Material:  Ordinary  Portland  Cement

Item Element Component Calculation Total  

1 External  Wall Cement  mortar  (1:6)  in 1m2  half  brick  thick  wall  requires  0.07m3  of  mortar
half  brickwall 55m2  half  brick  thick  wall  requires  3.85m3  of  mortar
1m3  of  mortar  requires  (1/7)  x  1420kg  of  OPC
3.85m3  of  mortar  requires  781kg  of  OPC                          781

2 External  Wall Cement  mortar  (1:6)  in 1m2  one  brick  thick  wall  requires  0.15m3  of  mortar
one  brickwall 46m2  one  brick  thick  wall  requires  6.90m3  of  mortar
1m3  of  mortar  requires  (1/7)  x  1420kg  of  OPC
6.90m3  of  mortar  requires  1400kg  of  OPC                    1,400

3 Internal  Wall Cement  mortar  (1:6)  in   1m2  half  brick  thick  wall  requires  0.07m3  of  mortar
half  brickwall 78m2  half  brick  thick  wall  requires  5.46m3  of  mortar
1m3  of  mortar  requires  (1/7)  x  1420kg  of  OPC
5.46m3  of  mortar  requires  1108kg  of  OPC                    1,108

4 Internal  Wall  Finishes Cement  screed  (1:4) 20mm  of  95m2  of  backings  is  1.90m3  of  cement  screed
1m3  of  screed  requires  (1/5)  x  1420kg  of  OPC
1.90m3  of  screed  requires  540kg  of  OPC                          540

5 Internal  Wall  Finishes Cement  plaster  (1:4) 20mm  of  132m2  of  finish  is  2.64m3  of  plaster
1m3  of  plaster  requires  (1/5)  x  1420kg  of  OPC
2.64m3  of  plaster  requires  750kg  of  OPC                          750

6 Internal  Floor  Finishes Cement  paving  (1:3) 20mm  of  18m2  of  backings  is  0.36m3  of  cement  paving
1m3  of  screed  requires  (1/4)  x  1420kg  of  OPC
0.36m3  of  paving  requires  128kg  of  OPC                          128

7 Internal  Floor  Finishes Cement  screed  (1:3) 20mm  of  98m2  of  backings  is  1.96m3  of  cement  screed
1m3  of  screed  requires  (1/4)  x  1420kg  of  OPC
1.96m3  of  screed  requires  696kg  of  OPC                          696

8 External  Finishes Cement  plaster  (1:4)  to   20mm  of  91m2  of  finish  is  1.82m3  of  plaster
wall 1m3  of  plaster  requires  (1/5)  x  1420kg  of  OPC
1.82m3  of  plaster  requires  517kg  of  OPC                          517

9 External  Finishes Cement  screed  (1:4)  to   20mm  of  18m2  of  backings  is  0.36m3  of  cement  screed
floor 1m3  of  screed  requires  (1/5)  x  1420kg  of  OPC
0.36m3  of  screed  requires  103kg  of  OPC                          103

TOTAL  (kg)                      6,023


Material:  Sand
Item Element Component Calculation Total  

1 External  Wall Cement  mortar  (1:6)  in 1m2  half  brick  thick  wall  requires  0.07m3  of  mortar
half  brickwall 55m2  half  brick  thick  wall  requires  3.85m3  of  mortar
1m3  of  mortar  requires  (6/7)  x  1600kg  of  sand
3.85m3  of  mortar  requires  5280kg  of  sand                    5,280

10 External  Wall Cement  mortar  (1:6)  in 1m2  one  brick  thick  wall  requires  0.15m3  of  mortar
one  brickwall 46m2  one  brick  thick  wall  requires  6.90m3  of  mortar
1m3  of  mortar  requires  (6/7)  x  1600kg  of  sand
6.90m3  of  mortar  requires  9463kg  of  sand                    9,463

11 Internal  Wall Cement  mortar  (1:6)  in   1m2  half  brick  thick  wall  requires  0.07m3  of  mortar
half  brickwall 78m2  half  brick  thick  wall  requires  5.46m3  of  mortar
1m3  of  mortar  requires  (6/7)  x  1600kg  of  sand
5.46m3  of  mortar  requires  7488kg  of  sand                    7,488

12 Internal  Wall  Finishes Cement  screed  (1:4) 20mm  of  95m2  of  backings  is  1.90m3  of  cement  screed
1m3  of  screed  requires  (4/5)  x  1600kg  of  sand
1.90m3  of  screed  requires  2432kg  of  sand                    2,432

13 Internal  Wall  Finishes Cement  plaster  (1:4) 20mm  of  132m2  of  finish  is  2.64m3  of  plaster
1m3  of  plaster  requires  (4/5)  x  1600kg  of  sand
2.64m3  of  plaster  requires  3380kg  of  sand                    3,380

14 Internal  Floor  Finishes Cement  paving  (1:3) 20mm  of  18m2  of  backings  is  0.36m3  of  cement  paving
1m3  of  screed  requires  (3/4)  x  1600kg  of  sand
0.36m3  of  paving  requires  432kg  of  sand                          432

15 Internal  Floor  Finishes Cement  screed  (1:3) 20mm  of  98m2  of  backings  is  1.96m3  of  cement  screed
1m3  of  screed  requires  (3/4)  x  1600kg  of  sand
1.96m3  of  screed  requires  2352kg  of  sand                    2,352

16 External  Finishes Cement  plaster  (1:4)  to   20mm  of  91m2  of  finish  is  1.82m3  of  plaster
wall 1m3  of  plaster  requires  (4/5)  x  1600kg  of  sand
1.82m3  of  plaster  requires  2330kg  of  sand                    2,330

