2B OPCO Procurement Plan

13-Feb-18
Procurement Package- URGENT DELIVERY
# Quantity Total Price (EURO) by Sea Total Price by Air (EURO) Air Freight Delivery Schedule (Weeks) by
Item Description Unit Rate (EURO) Delivery Schedule (Weeks) by Air
sea
1 Piping Matreial
1.1 90°-5D BEND BE, API 5L GR.B, SEAMLESS SCH STD SIZE 6Inch € 225.00 8 No's € 1,800.00 € 2,070.00 € 414.00 6 Weeks 9 Weeks
1.2 Pressure gauge, Dual Scale PSI& Bar with two way valve € 386.00 8 No's € 3,088.00 € 3,551.20 € 710.24 6 Weeks 9 Weeks
1.3 CORROSION COUPON HOLDER, SCRD. MNF'STD, Sch 80 SIZE 1Inch € 900.00 4 No's € 3,600.00 € 4,140.00 € 828.00 6 Weeks 9 Weeks
2 OGM's Extension Material € - € -
2.1 FLANGE, WN, RF, CS, A105N, 10", 300#, B 16.5, Sch 40 € 380.00 4 No's € 1,520.00 € 1,748.00 € 349.60 6 Weeks 9 Weeks
2.2 Gasket, Spiral Wound, SS304+Graphite filler, 4.5mm, 300#, 10". € 35.00 4 No's € 140.00 € 161.00 € 32.20 6 Weeks 9 Weeks
2.3 Stud with 2 Nuts, ASTM A193 GR.B7 / A194 GR.2H, 1", 170 Lg. € 7.50 96 No's € 720.00 € 828.00 € 165.60 6 Weeks 9 Weeks
3 600/1000V GRADE POWER CABLE € - € - 6 Weeks
3.1 4Cx50 mm2 € 7.41 680 MTR € 5,038.80 € 5,794.62 € 1,158.92 6 Weeks 8 Weeks
4 CONTROL CABLE € - € - 6 Weeks
4.1 1Cx2.5 mm2 RED € 50.00 397 MTR € 19,850.00 € 22,827.50 € 4,565.50 6 Weeks 8 Weeks
4.2 1Cx2.5 mm2 YELLOW € 50.00 400 MTR € 20,000.00 € 23,000.00 € 4,600.00 6 Weeks 8 Weeks
4.3 1Cx2.5 mm2 BLUE € 50.00 400 MTR € 20,000.00 € 23,000.00 € 4,600.00 6 Weeks 8 Weeks
5 Bulk Material ,CABLE GLANDING, LUGS € - € - 6 Weeks
5.1 Cable Ties (Suitable for 4Cx4 mm) € 95.00 8 Pkt € 760.00 € 874.00 € 174.80 6 Weeks 8 Weeks
5.2 Socket (230 V, 1 ph.IOA 3pin socket (indoor)) € 25.00 12 No's € 300.00 € 345.00 € 69.00 6 Weeks 8 Weeks
5.3 PVC cable protection tiles 1 Mtr length € 24.00 1600 No's € 38,400.00 € 44,160.00 € 8,832.00 6 Weeks 8 Weeks
5.4 Warning Tape (Danger LV Burred cable) € 3.00 1600 MTR € 4,800.00 € 5,520.00 € 1,104.00 6 Weeks 8 Weeks
5.5 Heat Shrinkable Tape € 200.00 80 MTR € 16,000.00 € 18,400.00 € 3,680.00 6 Weeks 8 Weeks
5.6 GI conduit pipe 25mm € 18.00 40 No's € 720.00 € 828.00 € 165.60 6 Weeks 8 Weeks
5.7 GI conduit 4ways - 25mm € 30.00 22 No's € 660.00 € 759.00 € 151.80 6 Weeks 8 Weeks
5.8 GI conduit normal Bends Thracted € 48.00 16 No's € 768.00 € 883.20 € 176.64 6 Weeks 8 Weeks
6 33KV TERMINATION KITS WITH THE REQUIRED NO OF LUGS EITHER 1CORE OR THREE CORES € - € -
6.1 1Cx70 mm2 33kV Cable Outdoor Termination for Transformer € 35.49 5 Sets € 177.45 € 204.07 € 40.81 6 Weeks 8 Weeks
7 EARTHING MATERIALS € - € - 6 Weeks
7.1 Earth electrodes - Copperbond rod 19 mm dia 2.5 meter long € 98.00 48 No's € 4,704.00 € 5,409.60 € 1,081.92 6 Weeks 8 Weeks
7.2 Two way Clamp € 42.00 33 No's € 1,386.00 € 1,593.90 € 318.78 6 Weeks 8 Weeks
7.3 COMPRESSION TERMINAL LUG, COPPER FOR 35 mm2 EARTH WIRE C/W NUT& BOLT € 87.00 70 No's € 6,090.00 € 7,003.50 € 1,400.70 6 Weeks 8 Weeks
8 LIGHTING SYSTEM - 2X36W FLUORESCENT FITTING FOR SUBSTATION € - € -
8.1 Decorative Type € 190.65 20 No's € 3,813.00 € 4,384.95 € 876.99 6 Weeks 8 Weeks
8.2 Emergency with Battery Backup (Decorative Type) € 255.40 7 No's € 1,787.80 € 2,055.97 € 411.19 6 Weeks 8 Weeks
8.3 Weather Proof Type € 312.92 4 No's € 1,251.68 € 1,439.43 € 287.89 6 Weeks 8 Weeks
8.4 Emergency with Battery Backup (Weather Proof Type) € 366.07 16 No's € 5,857.12 € 6,735.69 € 1,347.14 6 Weeks 8 Weeks
8.5 230V, 1PH. 10A, 3PIN SOCKET (DECORATIVE TYPE) € 35.00 3 No's € 105.00 € 120.75 € 24.15 6 Weeks 8 Weeks
8.6 One way lighting switch with PVC Box (indoor) € 18.00 16 No's € 288.00 € 331.20 € 66.24 6 Weeks 8 Weeks
8.7 High pressure Soduim vapour lamp - 250 W € 90.00 15 No's € 1,350.00 € 1,552.50 € 310.50 6 Weeks 8 Weeks
8.9 LIGHTING POLE TERMINALS WITH 3/FUSES IN THE LIGHTING POLE JUNCTION BOX. € 3,500.00 8 No's € 28,000.00 € 32,200.00 € 6,440.00 6 Weeks 8 Weeks
9 LIGHTING FIXTURES € - € -
9.1 Flood light 250W HPSV- Exn € 662.00 15 No's € 9,930.00 € 11,419.50 € 2,283.90 6 Weeks 8 Weeks
10 RUBBER MAT COVER RMU ROOM GROUND € - € - 6 Weeks
10.1 FOR 33 kV Ring Main Unit (RMU) € 3,400.00 3 Rolls € 10,200.00 € 11,730.00 € 2,346.00 6 Weeks 8 Weeks
10.2 FOR LV Distribution Board € 120.00 136 sq MTR € 16,320.00 € 18,768.00 € 3,753.60 6 Weeks 8 Weeks
11 CABLE TRAY € - € -
11.1 150mm wide ladder type Cable Tray with complete accessories € 45.00 32 MTR € 1,440.00 € 1,656.00 € 331.20 6 Weeks 8 Weeks

Total 2B OPCO Procurement Package Amount (EURO) € 230,864.85 € 265,494.58 € 53,098.92


Note:
Delivery depend on the timely payments
Payment shall be as per CONTRACT Currency and in our account outside Sudan