Decision-making is the process which starts after the above-mentioned steps of EIA are
completed. Usually the decision is taken by a manager or a committee, or personnel from the
concerned ministry who had not been associated with the EIA during its preparation. Technical
and economic aspects of project alternatives are thoroughly considered but, at times, political
expediency and project feasibility control the final choice. In general, a decision-maker has three
choices:
accepting one of the project alternatives
returning the EIA with a request for further study in certain specific areas
totally rejecting the proposed project along with alternative versions.
As pointed out by Ahmad and Sammy (1985), EIAs are expected to aid decision-making; and
therefore, preparation and drafting of an EIA should always be carried out with this clear
objective in mind.
EIA is a process to: gather information necessary for decision-making. Inform approval and
condition setting and help determine if a proposal is acceptable.
Decision-making is a process of: political choice between alternative directions, weighing the
benefits and costs, negotiation, bargaining and tradeoffs, balancing economic, social and
environmental factors.
Decision-makers need to understand:
EIA aims and concepts
EIA legislation, procedure and guidelines
the effectiveness of EIA practice
the limitations on EIA information
how EIA process and practice measure up internationally
issues of public consultation and third-party challenges
A decision to approve or reject a mining project is generally based on the final EIA, but in some
instances, an environmental clearance may be just one step in the mine permitting process. The
decision may be accompanied by certain conditions that must be fulfilled, such as posting a
reclamation bond or filing an Environmental Management Plan. [2]
In Uganda for example based on the review of the EIS, a decision is made to approve or reject
the proposed project. The decision-making process involves a number of steps: [3]
(i) Review of EIS
NEMA and the appropriate lead agency review the EIS, taking particular note of the
environmental impacts identified, the recommended mitigation measures, as well as the extent of
stakeholder consultation. The EIS is also subjected to public review. [3]
(ii) Public Hearing
Under Regulation 21(2), the Executive Director of NEMA is required to call for a public hearing
“where there is controversy or where the project may have trans-boundary impacts. [3]
H. a. C. Ministry of Works, Environmental Impact Assessment Guidelines for Road Projects- final
[1] draft, kampala, 2004.
[2] Y. a. S. G. Ahmad, Guidelines to Environmental Impact Assessment, Hodder and Stoughton, London,
1985.