Just as a groin accumulates
sand on the updrift side, so do jetties. The major difference is that jetties are usually longer
than groins and therefore create larger updrift beaches at the expense of the smaller
downdrift beaches.
On East Coast barrier islands, ocean tidal inlets migrate naturally with the longshore
current. A jetty system will permanently disrupt the equilibrium of the beach. This may
seriously affect the tidal circulation and the health of the wetlands between the barrier
islands and the mainland.
Inlets with short jetties that don't quite reach the surf will clog up with sand. The sand must
be dredged on a regular basis. A "sand by-passing" system may be built to pump sand
around the jetties. The sand pumping may come from within the inlet or from the updrift
beach. These methods are expensive and must be maintained indefinitely.
CONSTRUCTION OF A BREAKWATER / JETTY
When a breakwater is to be built at a certain location, and the environmental impact of such a
structure has already been evaluated and deemed environmentally feasible, the following
parameters are required before construction can commence:
• a detailed hydrographic survey of the site *** a geotechnical investigation of the sea bed;
• a wave height investigation or hindcasting *** a material needs assessment; and
• the cross-sectional design of the structure.
Material needs assessment
Given that most breakwaters consist of either rock or concrete or a mixture of both, it is evident
that if these primary construction materials are not available in the required volume in the
vicinity of the project site, then either the materials have to be shipped in from another source (by
sea or by road) or the harbour design has to be changed to allow for the removal of the breakwater
(the site may have to be moved elsewhere).
To calculate the volume of material required to build a rock breakwater, for example, equidistant
cross sections are required. Each cross-section consists of the proposed structure outline
superimposed on a cross-section of the sea bed.
16
Rules for very small projects with water depths not exceeding 3.0 metres for
rubble mound or rock breakwaters:
• Unaided breakwater design should not be attempted in waters deeper than 3 metres.
• If the foundation material is very soft and thick, then a geotextile filter mat should be placed
under the rock to prevent it from sinking and disappearing into the mud
• If a thin layer of loose or soft material exists above a hard layer, then this should be removed to
expose the hard interface and the breakwater built on this surface.
********************************************************************************
Flattened conduit - Probably the simplest way to build a geodesic dome frame, all you do is flatten the
end of some metal tubing bend it slightly then drill a hole. Do this to both ends get yourself a bag of bolts and
you can easily build a dome framework in a day. Used for burning man, climbing frames and other small
projects.
Advantages: Really easy to build, easily assembled/disassembled, no special tools required, just make sure
you don''t split the tube when you flatten it and that you flatten enough so you can put the bend in without
interfering with other struts.
Disadvantages: Quite crude, can only be covered with material because joints don''t finish level.
Tube and hub - Another simple construction technique, slightly more work than the flattened conduit
method but is a more professional and flexible system. Instead of joining the struts directly together a larger
diameter pipe is used as a hub holes are drilled through the hub and the struts are bolted to it.
Advantages: Makes a nice neat job with all struts finishing level while still being cheap and easy to build.
Disadvantages: Great for material covers but there is no easy way to fix a hard covering material.
17
Beam and hub
Wooden beams are attached to specially made hubs to form the dome framework; the angles are taken care of
by the hubs so all you have to do is cut the beams to the correct length. More expensive to build than a tube
type framework but makes a solid permanent dome.
Advantages: Simple dome construction system that doesn''t require specialist tools or knowledge to build.
Disadvantages: The hubs can be expensive and hard to find because they have to be specially made. When the
beams have board nailed on both sides there is no way to ventilate the void between, in a heated dome this
can lead to damp, dry rot and a number of other problems.
Advantages: Simple and extremely fast way to build a permanent dome structure.
Disadvantages: Because the panels are factory made you don''t get much design choice. Ventilation problems
can occur when material is fixed to both sides.
Stressed skin
Metal or fibreglass panels are bolted/riveted together to form the dome, there are no beams, hubs or separate
support structure the skin does everything.
Advantages: Probably the most cost effective and efficient way to build a dome. Some simple fabrication is
required but this can be easily sourced locally.
