FOREST LAND PROPOSALS OF SECL PENDING FOR STAGE-1 CLEARANCE: MADHYA PRADESH STATE.

(Status as on 30.4.2010)
Present Status.
Area of land Proposal
Name of Type of Type of Date of
Sl No Area. District applied (in Purpose. presently
Project. Project Proposal Appli-cation
Ha.) pending with

Proposal was pending with DFO, Anuppur since 23.10.2008 for


processing of the proposal. Tree enumeration and inspection of
the site etc., have been done. Proposal recommended to CCF,
1 HASDEO: Anuppur. Malga UG. Comple-ted. 208.42 Diversion 23.5.06. UG Mining. CCF, Shahdol
Shahdol (MP) on 22.8.2009, who in turn forwarded it to APCCF
(LM), Bhopal in Oct.'09. APCCF (LM) returned to CCF, Shahdol in
Nov,09.
Pending with Collector, Anuppur since 23.8.2007 for issuance of
Rajnagar Collector,
2 HASDEO: Anuppur. Comple-ted. 5.06 Diversion 23.8.07. -do- NoC as it involves revenue forest land (cjj bjj). Demarcation
OC. Anuppur.
completed.

The proposal submitted to DFO, South Shahdol on 15.5.2009. For


194.960 ha. site inspection done by SDO (Forest) on 28.7.09. As
per the advice of SDO(Forest) Jaitpur, meeting held with DFO,
South Shahdol on 19.8.09. Demarcation of proposed area & DFO, South
Amlai OC For OC counting of trees is completed. For 0.935 ha. Rev. forest land, Shahdol /
3 SOHAGPURl: Anuppur. Comple-ted. 195.9 Diversion 15.5.2009
Sector 'B'. Mining. applied to Collector, Shahdol on 4.3.2009. SDM, Sohagpur Collector,
instructed to Tahsildar, Burhar for site inspection on 21.7.09, which Shahdol.
is to be done. Tahsildar inspected the site on 31.10.09 and sent
inspection report to SDM, Sohagpur,who forwarded to
Collector,Shahdol for issuance of NOC.

MoEF, Bhopal has sought 3 point queries by the User Agency on


22.12.2009. Dy.CF (C), MoEF, Bhopal, has been forwarded to
Amlai UG & CCF, Shahdol on 15.1.10 by CCF (LM) , who inturn sent to GM, CCF(Central),
4 SOHAGPUR: Anuppur. Comple-ted. 32.45 Renewal 30.4.2003.
OC. Sohagpur for its compliance on 25.1.10. The area replied to the MOEF, Bhopal
MOEF quarries. Compliance forwarded to PCCF(Central), MOEF,
Bhopal vide CCF(LM), Bhopal letter no. 835 dtd 5.4.10.

APCCF (LM), MP, Bhopal submitted the proposal to Secy.


(Forest), MP Govt. on 10.8.2009, which was recommended further
to MoEF, New Delhi on 21.8.2009. DFO, Anuppur raised demand
for NPV on new rate. The proposal is pending at SECL HQ. DFO,
Anuppur has been asked to raise demand as per old rate as per
Kotma,
JAMUNA & Infrastru-cture the Order dated 28.3.2008 of Hon'ble Supreme Court of India vide
5 Anuppur Govinda & Completed 108.28 Diversion 12.10.06. CCF, Shahdol
KOTMA: & Colony etc. this office letter no. 895 dt. 6.10.09. Letter written to GM, J&K,
Meera.
SECL on 4.11.2009 by CoF, SECL to pursue the matter with DFO,
Anuppur for raising of revised demand.MoEF, New Delhi desired
the toposheet map vide ltr. no. 8-146/2006-FC dt. 28.1.10, which
has been forwarded to CCF, Shahdol vide ltr. no. F-1/426/06/10-
11/727 dt. 25.3.10.

Page 1 of 4
Present Status.
Area of land Proposal
Name of Type of Type of Date of
Sl No Area. District applied (in Purpose. presently
Project. Project Proposal Appli-cation
Ha.) pending with

Mining The proposal was pending with DFO, Anuppur since 6.1.2007 for
Kotma West,
purpose & its further processing. Tree counting and site inspection of SDO
JAMUNA & Jamuna UG,
6 Anuppur. Comple-ted. 255.74 Diversion 26.12.06. Infrastru- completed on 26.8.2008. Proposal returned to the Area and in DFO, Anuppur.
KOTMA: Jamuna 9&10
cture, Colony reference to which PoR issued. DFO, Anuppur has to inspect the
& Bhadra.
etc., site in respect of the cases of two PORs for closure of the case.

MoEF, Bhopal raised 4point queries vide ltr. no. 3043 dt. 21.12.09,
which has been forwarded to CCF. Shahdol by CCF (LM) vide ltr.
no. 150 dt. 15.1.10, who inturn sent to GM, J&K on 25.1.10. This
JAMUNA & For OC
7 Anuppur. Jamuna OC. Comple-ted. 25.26 Diversion 18.6.07. proposal was raised in the review meeting held at Shahdol Area
KOTMA: Mining.
18.2.10, but, no representative from the Area participated in the
meeting, hence, could not be discussed. The desired information
is still awaiting from the Area.

