PROJECT NAME : PALLI JANAPAD - RANGPUR

As on 20th May"2018
Work Schedule
Month Upto May'18 June'18 July'18 Aug'18 Sep'18 Oct'18
SL. Work Description 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30 10

1 Column Casting (712 Nos)

2 Beam Casting (20000 Rft)


3 Ferrocement Slab Installation (49000 sft)

4 1st Floor Hollo Block Work

5 2nd Floor Hollo Block Work

6 3rd Floor Hollo Block Work

7 Ground Floor Hollo Block Work

8 1st Floor Grill and Chowkat fitting with Electrical Work

9 2nd Floor Grill and Chowkat fitting with Electrical Work

10 3rd Floor Grill and Chowkat fitting with Electrical Work

11 Ground Floor Grill and Chowkat fitting with Electrical Work

12 Sanitary Work (Vertical Line)

13 Sanitary Internal Wiring 1st Floor

14 Sanitary Internal Wiring 2nd Floor


15 Sanitary Internal Wiring 3rd Floor

16 Sanitary Internal Wiring Ground Floor


17 Roof Top Truss Work

18 Roof Top sandwich Panel Installation

19 1st Floor Internal plaster work


20 2nd Floor Internal plaster work
21 3rd Floor Internal plaster work

22 Ground Floor Internal plaster work

23 Out side Plaster Work


24 1st Floor Tiles Work

25 2nd Floor Tiles Work


Month Upto May'18 June'18 July'18 Aug'18 Sep'18 Oct'18
SL.Work Description 10 20 30 10 20 30 10 20 30 10 20 30 10 20 30 10
26 3rd Floor Tiles Work
27 Ground Floor Tiles work

28 Stair Tiles Work

29 Ground Floor Sewerage line

30 Aluminium work

31 Paint Work
32 Internal Door Shutter fitting

33 Sanitary Fixing Work

34 Electrical Fixing Work

35 Solar Panel Work

36 Road work & Surface drain

37 Sub station Instrallation


38 Electrical Connection

39 Bio-Gas Plant

40 Final Checking and Cleaning

41 Hand Over
PROJECT NAME : PALLI JANAPAD - RANGPUR
As on 20th May"2018
Work Schedule
Month Nov'16
Oct'18 Nov'18 Dec'18
SL. Work Description 09 20 30 10 20 30 10 20 30

1 Column Casting (712 Nos) Completed

2 Beam Casting (20000 Rft) Completed

3 Ferrocement Slab Installation (49000 sft) Completed

4 1st Floor Hollo Block Work completed

5 2nd Floor Hollo Block Work Completed

6 3rd Floor Hollo Block Work Completed

7 Ground Floor Hollo Block Work Completed

8 1st Floor Grill and Chowkat fitting with Electrical Work

9 2nd Floor Grill and Chowkat fitting with Electrical Work

10 3rd Floor Grill and Chowkat fitting with Electrical Work

11 Ground Floor Grill and Chowkat fitting with Electrical Work

12 Sanitary Work (Vertical Line)

13 Sanitary Internal Wiring 1st Floor

14 Sanitary Internal Wiring 2nd Floor


15 Sanitary Internal Wiring 3rd Floor

16 Sanitary Internal Wiring Ground Floor


17 Roof Top Truss Work

18 Roof Top sandwich Panel Installation

19 1st Floor Internal plaster work


20 2nd Floor Internal plaster work
21 3rd Floor Internal plaster work

22 Ground Floor Internal plaster work

23 Out side Plaster Work


24 1st Floor Tiles Work

25 2nd Floor Tiles Work


Month Nov'16
Oct'18 Nov'18 Dec'18
SL.Work Description 09 20 30 10 20 30 10 20 30
26 3rd Floor Tiles Work
27 Ground Floor Tiles work

28 Stair Tiles Work

29 Ground Floor Sewerage line

30 Aluminium work

31 Paint Work
32 Internal Door Shutter fitting

33 Sanitary Fixing Work

34 Electrical Fixing Work

35 Solar Panel Work

36 Road work & Surface drain

37 Sub station Instrallation


38 Electrical Connection

39 Bio-Gas Plant

40 Final Checking and Cleaning

41 Hand Over
PROJECT: NEW WARE HOUSE OF TM TEXTILE & GARMENTS LTD.
Gant Chart
Month: OCT2013 Month: NOV 2013 Month: Dec 2013 Month: Jan 2014 Month: Feb 2014 Month: Mar 2014 Month: Apr 2014
SL. Name of the Work Items Status Duration Start Finish weeks weeks weeks weeks weeks weeks weeks
2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week

Plan(21/10/13) 21-Oct 7-Nov


1 Preperation of documents
,Quotation collection,selection of Actual
contractor & issuing work order
4 Mobilization of Materials
Plan(21/10/13) 8days 8-Nov 15-Nov
Actual
Plan(21/10/13) 8days 10-Nov 17-Nov
5 Site Preparation
Actual
Plan(21/10/13) 13days 15-Nov 27-Nov
6 Earth cutting
Actual