Disadvantages: Metal sweats when it gets cold so some form of insulation has to be glued to the inside of the
panels to prevent condensation forming. Cutting holes for doors and windows can seriously weaken the dome
structure.
Monolithic
There are basically three stages involved in building a monolithic dome: First an airform membrane made
from PVC is inflated on the site were the dome is to be built; this acts as the out weatherproof skin on the
finished dome. Next the inside is sprayed with polyurethane foam to insulate the structure; reinforcing bar is
fixed to the foam ready for the next stage. Finally a concrete mix is sprayed on top of the urethane to finish.
Advantages: Very strong efficient structure requiring very little in the way of heating/cooling.
Disadvantages: The outer airform that acts as a weatherproof membrane can be damaged easily allowing
water into the insulation layer. Both the PVC airform and the urethane foam insulation are oil based chemical
materials, which are not that environmentally friendly. Most monolithic domes require dehumidifiers or heat
exchange systems due to the fact that they are so airtight.
Space frame
Building domes using space frame is actually quite simple, the struts are made from solid bar and they are
connected together with solid balls that have fixing points machined into them. Very commonly seen at
airports and exhibition halls. Too expensive for the DIY builder but still interesting, the Eden project was
built using a space frame.
18
Brick and former
This building method dates back hundreds of years and was also used to build arches, bridges etc. A wooden
former is made to the shape required then stone, brick, or concrete is laid on top of the former to produce the
final dome shape. The former is used to hold the brick, stone or concrete in place until it sets and is able to
support its own weight. Usually the former is removed but there is no reason why it couldn''t be left in place.
Advantages: Makes a very strong long lasting dome that can be built using reclaimed materials.
Disadvantages: A lot of expense is involved in making the former that MUST support the whole weight of the
dome when the dome is finished the former becomes redundant. Building very large domes is not cost
effective using this system.
19
14 a) Explain the strengthening of masonry wall and protection methods of
structures with neat sketch. ( 13 Marks )
Unreinforced masonry walls have good compressive strength, but they are brittle
and very weak under the action of lateral loads which causes tension in walls.
Whenever tension forces acts on a masonry wall, it tends to crack.
Uses of half brick thick masonry walls are common as partitions in the interior of
RC framed buildings. These half brick masonry walls are unsafe under the action
of lateral forces during earthquake. Out of plane strengthening of partitions can
be clubbed together with lateral strengthening of building by providing reinforced
concrete jackets to the partitions.
20
sides of the walls.
For using reinforcement jackets, first the plaster is removed from the walls.
Mortar joints between bricks are cleaned. In case of any cracks in masonry walls,
those are first grouted. Anchor ties are are inserted in pre-drilled holes. The
surface of drill is cleaned, moistened, and cement slurry is spread on the masonry
surface and in drills.
The usual total thickness of RC jackets varies from 30mm to 100mm. The
thickness depends on the method for application of concrete layers.
21
o The minimum reinforcement with which the ends of the wall are strengthened should be
0.25% of jacket section.
o The diameter of the ties at the well ends should not be less than 8 mm with a maximum
spacing of 150 mm.
o The jacket must be anchored to the old concrete with dowels spaced at no more than 600
mm in both directions.
Fig: Strengthening of Masonry Walls by Application of Single and Double sided reinforced
concrete (RC) jackets
It is also important that the jacket should be able to transfer forces to slab
diaphragms. This can be achieved by providing epoxy grouted anchors and
diagonal connecting bars through holes made in slabs.
22
14 b) Explain seismic retrofitting and sub grade water proofing.
( 13 Marks )
Part ( i ) Seismic Retrofitting - 7 marks
Part ( ii ) Sub-grade Water Proofing -- 6 marks
Part ( i ) Seismic Retrofitting - 7 marks
Seismic Retrofitting is a collection of mitigation techniques for Earthquake Engineering so that the
building already damaged by earthquake or building which ius prone to seismic attack is strengthened
so as to bring it back to functional life
It is the modification of existing structures to make them more resistant to seismic activity, ground
motion, or soil failure due to earthquakes.
