The above deviations amount of Rs 1,06,00,000 /- will be met from the overall savings of
the estimate.
2. The L.S of the existing ground levels on LHS and RHS of R E Wall location for each approach
side in the drawings 6 to 13 is furnished as per site and the cross sections with ground levels are
herewith for submitted information and kind perusal
Under the circumstances explained above, I herewith submit the financial implication of
R.E Wall deviations proposal and I request to obtain the necessary approval from the competent
authority at an early date so as to enable us to execute the above items
From To
Sri B.Narasaiah M.Tech, M.I.E., The Executive Engineer,
Deputy Executive Engineer, (R&B) Division,
R&B Buildings sub division,Kakinada Rajamahendravaram
Letter no. Dy.EE/ROB/L.CNo.419/2011-12 dt .05.2018
Sir ,
Sub : - ROB Works – (R&B) Circle, Kakinada – (R&B) Division, Kakinada “Construction of ROB at
Biccavolu in liue of LC No.419 at Railway Km 611/21-23 Of Vijayawada - Visakhapatnam
Section Corresponding km 14/4 of Narasapurapupeta - Katravulapalli Road In East Godavari
District.” – R.E. Wall designs and drawings – Rsubmitting – Reg
Ref :- 1. L.S Agreement CR .No.46/2016-17 dt.18.07.2016
2. Memo No.8722/AEE3/ROB/L.C.No.419/2011-12 dated 25.04.2018 of the Superintending
Engineer, R&B Circle, Kakinada.
*********
With reference to the 2 nd cited above i, i here with resubmiting the RE wall proposal
along with sub soil investigation report contuded at the follwing RE wall locations for fovour of
infermation and for finalizing the R.E Wall design and drawings.
From To
Sri T.Satyanarayana B.E., The Superintending Engineer,
Executive Engineer, (R&B) Circle,
(R&B) Division, Rajamahendravaram Kakinada.
Letter no. EE/ROB/L.CNo.419/2011-12 dt 28.04.2018
Sir ,
Sub : - ROB Works – (R&B) Circle, Kakinada – (R&B) Division, Kakinada “Construction of ROB at
Biccavolu in liue of LC No.419 at Railway Km 611/21-23 Of Vijayawada - Visakhapatnam
Section Corresponding km 14/4 of Narasapurapupeta - Katravulapalli Road In East Godavari
District.” – R.E. Wall designs and drawings – Rsubmitting – Reg
Ref :- 1. L.S Agreement CR .No.46/2016-17 dt.18.07.2016
2. Memo No.8722/AEE3/ROB/L.C.No.419/2011-12 dated 25.04.2018 of the Superintending
Engineer, R&B Circle, Kakinada.
*********
With reference to the 2 nd cited above i, i here with resubmiting the RE wall proposal
along with sub soil investigition report contuded at the follwing RE wall locations for fovour of
infermation and for finalizing the R.E Wall design and drawings.
Executive Engineer,
(R&B) Division,
Rajamahendravaram.
From To
Sri B.Narasaiah M.Tech, M.I.E., The Executive Engineer,
Deputy Executive Engineer, (R&B) Division,
R&B Buildings sub division,Kakinada Rajamahendravaram
Letter no. Dy.EE/ROB/L.CNo.419/2011-12 dt 28.05.2018
Sir ,
Sub : - ROB Works – (R&B) Circle, Kakinada – (R&B) Division, Kakinada “Construction of ROB at
Biccavolu in liue of LC No.419 at Railway Km 611/21-23 Of Vijayawada - Visakhapatnam
Section Corresponding km 14/4 of Narasapurapupeta - Katravulapalli Road In East Godavari
District.” – Finacial implications due to R.E. Wall – Report Submitted - Reg
Ref :- 1) Chief Engineer(R&B) COT & RSW, Ibrahimpatnam Memo No : 880/D&P/AP/
EE-1/DEE-1/AEE-II/2011-12 dated 17-11-2017.
2) Dy.EE/ROB/L.C No.419/2011-12 dated 21-12-2017
*********
Adverting to the reference cited, I submit that the Financial implications due to R.E. Wall
proposals is as follows In the technical sanction estimate in the Part –A item under “ Construction
of Reinforced soil walls on both sides of ROB the financial implication is worked out as below.
Table -I
S.No Description of item More Less
1 Earth work excavation 66,096 -
2 VCC M15 levelling pad 1,77,093 -
3 Reinforced soil walls(4.00- 10,10,043 -
6.00 M)
4 Drainage fill - 12,10,483
5 VRCC M20 coping beam - 1,42,504
6 VRCC M25 Friction slab - 2,44,721
7 Parapet Wall - 6,25,583
8 Crash Barrier 27,98,232 -
9 HYSD for Crash Barrier 9,81,085 -
50,32,549 24,28,405
Net excess due to above items = Rs.26,04,144/-
(Rs.50,32,549-Rs.24,28,405)
Further in the technical sanction estimate in the Part-A item under “ Filling in between reinforced
soil walls in the Non-Viaduct portion and laying road crust above filling the financial implication
is worked out below.