Leveling,Dressing, Soling ,C.C Plan(21/10/13)


7 15 days 20-Nov 4-Dec
Casting in Column Foundation Actual

Plan(21/10/13) 20 days 25-Nov 14-Dec


8 Column Foundation up to GB.
Actual
Plan(21/10/13) 12 days 3-Dec 14-Dec
9 Back Filling/Sand Filling
Actual

Steel col. Rafter,Purlin etc. Plan(21/10/13) 22 days 2-Dec 23-Dec


10
Erection Actual

Plan(21/10/13) 30 days 13-Dec 11-Jan


11 5'' Brick Wall ,Lintel, Sunshade
Actual

Floor preparatiopn,Solling,RCC Plan(21/10/13)


12 25 days 26-Dec 19-Jan
Casting Actual
Plan(21/10/13) 24 days 8-Jan 31-Jan
13 Stairs
Actual

Plan(21/10/13)
14 Rcc casting at Mezzanine floor 26 days 22-Jan 16-Feb
Actual

Roof, Wall sheeting & Plan(21/10/13) 30 days 13-Feb 14-Mar


15
Accessories Actual
Plan(21/10/13) 30days 20-Feb 21-Mar
16 Mosaic Work(GF)
Actual
Plan(21/10/13) 31 days 18-Jan 17-Feb
17 Plaster Works(G.F wall )
Actual
Plan(21/10/13) 21 days 19-Feb 11-Mar
18 Floor Tiles(M.F)
Actual

Painting Works (Weather Coat)/ Plan(21/10/13)


19 15 days 27-Feb 13-Mar
plastic paints
Actual
Plan(21/10/13) 15 days 2-Mar 16-Mar
20 Outside Canopy
Actual

Door,Shutter,Exhaust Fan and Plan(21/10/13) 20 days 16-Mar 4-Apr


21
Window Works Actual

Plan(21/10/13) 10 days 4-Apr 13-Apr


22 Fine Tune
Actual

Plan(21/10/13) 1 day 14-Apr


23 Handover
23 Handover
Actual
4

4th week
PROJECT: NEW WARE HOUSE OF TM TEXTILE & GARMENTS LTD.
Gant Chart
Month: OCT2013 Month: NOV 2013 Month: Dec 2013 Month: Jan 2014 Month: Feb 2014 Month: Mar 2014 Month: Apr 2014
SL. Name of the Work Items Status Duration Start Finish weeks weeks weeks weeks weeks weeks weeks
2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week 3rd week 4th week 1 st week 2nd week

Plan(10/10/13) 21-Oct 31-Oct


1 Drawing, Design & Quotation
collection Actual
Plan(10/10/13) 1-Nov
2 work order
Actual

4 Mobilization of Materials
Plan(10/10/13) 5days 2-Nov 6-Nov
Actual
Plan(10/10/13) 8days 6-Nov 13-Nov
5 Site Preparation
Actual
Plan(10/10/13) 13days 9-Nov 21-Nov
6 Earth cutting
Actual

Dressing, Leveling, Soling C.C Plan(10/10/13)


7 15 days 14-Nov 28-Nov
Casting in Column Foundation Actual

Plan(10/10/13) 20 days 18-Nov 7-Dec


8 Column Foundation up to GB.
Actual
Plan(10/10/13) 12 days 27-Dec 7-Dec
9 Back Filling/Sand Filling
Actual
Steel col. Rafter,Purlin etc. Plan(10/10/13) 22 days 23-Nov 14-Dec
10
Erection Actual
Plan(10/10/13) 30 days 7-Dec 5-Jan
11 5'' Brick Wall ,Lintel, Sunshade
Actual

Floor preparatiopn,Solling,RCC Plan(10/10/13)


12 25 days 20-Dec 13-Jan
Casting Actual
Plan(10/10/13) 16 days 3-Jan 18-Jan
13 Stairs
Actual

Plan(10/10/13)
14 Rcc casting at Mezzanine floor 25 days 19-Jan 12-Feb
Actual

Roof, Wall sheeting & Plan(10/10/13) 30 days 7-Feb 8-Mar


15
Accessories Actual
Plan(10/10/13) 30days 14-Feb 15-Mar
16 Mosaic Work(GF)
Actual
Plan(10/10/13) 31 days 14-Jan 13-Feb
17 Plaster Works(G.F wall )
Actual
Plan(10/10/13) 21 days 13-Feb 5-Mar
18 Floor Tiles(M.F)
Actual

Painting Works (Weather Coat)/ Plan(10/10/13)


19 15 days 21-Feb 7-Mar
plastic paints
Actual
Plan(10/10/13) 15 days 21-Mar 4-Apr
20 Outside Canopy
Actual