The retrofit techniques are also applicable for other natural hazards such as tropical cyclones,
tornadoes, and severe winds from thunderstorms.
23
2 Adding Steel Bracings
RCC FRAME is
RIGID and BRITLLE / Less Ductile
3 COLUMN JACKETING
The existing smaller section RCC Column is
enlarged by adding new ties and main rebars
throughout its height and integrated with the
old rebars . then the whole assembly is
embedded in new strnger grade concrete
Basement Waterproofing
External Waterproofing Procedure:
24
1. The soil around the foundation is excavated
2. The weeping tiles are removed and the foundation walls are cleaned
3. Small holes are drilled into the bottom blocks to remove moisture in the wall
4. The walls and footings are coated by hand with a high quality rubberized urethane
5. Dimple board is installed with steel brackets and a finishing strip
6. New weeping tile with geotextile filter cloth are installed and connected to proper drainage
7. ¾ inch clear gravel is installed on top of the weepers to a minimum of a 1 ft depth
8. A geomembrane filter cloth is installed on top of the gravel. This will prevent the soil from clogging the
system.
9. Excavated soil is then backfilled
Interior Waterproofing
Weeping Tiles
Weeping tiles are installed around the perimeter of building foundation. They have holes in them that allow
them to collect water and either sends it to a city drainage system or to a sump pump.
Positive-side waterproofing
By creating a waterproof barrier on the side of applied hydrostatic pressure, positive-side
waterproofing prevents water from entering the wall. For a foundation, this would be the
outside surface, closest to the soil; for a fountain, it would be the inside (i.e. where the
25
water is).
For below-grade applications, the earth can be banked back such that a positive-side
membrane is installed after the foundation is set. In urban areas, this may not be an
option. Blind-side waterproofing incorporates the waterproof membrane on the face of the
shoring before the foundation is cast. Concrete is then poured, and the waterproofing
fuses to the foundation wall as it cures.
Options for positive side systems include:
fluid-applied membranes—similar to those used in roofing applications, they roll or
brush on as a liquid and cure to form a monolithic, seamless membrane;
sheet systems—also similar to those used on roofs, including single-ply thermoplastics
and rubberized asphalts;
hybrid systems—combining a fluid-applied membrane with embedded fabric reinforcing
to create a stronger, more resilient waterproof barrier; and
bentonite clay—a natural mineral derived from volcanic ash and applied as a sheet,
mat, panel, or spray to swell in the presence of moisture to create
a solid clay barrier.
Positive-side systems, used both above and below-grade, are generally preferred over
negative-side applications for their effectiveness. The structural barrier is completely
protected from corrosive chemicals in groundwater, as well as freeze-thaw cycle damage.
The shortcoming to positive-side systems lies in leak detection and remediation. Once
backfill is in place, the actual condition of the waterproofing cannot be inspected without
excavation. If the system fails, rehabilitation can involve major excavation and
reconstruction of paving, landscaping, and wall systems.
Blind-side waterproofing is similar to positive-side methodologies, but once the concrete is
poured, the waterproofing is buried and cannot be inspected. Even for membranes
installed after concrete is cast, it is too late to correct for sloppy installation once the
waterproofing is buried.
NEGATIVE-SIDE WATERPROOFING
Negative-side waterproofing protects the surface opposite the side of applied hydrostatic
pressure (e.g. the inside of a basement wall), such that water is redirected after it enters
the substrate. Negative-side waterproofing materials include:
cementitious systems—a combination of chemical waterproofing additives or acrylics
with cement and sand to achieve an impervious surface;
acrylic, latex, or crystalline additives—products that penetrate into the surface to provide
water protection.
Since the negative side is more accessible, it is easier to identify leak locations than with
positive-side systems. Negative-side coatings or injections also can be applied as a retrofit
measure.
On the downside, with negative-side waterproofing, moisture still enters the wall assembly,
which can cause components to degrade over time. The constant presence of moisture
can also lead to mold growth, corrosion, concrete deterioration, or damage to interrelated
building elements like floors or windows.