Table -II
S.No Description of item More Less
1 Forming Embankment - 42,210
2 GSB - 1,57,976
3 WMM - 1,82,286
I herewith submit the financial implication of R.E Wall deviations proposal and I request
to obtain the necessary approval from the competent authority at an early date so as to enable us to
execute the above items
Yours faithfully ,
From To
Sri T.Satyanarayana,B.Tech, The Superintending Engineer,
Executive Engineer,(R&B) (R&B) circle,
R&B Division,Rajamahendravaram Kakinada
Letter no. EE/ROB/L.CNo.419/2011-12 dt 28.05.2018
Sir ,
Sub : - ROB Works – (R&B) Circle, Kakinada – (R&B) Division, Kakinada “Construction of ROB at
Biccavolu in liue of LC No.419 at Railway Km 611/21-23 Of Vijayawada - Visakhapatnam
Section Corresponding km 14/4 of Narasapurapupeta - Katravulapalli Road In East Godavari
District.” – Finacial implications due to R.E. Wall – Report Submitted - Reg
Ref :- 1) Chief Engineer(R&B) COT & RSW, Ibrahimpatnam Memo No : 880/D&P/AP/
EE-1/DEE-1/AEE-II/2011-12 dated 17-11-2017.
2) Dy.EE/ROB/L.C No.419/2011-12 dated 28.05.2018
*********
Adverting to the reference cited, I submit that the Financial implications due to R.E. Wall
proposals is as follows In the technical sanction estimate in the Part –A item under “ Construction
of Reinforced soil walls on both sides of ROB the financial implication is worked out as below.
Table -I
S.No Description of item More Less
1 Earth work excavation 66,096 -
2 VCC M15 levelling pad 1,77,093 -
3 Reinforced soil walls(4.00- 10,10,043 -
6.00 M)
4 Drainage fill - 12,10,483
5 VRCC M20 coping beam - 1,42,504
6 VRCC M25 Friction slab - 2,44,721
7 Parapet Wall - 6,25,583
8 Crash Barrier 27,98,232 -
9 HYSD for Crash Barrier 9,81,085 -
50,32,549 24,28,405
Net excess due to above items = Rs.26,04,144/-
(Rs.50,32,549-Rs.24,28,405)
Further in the technical sanction estimate in the Part-A item under “ Filling in between reinforced
soil walls in the Non-Viaduct portion and laying road crust above filling the financial implication
is worked out below.
Table -II
S.No Description of item More Less
1 Forming Embankment - 42,210
2 GSB - 1,57,976
3 WMM - 1,82,286
I herewith submit the financial implication of R.E Wall deviations proposal and I request
to obtain the necessary approval from the competent authority at an early date so as to enable us to
execute the above items
Yours faithfully ,
Executive Engineer,
R&B Division,
Rajamahendravaram
GOVERNMENT OF ANDHRA PRADESH
ROADS AND BUILDINGS DEPARTMENT
From To
Smt.P.Asritha, M.Tech., Deputy Executive Engineer,
Asst. Executive Engineer (R&B), R&B Buildings sub division,
F.O.B Section-I, Rajahmundry Kakinada
I herewith submit the financial implication of R.E Wall deviations proposal and I request
to obtain the necessary approval from the competent authority at an early date so as to enable us to
execute the above items
Yours faithfully ,
From To
Smt. P.Asritha,M.Tech, The Dy.Executive Engineer,
Asst. Executive Engineer, (R&B) Buildings Sub Division,
FOB.-I, Rajahmundry Kakinada
Letter no. AEE/ROB/L.CNo.419/2011-12 dt 28.05.2018
Sir ,
Sub : - ROB Works – (R&B) Circle, Kakinada – (R&B) Division, Kakinada “Construction of ROB at
Biccavolu in liue of LC No.419 at Railway Km 611/21-23 Of Vijayawada - Visakhapatnam
Section Corresponding km 14/4 of Narasapurapupeta - Katravulapalli Road In East Godavari
District.” – Finacial implications due to R.E. Wall – Report Submitted - Reg
Ref :- 1) Chief Engineer(R&B) COT & RSW, Ibrahimpatnam Memo No : 880/D&P/AP/
EE-1/DEE-1/AEE-II/2011-12 dated 17-11-2017.
2) Dy.EE/ROB/L.C No.419/2011-12 dated 21-12-2017
*********
Adverting to the reference cited, I submit that the Financial implications due to R.E. Wall
proposals is as follows In the technical sanction estimate in the Part –A item under “ Construction
of Reinforced soil walls on both sides of ROB the financial implication is worked out as below.
Table -I
S.No Description of item More Less
1 Earth work excavation 66,096 -
2 VCC M15 levelling pad 1,77,093 -
3 Reinforced soil walls(4.00- 10,10,043 -
6.00 M)
4 Drainage fill - 12,10,483
5 VRCC M20 coping beam - 1,42,504
6 VRCC M25 Friction slab - 2,44,721
7 Parapet Wall - 6,25,583
8 Crash Barrier 27,98,232 -
9 HYSD for Crash Barrier 9,81,085 -
50,32,549 24,28,405
Net excess due to above items = Rs.26,04,144/-
(Rs.50,32,549-Rs.24,28,405)
Further in the technical sanction estimate in the Part-A item under “ Filling in between reinforced
soil walls in the Non-Viaduct portion and laying road crust above filling the financial implication
is worked out below.
Table -II
S.No Description of item More Less
1 Forming Embankment - 42,210
2 GSB - 1,57,976
3 WMM - 1,82,286
I herewith submit the financial implication of R.E Wall deviations proposal and I request
to obtain the necessary approval from the competent authority at an early date so as to enable us to
execute the above items
Yours faithfully ,