CONTROL DE PAGOS SUPERVISOR

MONTO FONDO DE
ITEM CONCEPTO MONTO BRUTO
CONTRATADO GARANTÍA
S/. 16,200.00
01.- PERIODO 21/11/2017-30/11/2017 S/. 5,400.00 S/. 810.00
02.- PERIODO 01/12/2017-31/12/2017 S/. 5,400.00 S/. 810.00
03.- PERIODO 01/01/2018-31/01/2018 S/. 5,400.00 S/. -
RVISOR

MONTO NETO A MONTO SALDO DE


CANCELAR ACUMULADO CONTRATO

S/. 4,590.00 S/. 5,400.00 S/. 10,800.00


S/. 4,590.00 S/. 10,800.00 S/. 5,400.00
S/. 5,400.00 S/. 16,200.00 S/. -
CONTROL DE PAGOS CONTRATISTA

RETENCION
MONTO
ITEM CONCEPTO MONTO BRUTO FONDO DE
CONTRATADO
GARANTIA
S/. 237,452.92
01.- VALORIZACION.NOVIEMBRE 2017 S/. 14,706.00 S/. 0.00
02.- VALORIZACION.DICIEMBRE 2017 S/. 93,807.92 S/. 0.00
03.- VALORIZACION.ENERO 2018 S/. 81,317.49 S/. 23,745.29
03.- VALORIZACION.FEBRERO 2018 S/. 47,621.51 S/. 0.00
TRATISTA

SALDO NETO A MONTO SALDO DE


CANCELAR ACUMULADO CONTRATO

S/. 14,706.00 S/. 14,706.00 S/. 222,746.92


S/. 93,807.92 S/. 108,513.92 S/. 128,939.00
S/. 57,572.20 S/. 189,831.41 S/. 47,621.51
S/. 47,621.51 S/. 237,452.92 S/. 0.00
Entrega de terreno 17 de noviembre de 2017
Fecha inicio de obra 21 de noviembre de 2017
Plazo Ejecucion 90 Dias Calendarios
Fecha de término de obra 18 de febrero de 2018
Primer Informe de termino 23 de febrero de 2018
Resolucion Comité de Recepcion 5 de marzo de 2018
Dias para recepcionar 9 Dias Calendarios

Fechas para Levantar Pliego de 6 de marzo de 2018 entre


Observaciones

Existe Observaciones se dispone 9 Dias Calendarios


Fecha Pliego Observaciones 10 de marzo de 2018
15 de marzo de 2018
Fecha Limite levantar observaciones 24 de marzo de 2018
informe de levantar observaciones 27 de marzo de 2018
Comité verificar Observaciones 3 de abril de 2018
14 de marzo de 2018

Levantan Observaciones 3/20/2018


informe levantar observaciones 3/23/2018
Verificacion observaciones 3/26/2018