Combination systems
For sensitive spaces below-grade, more sophisticated systems have been used. As an
example, a rare book vault built below the water table employed a wall-within-a-wall
arrangement, with a pump system in the channel between the inner and outer walls to
augment the positive side membrane.
26
15. a) Explain demolition by explosives using modern techniques.
( 13 marks )
For Building Demolition, the modern method using EXPLOSIVES is the BUILDING
IMPLOSION method. It is a CONTROLLED EXPLOSION
In the controlled demolition industry, building implosion is the strategic placing of explosive
material and timing of its detonation so that a structure collapses on itself in a matter of seconds,
minimizing the physical damage to its immediate surroundings. Despite its terminology, building
implosion also includes the controlled demolition of other structures, such
as bridges, smokestacks, towers, and tunnels.
Building implosion (which reduces to seconds a process which could take months or years to achieve by
other methods) typically occurs in urban areas and often involves large landmark structures.
In IMPLOSION Method, the goal is to induce a progressive collapse by weakening or removing
critical supports, therefore the building can no longer withstand gravity loads and will fail under its own
weight
Numerous small explosives, strategically placed within the structure, are used to catalyze the
collapse. Nitroglycerin, dynamite, or other explosives are used to shatter reinforced concrete
supports. Linear shaped charges are used to sever steel supports. These explosives are progressively
detonated on supports throughout the structure. Then, explosives on the lower floors initiate the
controlled collapse.[citation needed]
A simple structure like a chimney can be prepared for demolition in less than a day. Larger or more
complex structures can take up to six months of preparation to remove internal walls and wrap columns
with fabric and fencing before firing the explosives
1. Examine the Architectural & Strucural blueprints building to determine how the building is put
together.
2. Building is surveyed to study about the support structure on each floor.
3. Based on this data and drawing from past experiences with similar buildings, decide what explosives
to use, where to position them in the building and how to time their detonations.
1.1.1 Quantity of Explosives. The quantity of explosive to be placed depends upon the size of column
and extent up to which it is to be destroyed.
Lesser Quantity of explosive is placed in the corner columns and larger quantity of explosive is
placed in tbe inner and the middle columns, so as to destroy the inner / middle columns completely.
No outer column was weakened so that the building collapsed towards its centre from both side.
27
4.6.1 Pre-blast Considerations
(A) Pre-weakening of the structure shall be designed to ensure the structural stability before implosion
(B) To minimise the dispersion of building debris into adjoining land after blasting, a trench or bund
wall shall be installed outside the building to contain the debris
(C) A good design will cause the structure to fall towards the centre of the building and/or within the
protected area
(D) Good design will provide adequate and sufficient time delay to allow only one or two floors of the
building debris to fall on ground level at a time in order to limit the magnitude of the impact on the
ground;
(E) The design must also identify an exclusion zone to evacuate all residents or inhabitants during the
blasting. The impacts of noise and dust generated during the blasting shall be considered. Radius of the
typical exclusion zone shall not be less than 2.5 times the building height;
(F) If there are slopes and earth retaining walls or features, a geotechnical assessment shall be
conducted to ensure that the blasting will not affect the stability of these features;
(G) The entire site shall be under 24-hour security from the installation of explosive until final blasting.
(H) The Registered Specialist Contractor (Demolition) must co-ordinate with the government and local
28
community to determine the best procedures in notification, schedules for the events, traffic routing,
design for the sequence of events, evacuating residents, clear out personnel from the building and
assigning responsibilities during blasting. For the purpose of crowd control, blasting should be carried
out in the early morning of a Sunday or public holiday;
(I) An emergency plan shall be prepared to handle emergency situations such as premature explosion,
misfire or interruption due to bad weather including thunder and lightning;
(J) After the explosion, the blasting expert must check to make sure that there is no unfired explosive
left on site. The entire area must remain clear and under security control until the unfired explosives
have been detonated or safely dealt with by the blasting expert;
(K) As far as practicable, non-electrical initiation systems should be used to avoid the risk of pre-mature
detonation by stray currents, external electro-magnetic waves or radio frequencies. The installation shall
include a redundant system to ensure successful detonation. Nitroglycerine based explosives are not
permitted to be used.