17 External  Finishes Cement  screed  (1:4)  to   20mm  of  18m2  of  backings  is  0.36m3  of  cement  screed
floor 1m3  of  screed  requires  (4/5)  x  1600kg  of  sand
0.36m3  of  screed  requires  461kg  of  sand                          461

TOTAL  (kg)                  33,618

Material:  Ready  Mix  Concrete  Grade  25


Item Element Component Calculation  Total    

1 Work  Below  Lowest   Reinforced  concrete Pad  footing                                    1


Floor  Finish work Column  stump                                    1
Ground  beam                                  4

2 Frame Reinforced  concrete Beam                                    6


work

TOTAL  (m3)                                12


Material:  6mm  diameter  mild  steel  rebar
Item Element Component Calculation  Total    

1 External  Wall Bonding  ties 162  nos  of  450mm  bonding  ties                              73

2 Internal  Wall Bonding  ties 36  nos  of  450mm  bonding  ties                              16

TOTAL  (m)                                89

Material:  8mm  diameter  mild  steel  rebar


Item Element Component Calculation  Total    

1 Work  Below  Lowest   Mild  steel  rebar In  column  stump                              34


Floor  Finish In  ground  beam                          116

2 Frame Mild  steel  rebar In  column                              76


In  beam                              73

TOTAL  (kg)                            299


Material:  10mm  diameter  mild  steel  rebar
Item Element Component Calculation  Total    

1 Work  Below  Lowest   Mild  steel  rebar In  pad  footing                                  7


Floor  Finish In  ground  beam                          101

2 Frame Mild  steel  rebar In  beam                          100

TOTAL  (kg)                            208

Material:  10mm  diameter  high  tensile  rebar


Item Element Component Calculation  Total    

1 Work  Below  Lowest   High  tensile  rebar In  ground  beam                          300


Floor  Finish

2 Frame High  tensile  rebar In  beam                          250

TOTAL  (kg)                            550

Material:  12mm  diameter  high  tensile  rebar


Item Element Component Calculation  Total    

1 Work  Below  Lowest   High  tensile  rebar In  pad  footing                              17


Floor  Finish In  column  stumps                              90
In  ground  beam                          349

2 Frame High  tensile  rebar In  column                          208


In  beam                          270

TOTAL  (kg)                            934

Material:  16mm  diameter  high  tensile  rebar


Item Element Component Calculation  Total    

1 Work  Below  Lowest   High  tensile  rebar In  pad  footing                              20


Floor  Finish In  column  stumps                          100

2 Frame High  tensile  rebar In  column                          222

TOTAL  (kg)                            342


Material:  Cement  and  sand  bricks
Item Element Component Calculation  Total    

1 External  Wall Half  brickwall 1m2  of  brickwall  requires  59  pieces  of  bricks
55m2  of  brickwall  requires  3245  pieces  of  bricks                    3,245

2 External  Wall One  brickwall 1m2  of  brickwall  requires  118  pieces  of  bricks
46m2  of  brickwall  requires  5428  pieces  of  bricks                    5,428

3 Internal  Wall Half  brickwall 1m2  of  brickwall  requires  59  pieces  of  bricks
78m2  of  brickwall  requires  4602  pieces  of  bricks                    4,602

TOTAL  (nos)                  13,275

Material:  Exmet
Item Element Component Calculation  Total    

1 External  Wall Half  brickwall 10  nos  of  exmet  required  at  3m  high  wall
18.33m  long  wall  requires  184m  of  exmet                          184

2 External  Wall One  brickwall 10  nos  of  exmet  required  at  3m  high  wall
15.33m  long  wall  requires  154m  of  exmet                          154

3 Internal  Wall Half  brickwall 10  nos  of  exmet  required  at  3m  high  wall
26.00m  long  wall  requires  260m  of  exmet                          260

TOTAL  (m)                            598

Material:  Damp  proof  course  (6.1m  x  1m)


Item Element Component Calculation  Total    

1 External  Wall Half  brickwall 115mm  wide                              24

2 External  Wall One  brickwall 225mm  wide                              22

3 Internal  Wall Half  brickwall 115mm  wide                              26

TOTAL  (m)                                72


Material:  Dulux  Interior  Basecoat  Sealer
Item Element Component Calculation Total  

1 Internal  Wall  Finishes Painting 100m2  requires  10  litres  of  paint
132m2  requires  13.2  litres  of  paint                        13.2

2 Internal  Ceiling  Finishes Painting 100m2  requires  10  litres  of  paint
104m2  requires  10.4  litres  of  paint                        10.4

3 External  Finishes Painting  to  wall 100m2  requires  10  litres  of  paint
91m2  requires  9.1  litres  of  paint                            9.1

4 External  Finishes Painting  to  soffit 100m2  requires  10  litres  of  paint
36m2  requires  3.6  litres  of  paint                            3.6

TOTAL  (litres)                                36

Material:  Dulux  ICI  Maxilite  Trade  Emulsion  Paint


Item Element Component Calculation Total  

1 Internal  Wall  Finishes Painting 100m2  requires  9.52  litres  of  paint
132m2  requires  12.57  litres  of  paint
2  coats  requires  25.14  litres  of  paint                        25.1

2 Internal  Ceiling  Finishes Painting 100m2  requires  9.52  litres  of  paint
104m2  requires  9.90  litres  of  paint
2  coats  requires  19.80  litres  of  paint                        19.8

3 External  Finishes Painting  to  wall 100m2  requires  9.52  litres  of  paint
91m2  requires  8.66  litres  of  paint
2  coats  requires  17.33  litres  of  paint                        17.3

4 External  Finishes Painting  to  soffit 100m2  requires  9.52  litres  of  paint
36m2  requires  3.43  litres  of  paint
2  coats  requires  6.85  litres  of  paint                            6.9

TOTAL  (m2)                                69