Door,Shutter,Exhaust Fan and Plan(10/10/13) 20 days 4-Apr 23-Apr


21
Window Works Actual

Plan(10/10/13) 7 days 23-Apr 29-Apr


22 Fine Tune
Actual

Plan(10/10/13) 1 day 30-Apr


23 Handover
23 Handover
Actual
Apr 2014
eks
3rd week 4th week
Man-Material & Fund Planning
PALLI JANAPAD - RANGPUR
Required Volume Nov'17 Dec'17 Jan'18 Feb'18 Mar'18 Apr'18 May'18 June'18
Sand Filling &
F.c Panel Production (Nos) 1440.00 1440.00 Nos 1440.00 Nos 1359.00 Nos
Hollow Brick Production
75000.00 Nos 75000.00 Nos 75000.00 Nos 75000.00 Nos 75000.00 Nos 75000.00 Nos 75000.00 Nos

23693 Sft (GF 19101 Sft (GF 23693.00 Sft (1st 42967.00 Sft (1st 22220.00 Sft 44440.00 Sft (2nd
Roof Slab Casting
Roof) Roof) Floor Roof) Floor Roof) (2nd Floor Roof) Floor Roof)
Column Work 300 Nos 412 Nos 300 Nos 412 Nos 300 Nos 412 Nos
Works till 6072.5 Rft(1st 6072.5 Rft(1st 12145 12145
May"18 Brick Wall & Plaster 6072.5 Rft(GF)
Floor)) Floor)) Rft(2ndFloor) Rft(3rdFloor)
3rd Floor Roof SandwichPanel
11000 sft 11000 sft 11000 sft
Work
Electrical Work Electrical works Electrical works Electrical works Electrical works

Sanitary Works Sanitary Works Sanitary Works Sanitary Works Sanitary Works
Tiles and related Tiles Work Tiles Work Tiles Work Tiles Work Tiles Work
Cement 4726 Bag 4150 Bag 5484.81 Bags 4507.45 Bags 2977.85 Bags 23111.34 Bags
1st Class Brick 29658 Cft 29864.2 Cft 133585.6 Cft
Stone Chips 5208 Cft 8276.4 Cft 6911.1 Cft 7717.5 Cft 6911.1 Cft 18877.5 Cft
Pie Stone Chips 14622 Cft 3693.14 Cft 6433.95 Cft 9163.05Cft 3333Cft 6666 Cft
Materials Re-bar 306631 Kgs 39455.6 Kgs 34509.1 Kgs 37037.6 Kgs 23709.1 Kgs 62805.1 Kgs
Electrical Materials 25% 25% 25% 25%
Sanitary Materials 15% 20% 25% 20% 20%
Tiles and related Matrial 15% 15% 20% 20% 20% 10%
Sandwitch Panel 306631 Kgs 39455.6 Kgs 34509.1 Kgs 37037.6 Kgs 23709.1 Kgs 62805.1 Kgs
Roof Hoist 4 Nos

Mixture Machine, Vibrator,


Fork Lift, Hollow Block
Existing
Equipment Machine, FerroCement
production Tables

Trolley 1 No
Hand Motorized Roller Existing

Manpower 180 Men/day 180 Men/day 250 Men/day 250 Men/day 300 Men/day 300 Men/day 300 Men/day 120 Men/day
Quantam L A Construction
Banani DOHS, Dhaka-1206.

Work Program For Building # 09


Project Name : Palli Janapad Housing. Rangpur.

Start Finish Duration


S.L Discription of Work Remarks
Date Date Time
1 Building Colum, Tie Beam, Rod Binding
Shuttering and Casting.
2 Fero Cement Slab Installation.
3 1st Floor Hollo Block work
4 2nd Floor Hollo Block work
5 3rd Floor Hollo Block work
6 Ground Floor Hollo Block work
7 1st Floor Grill and Chowkat fitting with Electrical
work
8 2nd Floor Grill and Chowkat fitting with Electrical
work
9 3rd Floor Grill and Chowkat fitting with Electrical
work
10 Ground Floor Grill and Chowkat fitting with
Electrical work
11 Sanitary work (vertical line)
12 Sanitary Internal wring 1st floor
13 Sanitary Internal wring 2nd floor
14 Sanitary Internal wring 3rd floor
15 Sanitary Internal wring Ground floor
16 Roof Top Sandwich Panel Installation
17 1st Floor Internal plaster work
18 2nd Floor Internal plaster work
19 3rd Floor Internal plaster work
20 Ground Floor Internal plaster work
21 Out side plaster work
22 1st Floor Tiles work
23 2nd Floor Tiles work
24 3rd Floor Tiles work
25 Ground Floor Tiles work
26 Stair Tiles work
27 Ground floor sowarice line complite work
28 Alluminium work
29 Paint work
30 Internal Door shutter fitting
31 Sanitary fixing work
32 Electrical fixing work
33 sub station Installation
34 Electrical Connection
35 Genarator connection
36 Final checking and cleaning
37 Hand over