II Pekerjaan Galian
Alat :
- Exavator Unit 2.00 12,000,000.00 24,000,000.00
- Dump Truck Unit 4.00 1,925,000.00 7,700,000.00
Total 31,700,000.00
II Pekerjaan Plesteran
Alat :
- Concrete Mixer Unit 3 2,000,000.00 6,000,000.00
- Alat Bantu Ls 1 100,000.00 100,000.00
Bahan :
- Pasir kali M³ 1800 180,000.00 324,000,000.00
- Semen Zak 250 67,000.00 16,750,000.00
Tenaga :
- Pekerja Oh/hari 8.00 95,000.00 760,000.00
- Tukang Oh/hari 4.00 115,000.00 460,000.00
- Kepala Tukang Oh/hari 2.00 140,000.00 280,000.00
- Mandor Oh/hari 2.00 175,000.00 350,000.00
Total 348,700,000.00
Jumlah Total 963,922,000.00