ID Task Name (Weeks) Start date End Date /3 /3 /3 4 4
0 Activity schedule 26 12/3/2018 7/9/2018
1 Design Phase 24 12/3/2018 24/8/2018
2 A) Architectural 18 12/3/2018 13/7/2018
3 Schematic designs 4 12/3/2018 6/4/2018
4 Client approvaol 2 9/4/2018 20/4/2018
5 Designs development phase 4 23/4/2018 18/5/2018
6 Local authority/ Council approvals 4 21/5/2018 15/6/2018
7 Detail 8 21/5/2018 13/7/2018
8 B) Engineering 18 12/3/2018 13/7/2018
9 Feacibility studies (Soil investigations) 4 12/3/2018 6/4/2018
10 Structural designs 14 9/4/2018 13/7/2018
11 Concrete outlines 3 9/4/2018 27/4/2018
12 Detail Designs (RF designs) 11 30/4/2018 29/6/2018
13 Building services (E & M) 8 21/5/2018 13/7/2018
14 electrical 8 21/5/2018 13/7/2018
15 Mechanical 8 21/5/2018 13/7/2018
16 Plumbing 8 21/5/2018 13/7/2018
17 Contract documentation 6 21/5/2018 29/6/2018
18 Client approval 2 2/7/2018 13/7/2018
19 Bidding phase 8 16/7/2018 7/9/2018
20 Commencement of construction supervision 0 7/9/2018 7/9/2018
Week

16 23 30 7/ 14 21 28 4/ 11 18 25 2/ 9/ 16 23 30 6/ 13 20 27 3/
/4 /4 /4 5 /5 /5 /5 6 /6 /6 /6 7 7 /7 /7 /7 8 /8 /8 /8 9