(L) The Registered Specialist Contractor (Demolition) must provide evidence of his capability to safely
perform the demolition and shall illustrate to the approving authorities that the procedures are safe; 84
(M) The mode of collapse shall be demonstrated to ascertain that: (1) no part of the building will fall
beyond the protected area; (2) the impact of the structural collapse will not cause significant vibration
affecting (a) any underground tunnels; (b) any underground utilities; and (c) any adjoining properties.
(N) The structural safety of the building to be imploded shall be checked and certified to be sound and
safe at all stages prior to implosion.
Compact: These machines are small but powerful, and their compact size allows them to navigate
spaces that other equipment finds difficult to maneuver in. The machines small height means it can
easily fit through doorways, and its power and speed allow it to get the job done quickly and efficiently. H
demolition, in comparison, is much slower and less efficient.
29
Precise and versatile: Poise and precision are two elements that rank remote controlled robot
demolition above other imprecise demolition methods, such as balling, explosions and wire rope
pulling. Robotic demolition machines come with a range of different attachments that can be placed
on the hydraulic arm, such as grapples, shears and others. This versatility grants the user a
fantastic ability to choose which attachment is best for the specific situation.
Easy to operate: In the interests of safety, only trained professionals should operate the robotic
machine. However, these machines are generally easy to operate and run on hydraulic and/or
electric power.
No noise, vibration or fumes: Demolition methods such as balling, explosions, deliberate collapse
and wire rope pulling, all produce excessive amounts of noise, vibrations and mess, resulting in the
need for thorough cleanup. Remote controlled robot demolition is a clean method with minimal
vibration and minimal noise pollution. Its use also produces no fumes, making it healthier and
safer for anyone standing nearby.
Demolition Robot
Radio-controlled demolition robot
High Safety
The robot adopts digital video infrared monitoring and wire or wireless remote control system.
Therefore, the operator can stay away from the dangerous site.
The robot adopts low center of gravity and featuring reliable operation. Hence, the human and machine are
safe in the operation.
Environmental Care
The robot adopts electric-hydraulic proportional drive, which is featuring with stable operation,
low vibration and low noise.
The robot comes with motor drive or low pollution diesel drive. Therefore, the robot could reach Europe
EC standard without any harmful gas or low polluted gas.
Energy Conservation
The robot adopts load feedback variable pump system.
The system output is adjust by itself with the load requirement without any energy loss.
High Operation Efficiency
The robot adopts advanced hydraulic breaker and other hydraulic tools, which are featuring with
high breaking efficiency.
Therefore, the operation system features accuracy, flexibility and high efficiency.
Wide Application and Strong Adaptation
The robot could be used in metallurgy and cement industry, building demolition industry, rescue industry,
nuclear energy and chemical industry, mining exploitation and tunnel construction industry.
In conclusion, the robot is built to adapt to the condition of tough ground and narrow area.
31
The robot features multiple functions. The arm end is equipped
with quick coupler, which is easy to replace with breaker, shear, bucket, grab, drill and miller.
The robot adopts three-section working mechanism with large operation range. As a result, it could
reach the hitting point, hitting angle and direction flexibly in the operation range.
Compact structure, metal track and also 360° rotation.
The robot adopts advanced digital wireless remote control technology and digital video infrared
monitoring technology.
The advanced load feedback variable pump electric-hydraulic proportional hydraulic system is applied.
As a result, the actuator element could reach step-less speed adjustment, and the operation speed has
nothing to do with the load change.
The robot equipped with two types of power source, which is motor drive or diesel drive.
The optional forced cooling system ensures that the robot could work in high temperature.
Part – C
*&^%$*************************&^%#@&^*(&&&&&&&&&&&&&&&&&^^^^^^^^^^^^^^^%%%%%%%%
32