Which of the following is considered a vessel An alteration on a vessel is defined as

alteration? A) Addition of non-reinforced nozzle


B) Weld build up in a locally corroded area C)
Replacement of a hemi-spherical head with a
tori-spherical head D) Addition of fillet weld
patch

an 8 NPS nozzle is going to be added to a 2-to-1 A 14 NPS nozzle is going to be added to a vessel
ellipsoidal vessel head. The vessel is rated for shell. The vessel is rated for 100 psig at 650°F.
350 psig at 500°F. The vessel has inside dia. of and has an existing 10 NPS nozzle. Which of the
72". The largest existing nozzle on the vessel is following is true? A) This work is considered an
18 NPS. Which of the following is true? A) This alteration B) This work is considered a repair C)
work will be considered an alteration B) The The shell-to-nozzle weld must be radiographed
root pass on the welds must be checked with D) This work must be authorized only by the
either MT or PT C) The vessel must be API 510 inspector
hydrotested after the nozzles are completed D)
This work must be authorized by the API 510
Which of the following inspection organizations Which of the following is considered an API 510
is not considered an acceptable API 510 authorized inspection agency? A) The
authorized inspection agency? A) Holder of an owner/user's operating department B) the
appropriate ASME code symbol B) Insurance inspection organization of the jurisdiction C) an
company that writes pressure vessel insurance NDE contract organization D) the inspection
C) The owner/user D) The jurisdiction department of a vessel manufacturer

Which of the following equipment types is a repair on a vessel is defined as


covered by API 510? A) knock out drum rated at
12 psig@400°F B) tubular heater C) unfired
steam generator D) a 36" expansion joint

1 of 4
any physical change with design implications C) Replacement of a hemi-spherical head with a
tori-spherical head

A) This work is considered an alteration D) This work must be authorized by the API 510
inspector

B) the inspection organization of the jurisdiction A) Holder of an appropriate ASME code symbol

the work necessary to restore a vessel to C) unfired steam generator


suitable safe condition

2 of 4
A vessel's hemi-spherical head has corroded is Which of the following inspection organizations
going to be replaced in kind at the next T/A. The is not considered an acceptable API 510 repair
vessel is rated for 150 psig@700°F. The vessel organization? A) A contract company that is
has 60" I.D. Which of the following is true? A) acceptable to the owner/user B) the governing
This work is considered an alteration B) This jurisdiction based on the location of the pressure
work is considered a repair C) This work is vessel C) the owner/ user that owns the pressure
considered a rerate D) This work must be done vessel D) an organization authorized by the
in accordance with API 2210 jurisdiction

Which of the following is not considered a Temper embrittlement occurs in certain materials
vessel rerate? A) Decrease the MDMT B) when
increase the design pressure C) decrease the
design temp D) increase the fluid viscosity

Low chrome materials are subjected to temper-


embrittlement. These materials are

3 of 4
B) the governing jurisdiction based on the B) This work is considered a repair
location of the pressure vessel

The process temp exceeds 650°F D) increase the fluid viscosity

brittle at low temps due to metallurgical changes