As on 20th May"2018
Work Schedule
Month Upto May'18 June'18 July'18 Aug'18 Sep'18 Oct'18
SL. Work Description 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30 10
30 Aluminium work
31 Paint Work
32 Internal Door Shutter fitting
39 Bio-Gas Plant
41 Hand Over
PROJECT NAME : PALLI JANAPAD - RANGPUR
As on 20th May"2018
Work Schedule
Month Nov'16
Oct'18 Nov'18 Dec'18
SL. Work Description 09 20 30 10 20 30 10 20 30
30 Aluminium work
31 Paint Work
32 Internal Door Shutter fitting
39 Bio-Gas Plant
41 Hand Over
PROJECT: NEW WARE HOUSE OF TM TEXTILE & GARMENTS LTD.
Gant Chart
Month: OCT2013 Month: NOV 2013 Month: Dec 2013 Month: Jan 2014 Month: Feb 2014 Month: Mar 2014 Month: Apr 2014
SL. Name of the Work Items Status Duration Start Finish weeks weeks weeks weeks weeks weeks weeks
2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week
Plan(21/10/13)
14 Rcc casting at Mezzanine floor 26 days 22-Jan 16-Feb
Actual
4th week
PROJECT: NEW WARE HOUSE OF TM TEXTILE & GARMENTS LTD.
Gant Chart
Month: OCT2013 Month: NOV 2013 Month: Dec 2013 Month: Jan 2014 Month: Feb 2014 Month: Mar 2014 Month: Apr 2014
SL. Name of the Work Items Status Duration Start Finish weeks weeks weeks weeks weeks weeks weeks
2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week
4 Mobilization of Materials
Plan(10/10/13) 5days 2-Nov 6-Nov
Actual
Plan(10/10/13) 8days 6-Nov 13-Nov
5 Site Preparation
Actual
Plan(10/10/13) 13days 9-Nov 21-Nov
6 Earth cutting
Actual
Plan(10/10/13)
14 Rcc casting at Mezzanine floor 25 days 19-Jan 12-Feb
Actual
23693 Sft (GF 19101 Sft (GF 23693.00 Sft (1st 42967.00 Sft (1st 22220.00 Sft 44440.00 Sft (2nd
Roof Slab Casting
Roof) Roof) Floor Roof) Floor Roof) (2nd Floor Roof) Floor Roof)
Column Work 300 Nos 412 Nos 300 Nos 412 Nos 300 Nos 412 Nos
Works till 6072.5 Rft(1st 6072.5 Rft(1st 12145 12145
May"18 Brick Wall & Plaster 6072.5 Rft(GF)
Floor)) Floor)) Rft(2ndFloor) Rft(3rdFloor)
3rd Floor Roof SandwichPanel
11000 sft 11000 sft 11000 sft
Work
Electrical Work Electrical works Electrical works Electrical works Electrical works
Sanitary Works Sanitary Works Sanitary Works Sanitary Works Sanitary Works
Tiles and related Tiles Work Tiles Work Tiles Work Tiles Work Tiles Work
Cement 4726 Bag 4150 Bag 5484.81 Bags 4507.45 Bags 2977.85 Bags 23111.34 Bags
1st Class Brick 29658 Cft 29864.2 Cft 133585.6 Cft
Stone Chips 5208 Cft 8276.4 Cft 6911.1 Cft 7717.5 Cft 6911.1 Cft 18877.5 Cft
Pie Stone Chips 14622 Cft 3693.14 Cft 6433.95 Cft 9163.05Cft 3333Cft 6666 Cft
Materials Re-bar 306631 Kgs 39455.6 Kgs 34509.1 Kgs 37037.6 Kgs 23709.1 Kgs 62805.1 Kgs
Electrical Materials 25% 25% 25% 25%
Sanitary Materials 15% 20% 25% 20% 20%
Tiles and related Matrial 15% 15% 20% 20% 20% 10%
Sandwitch Panel 306631 Kgs 39455.6 Kgs 34509.1 Kgs 37037.6 Kgs 23709.1 Kgs 62805.1 Kgs
Roof Hoist 4 Nos
Trolley 1 No
Hand Motorized Roller Existing
Manpower 180 Men/day 180 Men/day 250 Men/day 250 Men/day 300 Men/day 300 Men/day 300 Men/day 120 Men/day
Quantam L A Construction
Banani DOHS, Dhaka-1206.