Anda di halaman 1dari 4

Respected Sir,

This is to bring to your knowledge that as per the review meeting point number 17 held
on 12/01/17, the consideration for reward on achievement of target was discussed.

So, it is our utmost request to consider our nomination for reward at VMGO Site.

Please note the following details.

SR NO MONTH PLANNED AMOUNT IN RS ACHIEVED AMOUNT IN RS


1 JAN’17 4,07,00,180.00 4,11,41,775.00
2 FEB’17 4,50,30,161.00 4,33,77,998.00
3 MAR’17 2,28,62,759.00 2,39,69,865.00
TOTAL 10,85,93,100.00 10,84,89,638.00

Also please note that, the planning amount consisted of 1.5 Cr rupees of The tower A and Tower B which
were yet to be started at the time by which planning was given. Out of 1.5 Cr rupees hardly 0.35 Cr
rupees are claimed for the Tower A and Tower B, depicting the rest achievement from the remaining
five towers (Tower C, D, E, F, and G).

Hence we stand viable for our reward and our claim for the same stands justified.

Thank you.

ATCH:-Certified bill copies of RA-9, 10, 11 for the month of Jan, Feb, and Mar’17 respectively.