Proposal was pending with APCCF (LM), MP, Bhopal since


6.12.2008, which was returned to CCF, Shahdol on 19.3.2009 with
some queries / clarification. Reply to queries submitted to APCCF
(LM), MP, Bhopal by CCF, Shahdol vide ltr. No. 5707 dt.
JAMUNA & Bhadra 24.8.2009. APCCF (LM), Bhopal recommended the proposal to
8 Anuppur. Comple-ted. 5.61 Renewal 26.12.2006. CCF, Shahdol.
KOTMA: Colliery. CCF, MoEF, Regional Office, Bhopal on 26.9.09 vide letter no. F-
1/496/08/10-11/2224. CCF(C) MoEF, Bhopal sought some
addl.information in 4 points from PS (Forest) MP Govt. Bhopal vide
ltr.no. 52 sdt. 6.1.2010, which was forwarded by CCF (LM) Bhopal
to CCF, Shahdol vide ltr. no. 328 dt. 29.1.10.

Proposal was recommended to MoEF, New Delhi. MoEF


nominated Dy. CF, Regional Office, MoEF, Bhopal to inspect the
site on 3.12.2008. Some queries were askesd by MoEF, Regonal
Office, Bhopal through CCF, Shahdol. Reply of the queries
submitted to CCF, Shahdol by the Area on 8.5.2009, which were
Govinda,
JAMUNA & Depillaring forwarded to MoEF, Bhopal on 25.5.2009. Proposal was forwarded
9 Anuppur Meera & Completed 48.300 Renewal 30.5.2006. CCF, Shahdol
KOTMA: Operation. to MoEF, New Delhi in July, 2009. Site inspection report has been
Kotma.
forwarded by CCF (C), MoEF, Regional Office, Bhopal to
MoEF,New Delhi vide ltr. no. MPA-0046/BHO/2638 dated
27.10.2009. MoEF, New Delhi desired the toposheet map vide ltr.
no. 8-146/2006-FC dt. 28.1.10, which has been forwarded to CCF,
Shahdol vide ltr. no. F-1/426/06/10-11/729 dt. 25.3.10.

Page 2 of 4
Present Status.
Area of land Proposal
Name of Type of Type of Date of
Sl No Area. District applied (in Purpose. presently
Project. Project Proposal Appli-cation
Ha.) pending with

Collector, Umaria issued NOC on 22.1.10 which was pending with


For OC
him since 5.10.07 as the case was of revenue forest land (cjj/bjj) &
10 JOHILLA: Umaria. Kanchan OC. Xth Plan. 12.134 Diversion 5.10.07 Mining (All DFO, UMARIA
forwarded to DFO, Umaria. DFO written letter on 6/3/10 to SDO,
right)
Forest, Umaria for site inspection.

TOTAL: 10 Proposals 897.15

Page 3 of 4
FOREST LAND PROPOSALS OF SECL PENDING FOR STAGE-2 CLEARANCE: MADHYA PRADESH STATE.
(Status as on 30.4.2010)
Sl Name of the Proposal Name of the Area of Purpose Date of MoEF’s letter reference Present Status. Pending
No Area. Code. Project. forest land application. no.& date. with.
(Ha)
1 HASDEO: Haldibari HSD – APD1 120.000 Diversion 11.3.2004. F.No. 8-64/2006-FC dated Demand Note for Gap Plantation and CPT to be raised by DFO,
(U.G.) (MP) 17.10. 2006. DFO, Annupur. Anuppur.
2 HASDEO: Kapildhara HSD – APD2 4.960 Renewal 30.4.2003. No. 6-MPC50/ 2005/ Report on Compliance of Conditions submitted to DFO, DFO,
UG. (MP) BHO/1988 dt. 27.11.2006. Anuppur on 26.5.2008. Demand Note for Gap Plantation and Anuppur.
CPT to be raised by DFO, Anuppur. Applied for waiving of
PCA cond. Imposed in 1st stage clearance.

3 HASDEO: Rajnagar RO HSD – APD3 502.000 Diversion 18.3.2002. F.No. 8-145/ 2006- FC dated Demand Note for PCA & Gap Plantation to be raised by DFO, DFO,
UG. (MP) (including 10.1.2008. Anuppur. Applied for waiving of PCA cond. Imposed in 1st Anuppur.
123.56 stage clearance.
Ha. SR)

4 HASDEO: Rajnagar RO HSD – 9.16 Regulari- 30.4.2003. No.8-C-6-201/94/ FCW/595/ Demand Note for Gap Plantation & CPT to be raised by DFO, DFO,
UG. APD4(MP) zation dt. 30.3.2005. Anuppur. Anuppur.
5 HASDEO: Kurja- HSD – APD5 126.37 Diversion -- F.No. 8-71/2002-FC dated CPT payment deposited to DFO on 23.12.09. Demand Note for DFO,
Sheetaldhara (MP) 23.5.2003. Gap Plantation to be raised by DFO, Anuppur. Anuppur.
(UG).
TOTAL:5 Proposals. 762.490